Monthly State Let Construction Report For Wichita Falls District As Of Mar 13, 2024 Page 1 Of 2

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromWAGONSELLER RD
To0.25 MI S OF SS 511
CSJ0013-05-065
Proj IDSTP 2B23(131)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2243728.65851120.2237.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began11-20-23
Work Completed
Time Computed00-00-00
Contract Working Days193
Addl Days Granted0
Working Days Charged21
Percent Time Used10
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-065
FC TRAFFIC CONTROL, INC. (0.99)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.11)
Contract #08233239
Totals2243728.6574509.62851120.2237.9

CountyWILBARGER
HighwayUS 287
FromUS 287 SB
ToAT PEASE RIVER RELIEF
CSJ0043-05-112
Proj IDF 2023(621)
Work TypeBRIDGE REPLACEMENT
 
3023404.301907555.3963.0
CountyWILBARGER
HighwayFM 392
FromFM 392
ToAT DRAW
CSJ0832-02-032
Proj IDF 2023(621)
Work TypeBRIDGE REPLACEMENT
 
859516.75566954.2365.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-23
Work Began07-10-23
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted8
Working Days Charged133
Percent Time Used61
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-112
FOUTSCO PAVING COMPANY, LLC (13.45)
TEXOP CONSTRUCTION (0.80)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.20)
BARRICADES UNLIMITED (0.81)
TRP CONSTRUCTION GROUP, LLC (0.35)
PENHALL COMPANY (0.18)
LANCO TURF & SEEDING, INC. (0.95)
TORO BRAVO CONSTRUCTION, LLC (0.39)
Contract #04233221
Totals3882921.05323364.232474509.6263.7

CountyWICHITA
HighwayUS 287
FromHARMONY RD
ToQUAIL VALLEY RD
CSJ0043-08-088
Proj IDSTP 2024(778)TP
Work TypeRESTORATION
 
5428567.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243018
Totals5428567.960.000.000.0

CountyWICHITA
HighwayBU 287J
FromFM 368
ToSL 11
CSJ0043-17-031
Proj IDF 2023(458)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9919386786.812008921.6221.4
Work Order06-22-23
Work Began07-31-23
Work Completed
Time Computed07-24-23
Contract Working Days200
Addl Days Granted0
Working Days Charged125
Percent Time Used62
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-031
W. S. CONSTRUCTION COMPANY (21.59)
FC TRAFFIC CONTROL, INC. (0.32)
HJC FARMS, INC. (3.84)
TRP CONSTRUCTION GROUP, LLC (1.90)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.60)
DUSTROL, INC. (0.04)
Contract #02233211
Totals9386786.81244749.662008921.6221.4

CountyWICHITA ETC
HighwayUS 82 ETC
FromWINDTHORST RD
ToFISHER RD (INTERCHANGE AREA FR/RAMPS)
CSJ0044-01-110
Proj IDF 2024(337)
Work TypeSEAL COAT
 
11122261.60254266.272.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-110
BARRICADES PLUS, LLC (1.60)
CENTERLINE TECHNOLOGIES, LLC (17.37)
Contract #11233205
Totals11122261.60254266.27254266.272.2

CountyMONTAGUE
HighwayUS 82
FromSH 175 / MONTAGUE STREET
ToNEAR FM 1816
CSJ0044-04-047
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
6.10027683391.0525070419.7490.5
CountyMONTAGUE
HighwayUS 82
From0.5 MI EAST OF US 81
ToNEAR FM 1816
CSJ0044-04-049
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
5.82920779023.0415489330.0074.5
Work Order08-19-21
Work Began10-25-21
Work Completed
Time Computed09-20-21
Contract Working Days719
Addl Days Granted0
Working Days Charged532
Percent Time Used73
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-047
STRAIGHT LINE SAWING & SEALING, INC. (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.03)
JR WEST TEXAS CONCRETE LLC (3.18)
AREA WIDE PROTECTIVE, INC. (0.25)
DUSTROL, INC. (0.25)
HAMMETT EXCAVATION, INC. (24.22)
STRIPING TECHNOLOGY, L.P. (0.97)
TEXAS SHAFTS, INC. (0.86)
L&H ELECTRICAL, LLC (0.70)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.84)
WITHERS CONSTRUCTION, LLC (0.86)
HERMANOS STEEL, LLC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.15)
FARR FOUNDATION, INC. (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC (0.92)
DUSTIN ALLEN, INC. (0.28)
SOUTHEAST GRINDING AND GROOVING LLC (0.02)
RAMBO CONTRACTING, INC. (0.19)
PANIOLO CONSTRUCTION SERVICES, LLC (0.06)
Contract #07213001
Totals48462414.09780577.5940559749.7483.6

CountyCOOKE
HighwayFM 1199
FromFM 3108
ToUS 82
CSJ0044-09-067
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1043643.15991264.6099.9
CountyCOOKE
HighwayFM 3108
FromFM 1199
ToFM 1630
CSJ3192-01-007
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2775494.462633897.1594.8
CountyCOOKE
HighwayFM 3108
FromFM 3108
ToAT ELM FORK TRINITY RIVER
CSJ3192-01-008
Proj IDBR 2021(706)
Work TypeBRIDGE REPLACEMENT
 
1208335.371218622.0399.9
Work Order08-18-21
Work Began12-07-21
Work Completed
Time Computed09-17-21
Contract Working Days238
Addl Days Granted5
Working Days Charged350
Percent Time Used144
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-09-067
JOE"S TREE SERVICE (0.76)
DUSTROL, INC. (1.29)
TEXAS SHAFTS, INC. (1.73)
BARRICADES UNLIMITED (2.23)
SOUTHERN CROSS CONTRACTORS, LLC (2.33)
RAMBO CONTRACTING, INC. (6.03)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.46)
PINNACLE GRINDING AND GROOVING LLC (0.00)
BRENDA PRICE TRUCKING (1.36)
GARRET SHIELDS INFRASTRUCTURE (2.70)
PROFESSIONAL TRAFFIC CONTROL LLC (0.13)
Contract #07213211
Totals5027472.980.004843783.7898.7

CountyWILBARGER
HighwayUS 283
FromRED RIVER
ToFM 924
CSJ0124-02-033
Proj IDF 2023(092)
Work TypeOVERLAY
 
6216761.986057796.9697.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began10-26-23
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted7
Working Days Charged79
Percent Time Used116
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0124-02-033
TRP CONSTRUCTION GROUP, LLC (2.61)
BARRICADES UNLIMITED (1.42)
HJC FARMS, INC. (0.81)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.30)
WEST TEXAS ROCK RESOURCES, LLC (0.62)
Contract #09223026
Totals6216761.982235656.746057796.9697.6

CountyWILBARGER
HighwayUS 183
From0.992 MI S OF FM 1763
ToBAYLOR COUNTY LINE
CSJ0124-04-038
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.68010036994.0010115388.4699.9
CountyBAYLOR
HighwayUS 183
FromWILBARGER CL
To5.737 MI N OF US 82
CSJ0124-05-025
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.2505079547.734657870.2691.6
Work Order11-19-20
Work Began01-21-21
Work Completed
Time Computed12-19-20
Contract Working Days359
Addl Days Granted11
Working Days Charged584
Percent Time Used157
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-038
BARRICADES UNLIMITED (1.89)
FC TRAFFIC CONTROL, INC. (0.22)
MARCOM"S MOWING SERVICE, LLC (0.28)
W. S. CONSTRUCTION COMPANY (9.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.41)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
ZACK BURKETT CO. (36.83)
Contract #10203205
Totals15116541.7317365.0014773258.7299.5

CountyBAYLOR
HighwayUS 183
FromUS 277
ToTHROCKMORTON CL
CSJ0125-01-034
Proj IDF 2023(090)
Work TypeREHABILITATION OF EXISTING ROAD
 
7724536.692646477.7834.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began04-17-23
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged144
Percent Time Used68
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0125-01-034
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.99)
CHEROKEE SERVICES (0.23)
CONTRACTORS SERVICE, LTD. (0.77)
HJC FARMS, INC. (2.00)
JR WEST TEXAS CONCRETE LLC (2.15)
LANCO TURF & SEEDING, INC. (2.91)
Contract #09223234
Totals7724536.69327098.152646477.7834.2

CountyBAYLOR
HighwayUS 82
FromKNOX COUNTY LINE
ToBU 183B
CSJ0133-04-042
Proj IDF 2022(303)
Work TypeSUPER-2 HIGHWAY
 
12.57915938381.2612622309.5979.2
Work Order01-05-22
Work Began03-21-22
Work Completed
Time Computed02-04-22
Contract Working Days377
Addl Days Granted46
Working Days Charged425
Percent Time Used100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-04-042
DUSTIN ALLEN, INC. (0.42)
MARCOM"S MOWING SERVICE, LLC (0.75)
TRP CONSTRUCTION GROUP, LLC (1.11)
W. S. CONSTRUCTION COMPANY (12.80)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.49)
CONTRACTORS SERVICE, LTD. (0.56)
Contract #12213023
Totals15938381.262232531.9412622309.5979.2

CountyCLAY
HighwayFM 174
FromFM 3077
ToFM 1288 SOUTH
CSJ0137-10-026
Proj IDSTP 2023(471)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4129054.654679617.4699.9
CountyCLAY
HighwayFM 174
FromFM 1288 SOUTH
ToFM 1288 NORTH
CSJ0681-08-027
Proj IDSTP 2023(471)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
428254.20400925.0593.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-23
Work Began05-30-23
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged103
Percent Time Used55
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0137-10-026
JR WEST TEXAS CONCRETE LLC (12.53)
J. H. ODEN CONTRACTING COMPANY (1.96)
TRP CONSTRUCTION GROUP, LLC (1.26)
MARCOMS CONSTRUCTION LLC (1.07)
HJC FARMS, INC. (0.90)
TEXAS TRAFFIC AND BARRICADE, LLC (0.38)
WEST TEXAS ROCK RESOURCES, LLC (0.23)
Contract #03233013
Totals4557308.8517000.005080542.5199.9

CountyWILBARGER
HighwayUS 70
FromSL 488
ToBU 287F
CSJ0146-07-033
Proj IDF 2023(460)
Work TypeRESTORATION
 
2143240.001455457.1467.9
Work Order03-06-23
Work Began07-24-23
Work Completed
Time Computed04-05-23
Contract Working Days122
Addl Days Granted39
Working Days Charged122
Percent Time Used75
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0146-07-033
DIIBS SPECIALISTS, LLC (12.53)
LINEAR TRAFFIC MARKINGS LLC (0.89)
Contract #02233024
Totals2143240.00290979.731455457.1467.9

CountyWICHITA
HighwaySH 240
FromIH 44
ToNEAR ROBINSON ROAD
CSJ0156-02-033
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
701607.84925854.4899.9
CountyWICHITA
HighwaySH 240
FromNEAR ROBINSON ROAD
To2ND STREET
CSJ0156-03-049
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1128031.001653445.7099.9
Work Order08-25-21
Work Began07-11-22
Work Completed
Time Computed09-24-21
Contract Working Days152
Addl Days Granted94
Working Days Charged246
Percent Time Used100
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-02-033
GARRET SHIELDS INFRASTRUCTURE (103.09)
WEST TEXAS ROCK RESOURCES, LLC (0.72)
WG ENGINEERING & CONSTRUCTION, LLC (16.02)
STRIPE-A-ZONE, LLC (6.13)
MEDELLIN HDD LLC (0.39)
ARBOR RESOURCES, LLC (1.55)
LINEAR TRAFFIC MARKINGS LLC (5.92)
WATTS ENTERPRISES, LLC (0.59)
BROTHERS RDC PAVING, LLC (1.55)
Contract #07213019
Totals1829638.840.002579300.1899.9

CountyWICHITA
HighwayUS 82 ETC
FromUS 82 EB (KELL)
ToAT KEMP BLVD
CSJ0156-04-120
Proj IDBR 2024(686)
Work TypeBRIDGE MAINTENANCE
 
1.9962856132.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days442
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TALBERT COMPANIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-04-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243229
Totals2856132.080.000.000.0

CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-119
Proj IDNH 2021(327)
Work TypeWIDEN FREEWAY
 
7.900208432431.14113490087.9853.9
CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-120
Proj IDROW 0195-1-120
Work TypeRIGHT OF WAY
 
7.9001566682.221560325.7299.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-21
Work Began06-21-21
Work Completed
Time Computed00-00-00
Contract Working Days1,395
Addl Days Granted0
Working Days Charged785
Percent Time Used56
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-119
DOUBLE EE CONTRACTORS, LLC (0.01)
BARRICADES UNLIMITED (0.67)
ANTIGO CONSTRUCTION, INC. (0.24)
SOUTHERN CROSS CONTRACTORS, LLC (0.05)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.10)
FORTSON CONTRACTING, INC. (0.58)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.43)
SCOTT DERR PAINTING CO, LLC (0.06)
W.O.E. CONSTRUCTION, INC. (2.24)
TEXAS SHAFTS, INC. (0.67)
OSCAR ORDUNO, INC. (1.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.27)
MONARREZ TRUCKING LLC. (0.00)
DALE BROWN, INC. (0.13)
TIME STRIPING, INC. (0.05)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.17)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
WITHERS CONSTRUCTION, LLC (0.00)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
VENUS CONSTRUCTION COMPANY (0.78)
RAY"S THREADING AND FAB SHOP (0.62)
SKAGGS ROAD BORING, INC. (0.15)
HERMANOS STEEL, LLC (0.04)
ZACHRY CONSTRUCTION CORPORATION (0.00)
KHONSU ENTERPRISE LLC (0.36)
H & H CONCRETE ON DEMAND INC (0.56)
TORO BRAVO CONSTRUCTION, LLC (6.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
POTERE CONSTRUCTION LLC (0.68)
A.E.A. TRANSPORTATION (0.00)
TIM ANTHONY SERVICES, LLC (0.00)
MCRYAN HAULING, INC. (0.00)
TRP CONSTRUCTION GROUP, LLC (0.61)
SLATON BROS, INC. (0.23)
PRESLEY LAND MANAGEMENT LLC (0.00)
DDM MATERIALS, INC. (0.00)
ALLIED DRILLING COMPANY (0.01)
SOUTHEAST GRINDING AND GROOVING LLC (0.01)
Contract #02213201
Totals209999113.361667217.41115050413.7054.2

CountyCLAY
HighwayUS 287
FromSH 148
ToNEAR NEW LONDON RD (NB AND SB)
CSJ0224-01-062
Proj IDF 2023(805)
Work TypeOVERLAY
 
2393785.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0224-01-062
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.66)
HJC FARMS, INC. (4.68)
TRP CONSTRUCTION GROUP, LLC (1.44)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.37)
Contract #05233056
Totals2393785.600.000.000.0

CountyCLAY
HighwayUS 287
FromNEAR LONE STAR ROAD
ToMONTAGUE COUNTY LINE
CSJ0224-02-052
Proj IDC 224-2-52
Work TypeOVERLAY
 
5372832.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0224-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243216
Totals5372832.450.000.000.0

CountyCLAY
HighwaySH 79
FromFM 171 (SOUTH)
ToRED RIVER RELIEF STRUCTURE
CSJ0282-02-031
Proj IDF 2023(806)
Work TypeOVERLAY
 
3246126.19122542.323.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-23
Work Began09-18-23
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged10
Percent Time Used16
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0282-02-031
TRP CONSTRUCTION GROUP, LLC (2.22)
HJC FARMS, INC. (1.20)
LANCO TURF & SEEDING, INC. (0.23)
BARRICADES UNLIMITED (0.22)
Contract #05233057
Totals3246126.190.00122542.323.7

CountyCLAY
HighwaySH 79
FromAPPROX 1 MILE NORTH OF FM 2393
ToSH 148
CSJ0282-03-031
Proj IDF 2023(794)
Work TypeOVERLAY
 
4472468.251270055.0928.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-23
Work Began08-14-23
Work Completed
Time Computed00-00-00
Contract Working Days127
Addl Days Granted0
Working Days Charged123
Percent Time Used96
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0282-03-031
JR WEST TEXAS CONCRETE LLC (15.21)
HJC FARMS, INC. (3.23)
TRP CONSTRUCTION GROUP, LLC (1.61)
FC TRAFFIC CONTROL, INC. (0.36)
LANCO TURF & SEEDING, INC. (0.41)
Contract #05233021
Totals4472468.25282548.011270055.0928.3

page 1 | page 2