Monthly State Let Construction Report For Wichita Falls District As Of Jun 10, 2015 Page 1 Of 3

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWICHITA
Highway IH 44 ETC
From MAURINE STREET
To SP 325 (EAST FRONTAGE ROAD)
CSJ 0043-09-121
Proj ID IM 0448(016)
Work Type SEAL COAT
 
140.976 5404266.01 0.00 5583675.09 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 04-22-14
Work Completed 09-29-14
Time Computed 01-22-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 106
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-121
FLAT LINE, INC.( 20.68%)
RED SIXTEEN CONSTRUCTION, INC. (2.55%)
Contract # 10133222
Totals 5404266.01 0.00 5583675.09 100.0

CountyWICHITA
Highway US 287
From AT HUNTINGTON ROAD
To .
CSJ 0043-09-122
Proj ID BR 2015(600)
Work Type BRIDGE REPLACEMENT
 
0.410 2426317.29 0.00 0.00 0.0
Work Order 03-30-15
Work Began 00-00-00
Work Completed  
Time Computed 04-15-15
Contract Working Days 178
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-122
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.95%)
MCL CONTRACTING, LLC (0.13%)
DUSTROL, INC.(1.80%)
ZACK BURKETT CO. ( 15.67%)
LANCO TURF & SEEDING, INC. (1.35%)
DUSTIN ALLEN, INC. (2.65%)
Contract # 02153228
Totals 2426317.29 0.00 0.00 0.0

CountyWICHITA
Highway IH 44
From NEAR SP 325/US 287 INTERSECTION
To NEAR WICHITA RIVER
CSJ 0043-09-123
Proj ID NH 1502(062)
Work Type RESTORATION
 
2.548 1634013.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-12-15
Work Began 00-00-00
Work Completed  
Time Computed 06-12-15
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153053
Totals 1634013.82 0.00 0.00 0.0

CountyWICHITA
Highway BU 287J
From CITY VIEW DRIVE
To IH 44 ON RAMP
CSJ 0043-17-028
Proj ID NH 2015(401)
Work Type OVERLALY
 
2.197 802018.50 0.00 0.00 0.0
CountyWILBARGER
Highway US 283
From FM 924
To FM 925
CSJ 0124-02-031
Proj ID STP 2015(402)
Work Type OVERLAY
 
7.129 1711461.76 0.00 0.00 0.0
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 12
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-028
COTHRAN TRUCKING, LLC(0.71%)
COWBELL TRAFFIC SERVICE, INC.(0.78%)
STRIPE-A-ZONE, INC.(3.58%)
CONTRACTORS SERVICE COMPANY(0.19%)
TEXOP CONSTRUCTION (2.11%)
Contract # 12143029
Totals 2513480.26 0.00 0.00 0.0

CountyWICHITA
Highway US 82
From GALVESTON STREET
To MCKINNEY ROAD
CSJ 0044-01-098
Proj ID NH 1302(019)
Work Type OVERLAY
 
2.705 1769278.83 3338.06 2157305.02 100.0
Work Order 08-12-13
Work Began 10-08-13
Work Completed 12-12-14
Time Computed 08-28-13
Contract Working Days 30
Addl Days Granted 2
Working Days Charged 53
Percent Time Used 165
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-098
COTHRAN TRUCKING, LLC(1.44%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.14%)
O. TREVINO CONSTRUCTION, LLC (3.49%)
WEST TEXAS RUMBLE STRIP(0.23%)
TEX OP CONSTRUCTION, LP(6.78%)
CROSSROADS, L.P. (0.48%)
Contract # 07133248
Totals 1769278.83 3338.06 2157305.02 100.0

CountyCLAY
Highway US 82
From EAST CITY LIMITS OF HENRIETTA
To MONTAGUE COUNTY LINE
CSJ 0044-03-047
Proj ID NH 2013(784)
Work Type REHABILITATION OF EXISTING ROAD
 
12.888 5114930.10 0.00 1790604.61 35.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 12-18-13
Work Completed  
Time Computed 08-30-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 123
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-03-047
W.S. CONSTRUCTION COMPANY(4.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
COTHRAN TRUCKING, LLC(0.16%)
Contract # 05133021
Totals 5114930.10 0.00 1790604.61 35.9

CountyMONTAGUE
Highway US 82
From AT UP RR, 0.8 MI WEST OF US 81
To NEAR RINGGOLD
CSJ 0044-04-044
Proj ID STP 1102(216)RGS
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.589 6249421.47 18150.00 6498155.92 100.0
Work Order 09-06-11
Work Began 01-03-12
Work Completed 03-06-15
Time Computed 11-05-11
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 95
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-044
TEXAS SHAFTS, INC. (2.66%)
NORTH TEXAS REBAR, LLC (0.31%)
CONCRETE CUTTING BY BOND (0.11%)
JM MATERIALS, INC. (0.14%)
PEACHTREE CONSTRUCTION, LTD. (0.53%)
TRAC-WORK, INC.( 10.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.32%)
MOBILE ENTERPRISES, INC. (1.39%)
ERWIN STEEL WORKS, LLC (0.52%)
ODUM SERVICES, L.P.(0.28%)
NORTH TEXAS CONTRACTING, INC.(7.92%)
AR DANIEL SERVICES (0.91%)
J. E. GUZMAN CONSTRUCTION, INC.(0.26%)
MAXIM CRANE WORKS(0.12%)
LINDAMOOD DEMOLITION, INC. (0.60%)
Contract # 08113202
Totals 6249421.47 18150.00 6498155.92 100.0

CountyMONTAGUE
Highway US 82
From NEAR THE EAST CITY LIMITS OF NOCONA
To FM 1815 (EB & WB LANES)
CSJ 0044-06-071
Proj ID NH 2014(270)
Work Type OVERLAY
 
11.428 4997746.20 0.00 4906703.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 07-09-14
Work Completed 04-30-15
Time Computed 03-18-14
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 96
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-071
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
CROSSROADS, L.P. (0.37%)
DUSTROL, INC.(1.66%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.69%)
HJC FARMS, INC.(0.96%)
Contract # 12133219
Totals 4997746.20 0.00 4906703.57 100.0

CountyMONTAGUE
Highway US 82
From SAINT JO
To COOKE COUNTY LINE
CSJ 0044-06-073
Proj ID NH 2015(691)
Work Type OVERLAY
 
8.118 3960785.97 0.00 0.00 0.0
Work Order 04-07-15
Work Began 00-00-00
Work Completed  
Time Computed 04-23-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153221
Totals 3960785.97 0.00 0.00 0.0

CountyCOOKE
Highway US 82
From ASH STREET
To MAPLE STREET
CSJ 0044-07-068
Proj ID NH 2015(469)
Work Type LANDSCAPE
 
0.302 145746.35 40377.70 40377.70 27.7
Work Order 02-26-15
Work Began 04-28-15
Work Completed  
Time Computed 03-14-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 6
Contractor(s)
BEVERLY SUE GLOBAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-07-068
PARKER ELECTRIC(8.39%)
MHB CONSTRUCTION, INC. ( 54.79%)
Contract # 01153203
Totals 145746.35 40377.70 40377.70 27.7

CountyCOOKE
Highway US 82
From NEAR WEBER DRIVE
To NEAR IH 35
CSJ 0044-08-066
Proj ID NH 2013(625)
Work Type MISCELLANEOUS CONSTRUCTION
 
6.004 619413.20 0.00 636382.46 99.9
Work Order 02-18-14
Work Began 06-16-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 61
Addl Days Granted 11
Working Days Charged 71
Percent Time Used 98
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-066
LIRA ELECTRIC( 43.71%)
DUSTROL, INC.(5.81%)
STRAIGHT LINE SAWING & SEALING (1.21%)
STRIPING TECHNOLOGY, L.P.(3.12%)
FORTSON CONTRACTING, INC.(1.40%)
Contract # 11133208
Totals 619413.20 0.00 636382.46 99.9

CountyCOOKE
Highway US 82
From FM 1199 SOUTH
To NEAR IH 35
CSJ 0044-08-068
Proj ID NH 2015(403)
Work Type OVERLAY
 
3.876 1673272.77 0.00 0.00 0.0
Work Order 01-07-15
Work Began 00-00-00
Work Completed  
Time Computed 01-23-15
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143209
Totals 1673272.77 0.00 0.00 0.0

CountyBAYLOR
Highway SH 114 ETC
From US 183
To NEAR FM 1285
CSJ 0133-05-026
Proj ID NH 2015(232)
Work Type SEAL COAT
 
147.201 6495189.51 0.00 34704.26 0.5
Work Order 11-17-14
Work Began 00-00-00
Work Completed  
Time Computed 12-03-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0133-05-026
VIZCAINO, L.P. ( 19.43%)
FLASHER EQUIPMENT COMPANY(1.26%)
Contract # 10143220
Totals 6495189.51 0.00 34704.26 0.5

CountyWICHITA
Highway SH 25 ETC
From US 287
To BU 287H
CSJ 0137-02-027
Proj ID STP 2015(404)
Work Type OVERLAY
 
5.439 1612714.61 0.00 0.00 0.0
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0137-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143229
Totals 1612714.61 0.00 0.00 0.0

CountyCLAY
Highway FM 174
From FM 1288 NORTH
To MONTAGUE COUNTY LINE
CSJ 0137-11-009
Proj ID STP 2015(306)
Work Type REHABILITATION OF EXISTING ROADWAY
 
9.033 3000739.79 25125.00 196767.27 6.5
Work Order 01-05-15
Work Began 04-06-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 4
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0137-11-009
MARCOM"S MOWING SERVICE, LLC (0.87%)
LANCO TURF & SEEDING, INC. (1.24%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.74%)
ALTUS TRAFFIC MANAGEMENT LLC (0.40%)
W.S. CONSTRUCTION COMPANY(9.46%)
Contract # 11143008
Totals 3000739.79 25125.00 196767.27 6.5

CountyWILBARGER
Highway US 70
From US 70 AT THE RED RIVER
To .
CSJ 0147-02-008
Proj ID BR 1502(346)
Work Type BRIDGE MAINTENANCE
 
1.136 769343.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0147-02-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153259
Totals 769343.00 0.00 0.00 0.0

CountyWICHITA
Highway SH 240
From AT SINCLAIR ROAD DRAIN
To .
CSJ 0156-03-046
Proj ID BR 2015(693)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.021 320260.00 0.00 0.00 0.0
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 05-06-15
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153229
Totals 320260.00 0.00 0.00 0.0

CountyARCHER
Highway US 277
From 1.69 MILES WEST OF FM 368
To 0.795 MILES EAST OF FERGUSON ROAD
CSJ 0156-05-048
Proj ID NH 2013(621)
Work Type WIDEN NON - FREEWAY
 
9.154 16393546.60 181471.67 10004139.71 61.0
Work Order 11-08-13
Work Began 01-17-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 330
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 56
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-048
W.S. CONSTRUCTION COMPANY(7.45%)
ATCI ELECTRICAL(1.94%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.73%)
TEXAS ALTERNATIVE GRASSER, INC.(0.56%)
BARRICADES UNLIMITED (1.19%)
CONTRACTORS SERVICE COMPANY(0.25%)
WEST TEXAS RUMBLE STRIP(0.07%)
TEX OP CONSTRUCTION, LP(0.33%)
HJC FARMS, INC.(0.74%)
LONGHORN MULCHING, INC.(0.34%)
Contract # 08133210
Totals 16393546.60 181471.67 10004139.71 61.0

CountyARCHER
Highway US 277
From 2.083 MILES WEST OF FM 2846
To 1.69 MILES WEST OF FM 368
CSJ 0156-05-049
Proj ID NH 1302(006)
Work Type WIDEN NON - FREEWAY
 
4.005 14393280.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-15
Work Began 00-00-00
Work Completed  
Time Computed 06-21-15
Contract Working Days 313
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153007
Totals 14393280.57 0.00 0.00 0.0

CountyBAYLOR
Highway US 277
From 2.78 MILES EAST OF RM 1919
To 0.64 MILES EAST OF US 183/283
CSJ 0156-06-039
Proj ID C 156-6-39
Work Type WIDEN NON - FREEWAY
 
5.896 10550963.24 0.00 10715501.63 99.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 269
Addl Days Granted 75
Working Days Charged 344
Percent Time Used 100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-06-039
CONTRACTORS SERVICE COMPANY(0.26%)
TEX OP CONSTRUCTION, LP(0.28%)
W.S. CONSTRUCTION COMPANY(6.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
ZACK BURKETT CO. ( 26.33%)
WILLIS ELECTRIC CO., LP(1.32%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 06123203
Totals 10550963.24 0.00 10715501.63 99.9

page 1 | page 2 | page 3