Monthly State Let Construction Report For Wichita Falls District As Of Mar 13, 2024 Page 2 Of 2

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA ETC
HighwayFM 2380 ETC
FromFM 369
ToARCHER COUNTY LINE
CSJ0283-01-018
Proj IDF 2023(810)
Work TypeOVERLAY
 
7479603.50241611.163.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0283-01-018
CHEROKEE SERVICES (0.35)
BARRICADES UNLIMITED (0.73)
DUSTROL, INC. (8.75)
TRP CONSTRUCTION GROUP, LLC (2.51)
Contract #05233254
Totals7479603.50115230.47241611.163.2

CountyTHROCKMORTON
HighwaySH 79
FromYOUNG COUNTY LINE
ToMEXICAN SPRINGS RD
CSJ0284-02-026
Proj IDF 2023(922)
Work TypeREHABILITATION OF EXISTING ROAD
 
7963304.671212974.6615.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-12-23
Work Began12-12-23
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged54
Percent Time Used22
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0284-02-026
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
TEXOP CONSTRUCTION (0.24)
BARRICADES UNLIMITED (0.48)
FLAT LINE, INC. (0.78)
MARCOMS CONSTRUCTION LLC (0.73)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.91)
DUSTIN ALLEN, INC. (0.65)
W. S. CONSTRUCTION COMPANY (2.51)
CLARK HAULING SOLUTIONS LLC (0.50)
ZACK BURKETT CO. (0.50)
WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.62)
SAENZ TRANSPORT, LLC (0.62)
Contract #06233214
Totals7963304.67623634.061212974.6615.2

CountyTHROCKMORTON
HighwaySH 79
FromMEXICAN SPRINGS RD
ToUS 183
CSJ0284-02-027
Proj IDC 284-2-27
Work TypeWIDEN NON-FREEWAY
 
7882206.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days178
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0284-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243012
Totals7882206.690.000.000.0

CountyCOOKE
HighwayFM 51
FromAT ELM FORK TRINITY RIVER
To.
CSJ0312-01-076
Proj IDBR 2022(425)
Work TypeBRIDGE REPLACEMENT
 
0.1104761917.354896449.9799.9
Work Order05-12-22
Work Began09-06-22
Work Completed
Time Computed06-13-22
Contract Working Days285
Addl Days Granted0
Working Days Charged256
Percent Time Used89
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-076
4-WAY HAULERS, LLC (0.66)
HERMANOS STEEL, LLC (6.40)
MASSEY CONTRACTORS, LLC (3.02)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.34)
FC TRAFFIC CONTROL, INC. (1.01)
STRIPING TECHNOLOGY, L.P. (0.77)
WYLIE DRILLING & DRAINAGE, INC. (3.92)
TEXOP CONSTRUCTION (0.44)
MICA CORPORATION (1.09)
DFW REBAR, INC. (0.20)
JAGOE-PUBLIC COMPANY (7.31)
Contract #04223009
Totals4761917.350.004896449.9799.9

CountyCLAY
HighwaySH 148
FromFM 1883
ToRUSSELL CREEK
CSJ0391-04-030
Proj IDSTP 2022(627)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5543432425.50359068.0911.7
CountyZERO COUNTIES
Highway
From
To
CSJ0391-05-021
Proj ID
Work Type
 
0.002065476.570.0
CountyZERO COUNTIES
Highway
From
To
CSJ0391-05-022
Proj ID
Work Type
 
0.00852544.140.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-22
Work Began10-04-22
Work Completed
Time Computed00-00-00
Contract Working Days181
Addl Days Granted0
Working Days Charged225
Percent Time Used124
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0391-04-030
W. S. CONSTRUCTION COMPANY (11.64)
HJC FARMS, INC. (5.12)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.28)
TRP CONSTRUCTION GROUP, LLC (1.61)
Contract #06223218
Totals3432425.5010500.003277088.8096.7

CountyCLAY
HighwaySH 148
FromSH 148 AT RUSSELL CREEK
To.
CSJ0391-05-023
Proj IDBR 2022(628)
Work TypeBRIDGE MAINTENANCE
 
141638.300.000.0
CountyCLAY
HighwaySH 148
FromSH 148 AT E FORK OF THE LITTLE WICHITA R
To.
CSJ0391-05-024
Proj IDBR 2022(628)
Work TypeBRIDGE MAINTENANCE
 
125478.300.000.0
CountyCLAY
HighwaySH 148
FromFM 174
ToNEAR W PLEASANT VALLEY RD
CSJ0391-05-025
Proj IDF 2023(923)
Work TypeWIDEN NON-FREEWAY
 
4499454.60860736.1019.1
CountyCLAY
HighwaySH 148
FromNEAR W PLEASANT VALLEY RD
ToJACK CL
CSJ0391-05-026
Proj IDF 2023(923)
Work TypeWIDEN NON-FREEWAY
 
2113038.51233644.0511.0
Work Order07-26-23
Work Began10-02-23
Work Completed
Time Computed08-28-23
Contract Working Days316
Addl Days Granted0
Working Days Charged79
Percent Time Used25
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0391-05-023
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.10)
COLD CREEK CONSTRUCTION, LTD (4.15)
DUSTIN ALLEN, INC. (2.77)
FC TRAFFIC CONTROL, INC. (0.47)
FLAT LINE, INC. (0.55)
MARCOMS CONSTRUCTION LLC (0.52)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
W. S. CONSTRUCTION COMPANY (15.25)
Contract #06233009
Totals6879609.71268668.501094380.1515.9

CountyMONTAGUE
HighwayFM 677
FromFM 677
ToAT COBB HOLLOW
CSJ0423-02-025
Proj IDF 2023(620)
Work TypeBRIDGE REPLACEMENT
 
2630598.361865544.4270.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-23
Work Began09-18-23
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged101
Percent Time Used45
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0423-02-025
BARRICADES UNLIMITED (0.38)
GREGORY PILE DRIVING, INC. (1.84)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (3.17)
HODGES AND SON CONSTRUCTION COMPANY, INC. (7.86)
TORO BRAVO CONSTRUCTION, LLC (0.22)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.81)
GARY A. CRAIN, INC. (0.12)
Contract #04233034
Totals2630598.36461065.221865544.4270.9

CountyYOUNG
HighwaySH 114
FromSH 79
To0.8 MI WEST OF FM 1769
CSJ0444-01-044
Proj IDF 2023(055)
Work TypeSUPER-2 HIGHWAY
 
10524957.681041196.859.8
CountyYOUNG
HighwaySH 114
FromSH 114 AT SALT CREEK
To.
CSJ0444-01-046
Proj IDF 2023(207)
Work TypeBRIDGE MAINTENANCE
 
87937.5088396.8899.9
Work Order10-06-22
Work Began03-06-23
Work Completed
Time Computed12-20-22
Contract Working Days275
Addl Days Granted0
Working Days Charged215
Percent Time Used78
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0444-01-044
W. S. CONSTRUCTION COMPANY (11.72)
LANCO TURF & SEEDING, INC. (1.04)
CONTRACTORS SERVICE, LTD. (0.64)
TRP CONSTRUCTION GROUP, LLC (1.61)
HJC FARMS, INC. (3.38)
Contract #09223021
Totals10612895.1899480.001129593.7310.6

CountyYOUNG
HighwayFM 701
FromFM 701
ToAT CLEAR FORK OF THE BRAZOS RIVER
CSJ0570-03-019
Proj IDBR 2023(333)
Work TypeBRIDGE REPLACEMENT
 
0.1143033426.361680356.4255.3
CountyYOUNG
HighwayFM 701
FromFM 701
ToAT CLEAR FORK BRAZOS RIVER
CSJ0570-03-020
Proj IDBR 1802(482)
Work TypeBRIDGE REPLACEMENT
 
0.1052535575.11618709.5124.4
CountyYOUNG
HighwayFM 1974
FromFM 1974
ToAT CLEAR FORK OF THE BRAZOS RIVER
CSJ2217-01-015
Proj IDBR 2023(334)
Work TypeBRIDGE REPLACEMENT
 
0.0872276443.532355003.8899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-27-23
Work Began05-01-23
Work Completed
Time Computed00-00-00
Contract Working Days336
Addl Days Granted0
Working Days Charged178
Percent Time Used52
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0570-03-019
FC TRAFFIC CONTROL, INC. (0.03)
WYLIE DRILLING & DRAINAGE, INC. (6.29)
ODUM SERVICES, LLC (1.30)
PENHALL COMPANY (0.13)
S & S BRIDGE PAINTING, INC. (0.77)
HERMANOS STEEL, LLC (0.53)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.32)
PEACHTREE CONSTRUCTION, LTD. (7.84)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.63)
TORO BRAVO CONSTRUCTION, LLC (0.20)
Contract #01233211
Totals7845445.00414049.284654069.8159.3

CountyBAYLOR
HighwayFM 422
FromFM 422
ToAT GODWIN CREEK
CSJ0814-01-037
Proj IDBR 2024(544)
Work TypeBRIDGE REPLACEMENT
 
2860939.10331618.0011.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-24
Work Began02-20-24
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged9
Percent Time Used6
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-037
SUPERIOR TRAFFIC CONTROL, LLC (1.63)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.77)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.81)
TORO BRAVO CONSTRUCTION, LLC (0.05)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.78)
PEACHTREE CONSTRUCTION, LTD. (9.14)
HODGES AND SON CONSTRUCTION COMPANY, INC. (5.33)
AWP SAFETY (0.10)
Contract #12233029
Totals2860939.10331618.00331618.0011.5

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToWICHITA AND GRAHAM AREAS
CSJ0903-00-119
Proj IDF 2022(378)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
689012.10686535.4499.9
Work Order06-22-22
Work Began12-15-22
Work Completed
Time Computed09-20-22
Contract Working Days70
Addl Days Granted0
Working Days Charged74
Percent Time Used105
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-119
MEDELLIN HDD LLC (8.25)
Contract #05223024
Totals689012.100.00686535.4499.9

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToGAINESVILLE AREA
CSJ0903-00-120
Proj IDF 2022(377)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
833158.86754538.8392.2
Work Order06-22-22
Work Began02-15-23
Work Completed
Time Computed09-20-22
Contract Working Days78
Addl Days Granted0
Working Days Charged101
Percent Time Used129
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-120
MEDELLIN HDD LLC (6.41)
Contract #05223229
Totals833158.860.00754538.8392.2

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE WICHITA FALLS DISTRICT
CSJ0903-00-122
Proj IDC 903-00-122
Work TypeBRIDGE MAINTENANCE
 
1041194.001073294.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-23
Work Began09-05-23
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged51
Percent Time Used75
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233042
Totals1041194.000.001073294.1099.9

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS
ToIN WICHITA AND CLAY COUNTIES
CSJ0903-00-123
Proj IDC 903-00-123
Work TypeBRIDGE MAINTENANCE
 
1166854.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243224
Totals1166854.000.000.000.0

CountyCLAY
HighwayVA
FromWITHIN LAKE ARROWHEAD STATE PARK
To.
CSJ0903-06-022
Proj IDC 903-6-22
Work TypeREHABILITATION OF EXISTING ROAD
 
0.1002547006.802873010.9499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-11-22
Work Began11-30-22
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted30
Working Days Charged98
Percent Time Used85
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-06-022
DUSTROL, INC. (0.85)
BARRICADES UNLIMITED (0.18)
LANCO TURF & SEEDING, INC. (0.30)
H & F TRUCKING (0.98)
Contract #09223015
Totals2547006.800.002873010.9499.9

CountyARCHER
HighwayCR
FromCR 232 (SIGNED WILSON RANCH ROAD)
ToAT HOLLIDAY CREEK
CSJ0903-29-027
Proj IDBR 2020(351)
Work TypeBRIDGE REPLACEMENT
 
385530.00371905.8496.4
CountyARCHER
HighwayCR
FromCR 261 (SIGNED RIVER ROAD)
ToAT DRAW
CSJ0903-29-029
Proj IDBR 2022(780)
Work TypeBRIDGE REPLACEMENT
 
438686.00416352.3994.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-23
Work Began04-03-23
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged95
Percent Time Used93
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-29-027
LANCO TURF & SEEDING, INC. (3.41)
DUSTIN ALLEN, INC. (5.33)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.72)
TORO BRAVO CONSTRUCTION, LLC (0.46)
Contract #01233023
Totals824216.006025.00788258.2395.6

CountyCOOKE
HighwayFM 1198
FromUS 82
ToFM 1630
CSJ1351-01-016
Proj IDF 2023(924)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.1137202957.372023063.6728.0
CountyCOOKE
HighwayFM 1198
FromFM 1630
ToFM 922
CSJ1351-02-007
Proj IDF 2023(924)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.5394904538.62566819.4011.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-23
Work Began10-16-23
Work Completed
Time Computed00-00-00
Contract Working Days407
Addl Days Granted0
Working Days Charged63
Percent Time Used15
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 1351-01-016
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.57)
SOUTHERN CROSS CONTRACTORS, LLC (1.56)
DALLAS LITE AND BARRICADE, INC. (0.44)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
JR WEST TEXAS CONCRETE LLC (15.65)
JOE"S TREE SERVICE (0.17)
TRP CONSTRUCTION GROUP, LLC (0.52)
Contract #06233208
Totals12107495.99340280.052589883.0721.3

CountyCOOKE
HighwayFM 1630
FromMONTAGUE COUNTY LINE
ToCR 341
CSJ1609-01-029
Proj IDSTP 2B23(120)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2744283.781817445.9966.2
CountyCOOKE
HighwayFM 1630
FromCR 341
ToFM 373
CSJ1609-01-030
Proj IDSTP 2B23(120)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1866856.85903744.1448.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-23
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged92
Percent Time Used54
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1609-01-029
TEXAS TRAFFIC AND BARRICADE, LLC (0.34)
DUSTROL, INC. (1.31)
TRP CONSTRUCTION GROUP, LLC (3.33)
SOUTHERN CROSS CONTRACTORS, LLC (1.67)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.56)
Contract #06233618
Totals4611140.63260295.802721190.1359.0

CountyARCHER
HighwayFM 1954
FromUS 281
ToCLAY COUNTY LINE
CSJ1837-02-017
Proj IDF 2023(091)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.2727814963.762538461.6332.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began01-16-23
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted74
Working Days Charged227
Percent Time Used76
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1837-02-017
W. S. CONSTRUCTION COMPANY (20.80)
LANCO TURF & SEEDING, INC. (1.66)
DUSTIN ALLEN, INC. (1.04)
BARRICADES UNLIMITED (0.26)
MARCOM"S MOWING SERVICE, LLC (0.63)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.85)
Contract #09223235
Totals7814963.76154834.282538461.6332.4

page 1 | page 2