Monthly State Let Construction Report For Wichita Falls District As Of Jan 11, 2016 Page 1 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTAGUE
Highway US 81 ETC
From 3.513 MI N OF SL 19
To 0.121 MI N OF SL 19
CSJ 0013-02-020
Proj ID STP 2016(030)HES
Work Type HAZARD ELIMINATION SAFETY
 
91.464 535748.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153027
Totals 535748.34 0.00 0.00 0.0

CountyWILBARGER
Highway US 70
From US 287
To NEAR BENTLEY STREET
CSJ 0043-05-104
Proj ID C 43-5-104
Work Type OVERLAY
 
1.266 1537319.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153040
Totals 1537319.84 0.00 0.00 0.0

CountyWILBARGER
Highway US 287 ETC
From FM 1763
To SH 240 (FRONTAGE ROADS ONLY)
CSJ 0043-07-108
Proj ID NH 2016(216)
Work Type SEAL COAT
 
196.102 6799282.28 36378.59 36378.59 0.5
Work Order 11-24-15
Work Began 00-00-00
Work Completed  
Time Computed 12-24-15
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153225
Totals 6799282.28 36378.59 36378.59 0.5

CountyWICHITA
Highway IH 44 ETC
From MAURINE STREET
To SP 325 (EAST FRONTAGE ROAD)
CSJ 0043-09-121
Proj ID IM 0448(016)
Work Type SEAL COAT
 
140.976 5404266.01 0.00 5583675.09 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 04-22-14
Work Completed 09-29-14
Time Computed 01-22-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 106
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-121
FLAT LINE, INC.( 20.68%)
RED SIXTEEN CONSTRUCTION, INC. (2.55%)
Contract # 10133222
Totals 5404266.01 0.00 5583675.09 100.0

CountyWICHITA
Highway US 287
From AT HUNTINGTON ROAD
To .
CSJ 0043-09-122
Proj ID BR 2015(600)
Work Type BRIDGE REPLACEMENT
 
0.410 2426317.29 136328.07 1728399.03 71.2
Work Order 03-30-15
Work Began 06-29-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 178
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 69
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-122
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.95%)
MCL CONTRACTING, LLC (0.13%)
DUSTROL, INC.(1.80%)
ZACK BURKETT CO. ( 20.20%)
LANCO TURF & SEEDING, INC. (1.49%)
DUSTIN ALLEN, INC. (3.70%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
W.S. CONSTRUCTION COMPANY(1.11%)
STRIPING TECHNOLOGY, L.P.(1.47%)
Contract # 02153228
Totals 2426317.29 136328.07 1728399.03 71.2

CountyWICHITA
Highway IH 44
From NEAR SP 325/US 287 INTERSECTION
To NEAR WICHITA RIVER
CSJ 0043-09-123
Proj ID NH 1502(062)
Work Type RESTORATION
 
2.548 1634013.82 4500.00 1709981.35 99.9
Work Order 05-12-15
Work Began 08-05-15
Work Completed  
Time Computed 06-12-15
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 93
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-123
COTHRAN TRUCKING, LLC(1.39%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
TEX OP CONSTRUCTION, LP(6.55%)
BARRICADES UNLIMITED (1.30%)
HALL BROTHERS, INC.(5.41%)
SILVER CREEK CONSTRUCTION, INC.( 30.59%)
Contract # 04153053
Totals 1634013.82 4500.00 1709981.35 99.9

CountyWICHITA
Highway US 287
From JOHSNSON ROAD
To FM 368 ENTRANCE RAMP (SB)
CSJ 0043-09-124
Proj ID NH 2016(354)
Work Type OVERLAY
 
8.057 2435987.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-124
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163221
Totals 2435987.72 0.00 0.00 0.0

CountyWICHITA
Highway BU 287J
From CITY VIEW DRIVE
To IH 44 ON RAMP
CSJ 0043-17-028
Proj ID NH 2015(401)
Work Type OVERLALY
 
2.197 802018.50 581440.57 691239.57 94.0
CountyWILBARGER
Highway US 283
From FM 924
To FM 925
CSJ 0124-02-031
Proj ID STP 2015(402)
Work Type OVERLAY
 
7.129 1711461.76 211982.08 1925753.97 99.9
Work Order 01-05-15
Work Began 11-02-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 263
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-028
COTHRAN TRUCKING, LLC(0.71%)
COWBELL TRAFFIC SERVICE, INC.(0.78%)
STRIPE-A-ZONE, INC.(3.58%)
CONTRACTORS SERVICE COMPANY(0.19%)
TEXOP CONSTRUCTION (2.11%)
Contract # 12143029
Totals 2513480.26 793422.65 2616993.54 99.9

CountyWICHITA
Highway BU 287J
From IH 44
To BRIDGE N OF FM 171
CSJ 0043-17-029
Proj ID STP 2016(378)
Work Type OVERLAY
 
1.594 655287.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 19
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153032
Totals 655287.30 0.00 0.00 0.0

CountyWICHITA
Highway US 82
From GALVESTON STREET
To MCKINNEY ROAD
CSJ 0044-01-098
Proj ID NH 1302(019)
Work Type OVERLAY
 
2.705 1769278.83 0.00 2157305.02 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-12-13
Work Began 10-08-13
Work Completed 12-12-14
Time Computed 08-28-13
Contract Working Days 30
Addl Days Granted 2
Working Days Charged 53
Percent Time Used 165
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-098
COTHRAN TRUCKING, LLC(1.44%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.14%)
O. TREVINO CONSTRUCTION, LLC (3.49%)
WEST TEXAS RUMBLE STRIP(0.23%)
TEX OP CONSTRUCTION, LP(6.78%)
CROSSROADS, L.P. (0.48%)
Contract # 07133248
Totals 1769278.83 0.00 2157305.02 100.0

CountyCLAY
Highway US 82 ETC
From US 82 EASTBOUND AT DUCK CREEK
To .
CSJ 0044-02-079
Proj ID BR 2016(355)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
24.674 5938095.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-02-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163022
Totals 5938095.15 0.00 0.00 0.0

CountyCLAY
Highway US 82
From EAST CITY LIMITS OF HENRIETTA
To MONTAGUE COUNTY LINE
CSJ 0044-03-047
Proj ID NH 2013(784)
Work Type REHABILITATION OF EXISTING ROAD
 
12.888 5114930.10 0.00 5094428.48 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 12-18-13
Work Completed  
Time Computed 08-30-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 329
Percent Time Used 185
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-03-047
W.S. CONSTRUCTION COMPANY(4.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
COTHRAN TRUCKING, LLC(0.16%)
PAVEMENT MARKINGS INC. (2.12%)
RICE ENVIRONMENTAL SERVICES(1.29%)
Contract # 05133021
Totals 5114930.10 0.00 5094428.48 99.9

CountyMONTAGUE
Highway US 82
From AT UP RR, 0.8 MI WEST OF US 81
To NEAR RINGGOLD
CSJ 0044-04-044
Proj ID STP 1102(216)RGS
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.589 6249421.47 0.00 6498155.92 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-06-11
Work Began 01-03-12
Work Completed 03-06-15
Time Computed 11-05-11
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 95
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-044
TEXAS SHAFTS, INC. (2.66%)
NORTH TEXAS REBAR, LLC (0.31%)
CONCRETE CUTTING BY BOND (0.11%)
JM MATERIALS, INC. (0.14%)
PEACHTREE CONSTRUCTION, LTD. (0.53%)
TRAC-WORK, INC.( 10.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.32%)
MOBILE ENTERPRISES, INC. (1.39%)
ERWIN STEEL WORKS, LLC (0.52%)
ODUM SERVICES, L.P.(0.28%)
NORTH TEXAS CONTRACTING, INC.(7.92%)
AR DANIEL SERVICES (0.91%)
J. E. GUZMAN CONSTRUCTION, INC.(0.26%)
MAXIM CRANE WORKS(0.12%)
LINDAMOOD DEMOLITION, INC. (0.60%)
Contract # 08113202
Totals 6249421.47 0.00 6498155.92 100.0

CountyMONTAGUE
Highway US 82
From NEAR THE EAST CITY LIMITS OF NOCONA
To FM 1815 (EB & WB LANES)
CSJ 0044-06-071
Proj ID NH 2014(270)
Work Type OVERLAY
 
11.428 4997746.20 0.00 4917023.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 07-09-14
Work Completed 04-30-15
Time Computed 03-18-14
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 96
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-071
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
CROSSROADS, L.P. (0.37%)
DUSTROL, INC.(1.66%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.69%)
HJC FARMS, INC.(0.96%)
Contract # 12133219
Totals 4997746.20 0.00 4917023.57 100.0

CountyMONTAGUE
Highway US 82
From SAINT JO
To COOKE COUNTY LINE
CSJ 0044-06-073
Proj ID NH 2015(691)
Work Type OVERLAY
 
8.118 3960785.97 142911.79 4374356.22 99.9
Work Order 04-07-15
Work Began 06-24-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 85
Addl Days Granted 7
Working Days Charged 89
Percent Time Used 96
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-073
ALTUS TRAFFIC MANAGEMENT LLC (0.11%)
TEXOP CONSTRUCTION (0.29%)
STRIPE-A-ZONE, INC.(1.64%)
MARCOM"S MOWING SERVICE, LLC (0.33%)
DUSTROL, INC.(0.57%)
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
Contract # 03153221
Totals 3960785.97 142911.79 4374356.22 99.9

CountyCOOKE
Highway US 82
From ASH STREET
To MAPLE STREET
CSJ 0044-07-068
Proj ID NH 2015(469)
Work Type LANDSCAPE
 
0.302 145746.35 0.00 131768.03 90.4
Work Order 02-26-15
Work Began 04-28-15
Work Completed  
Time Computed 03-14-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 66
Contractor(s)
BEVERLY SUE GLOBAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-07-068
PARKER ELECTRIC(8.39%)
MHB CONSTRUCTION, INC. ( 54.79%)
Contract # 01153203
Totals 145746.35 0.00 131768.03 90.4

CountyCOOKE
Highway US 82
From NEAR WEBER DRIVE
To NEAR IH 35
CSJ 0044-08-066
Proj ID NH 2013(625)
Work Type MISCELLANEOUS CONSTRUCTION
 
6.004 619413.20 0.00 645615.04 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-14
Work Began 06-16-14
Work Completed 11-20-15
Time Computed 05-19-14
Contract Working Days 61
Addl Days Granted 11
Working Days Charged 71
Percent Time Used 98
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-066
LIRA ELECTRIC( 43.71%)
DUSTROL, INC.(5.81%)
STRAIGHT LINE SAWING & SEALING (1.21%)
STRIPING TECHNOLOGY, L.P.(3.12%)
FORTSON CONTRACTING, INC.(1.40%)
Contract # 11133208
Totals 619413.20 0.00 645615.04 100.0

CountyCOOKE
Highway US 82
From FM 1199 SOUTH
To NEAR IH 35
CSJ 0044-08-068
Proj ID NH 2015(403)
Work Type OVERLAY
 
3.876 1673272.77 0.00 1750513.69 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 07-07-15
Work Completed 10-26-15
Time Computed 01-23-15
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 158
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-068
TOTAL HIGHWAY MAINTENANCE, LLC (0.12%)
STRIPE-A-ZONE, INC.(2.13%)
TEXOP CONSTRUCTION (0.41%)
Contract # 12143209
Totals 1673272.77 0.00 1750513.69 100.0

CountyBAYLOR
Highway SH 114 ETC
From US 183
To NEAR FM 1285
CSJ 0133-05-026
Proj ID NH 2015(232)
Work Type SEAL COAT
 
147.201 6495189.51 0.00 6398195.86 100.0
Work Order 11-17-14
Work Began 07-22-15
Work Completed 11-18-15
Time Computed 12-03-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 98
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0133-05-026
VIZCAINO, L.P. ( 19.43%)
FLASHER EQUIPMENT COMPANY(1.26%)
Contract # 10143220
Totals 6495189.51 0.00 6398195.86 100.0

CountyWICHITA
Highway SH 25 ETC
From US 287
To BU 287H
CSJ 0137-02-027
Proj ID STP 2015(404)
Work Type OVERLAY
 
5.439 1612714.61 0.00 1511254.02 95.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 07-27-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 174
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0137-02-027
COTHRAN TRUCKING, LLC(1.11%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
TEXOP CONSTRUCTION (7.30%)
STRIPE-A-ZONE, INC.(3.68%)
Contract # 12143229
Totals 1612714.61 0.00 1511254.02 95.4

page 1 | page 2 | page 3 | page 4