Monthly State Let Construction Report For Wichita Falls District As Of Jun 15, 2016 Page 2 Of 3

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOOKE
Highway IH 35 ETC
From ON IH 35
To AT FM 51 (NB & SB)
CSJ 0195-01-099
Proj ID NH 1502(347)
Work Type MISCELLANEOUS
 
1.039 2144827.68 75988.70 809700.42 37.7
Work Order 11-10-15
Work Began 01-25-16
Work Completed  
Time Computed 11-10-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 32
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-099
ALTUS TRAFFIC MANAGEMENT LLC (0.78%)
EROSION CONTROL MANAGEMENT SERVICES(0.22%)
STRIPING TECHNOLOGY, L.P.(4.11%)
S & S BRIDGE PAINTING, INC.(9.11%)
HJC FARMS, INC.( 18.98%)
TEXAS CUTTING & CORING, INC. (1.37%)
Contract # 06153016
Totals 2144827.68 75988.70 809700.42 37.7

CountyWICHITA
Highway US 281 ETC
From 0.1 MI W OF WINDTHORST RD
To US 281 CONNECTOR
CSJ 0249-01-045
Proj ID NH 2016(381)
Work Type OVERLAY
 
10.480 2947967.38 0.00 0.00 0.0
Work Order 03-02-16
Work Began 00-00-00
Work Completed  
Time Computed 04-01-16
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0249-01-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163008
Totals 2947967.38 0.00 0.00 0.0

CountyARCHER
Highway US 281
From SH 25
To JACK COUNTY LINE
CSJ 0249-04-039
Proj ID STP 2013(624)
Work Type REHABLIITAITION OF EXISTING ROAD
 
8.737 10168493.22 326150.46 2784040.99 27.3
Work Order 05-08-15
Work Began 07-13-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 345
Addl Days Granted 1
Working Days Charged 125
Percent Time Used 36
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
W.S. CONSTRUCTION COMPANY(6.30%)
CROSSROADS, L.P. (0.23%)
STRIPING TECHNOLOGY, L.P.(1.55%)
DUSTROL, INC.(2.47%)
WOLFE CONSTRUCTION GROUP, INC. (0.85%)
MARCOM"S MOWING SERVICE, LLC (0.35%)
WEST TEXAS RUMBLE STRIP(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30%)
Contract # 03153034
Totals 10168493.22 326150.46 2784040.99 27.3

CountyCOOKE
Highway FM 51
From NEAR IH 35 FRONTAGE ROAD
To FM 1306
CSJ 0312-01-077
Proj ID STP 2016(383)
Work Type OVERLAY
 
1.255 565293.98 121711.31 601857.31 99.9
Work Order 01-29-16
Work Began 03-22-16
Work Completed  
Time Computed 02-28-16
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 41
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-077
CROSSROADS, L.P. (1.05%)
WOLFE CONSTRUCTION GROUP, INC. (0.69%)
TOTAL HIGHWAY MAINTENANCE, LLC (5.16%)
DUSTROL, INC.(8.11%)
Contract # 12153213
Totals 565293.98 121711.31 601857.31 99.9

CountyCLAY
Highway SH 148
From NEAR US 287
To NEAR ANGLE LANE
CSJ 0391-04-024
Proj ID STP 1502(096)
Work Type REHABILITATION OF EXISTING ROAD
 
4.689 2379349.36 590496.58 2281404.89 95.8
Work Order 06-30-15
Work Began 08-07-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 134
Addl Days Granted 24
Working Days Charged 152
Percent Time Used 96
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0391-04-024
TRANSPORT TRUST(5.80%)
ALTUS TRAFFIC MANAGEMENT LLC (0.35%)
WOLFE CONSTRUCTION GROUP, INC. (1.22%)
W.S. CONSTRUCTION COMPANY( 21.50%)
HJC FARMS, INC.(0.60%)
DUSTROL, INC.(1.29%)
TRP CONSTRUCTION GROUP, LLC(1.16%)
BEAN ELECTRICAL, INC.(3.22%)
C & S UTILITY CONTRACTORS, INC.(1.07%)
Contract # 05153013
Totals 2379349.36 590496.58 2281404.89 95.8

CountyYOUNG
Highway FM 61
From US 380
To FM 3003
CSJ 0529-01-023
Proj ID STP 1602(001)
Work Type OVERLAY
 
8.797 4288948.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 186
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0529-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163003
Totals 4288948.68 0.00 0.00 0.0

CountyWICHITA
Highway SH 258
From 0.2 MILES WEST OF FM 2226
To US 82
CSJ 0544-01-020
Proj ID STP 2013(903)HES
Work Type REHABILITATION OF EXISTING ROAD
 
7.000 3882193.04 6968.05 3893256.48 99.9
CountyWICHITA
Highway SH 258
From SH 25
To 0.2 MILES WEST OF FM 2226
CSJ 0544-01-021
Proj ID STP 2013(904)
Work Type REHABILITATION OF EXISTING ROAD
 
3.353 1941339.06 4190.00 1955718.85 99.9
Work Order 12-19-13
Work Began 03-06-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 150
Addl Days Granted 23
Working Days Charged 360
Percent Time Used 208
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
ZACK BURKETT CO. ( 42.92%)
FLAT LINE, INC.(0.83%)
J.V. CONCRETE CONSTRUCTION ( 15.86%)
MARCOM"S MOWING SERVICE, LLC (2.95%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
W.S. CONSTRUCTION COMPANY(4.69%)
Contract # 09133206
Totals 5823532.10 11158.05 5848975.33 99.9

CountyWICHITA
Highway FM 171
From FM 890
To CLAY COUNTY LINE
CSJ 0681-01-021
Proj ID STP 2015(875)HES
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.577 4534926.90 71263.71 3679333.51 81.2
Work Order 06-01-15
Work Began 07-07-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 102
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0681-01-021
ALTUS TRAFFIC MANAGEMENT LLC (0.22%)
W.S. CONSTRUCTION COMPANY( 28.48%)
BARRICADES UNLIMITED (1.45%)
MARCOM"S MOWING SERVICE, LLC (0.40%)
JE CASEY, LLC(1.96%)
ZACK BURKETT CO. ( 27.96%)
Contract # 04153244
Totals 4534926.90 71263.71 3679333.51 81.2

CountyWILBARGER
Highway FM 91
From FM 91 AT WANDERERS CREEK
To .
CSJ 0702-01-014
Proj ID BR 2016(928)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.767 2458571.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163019
Totals 2458571.50 0.00 0.00 0.0

CountyCOOKE
Highway FM 678
From FM 3092
To FM 3164
CSJ 0782-01-033
Proj ID STP 1502(097)
Work Type REHABILITATION OF EXISTING ROADWAY
 
9.586 3375961.86 119644.22 1653213.94 48.9
Work Order 07-06-15
Work Began 01-25-16
Work Completed  
Time Computed 08-06-15
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 31
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0782-01-033
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
VENUS CONSTRUCTION ( 24.18%)
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
HJC FARMS, INC.(0.88%)
RAMBO CONTRACTING, INC.(4.48%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59%)
HAYWARD BAKER, INC.(2.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.91%)
Contract # 05153014
Totals 3375961.86 119644.22 1653213.94 48.9

CountyWICHITA
Highway FM 369
From AT FAIRWAY INT, NEAR HUGHES ST
To NEAR MCNIEL AVE
CSJ 0802-02-052
Proj ID STP 2013(622)
Work Type MISCELLANEOUS WORK
 
0.331 1792483.50 430332.80 1096471.80 61.1
Work Order 07-24-15
Work Began 03-14-16
Work Completed  
Time Computed 08-23-15
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 22
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-052
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
OSCAR ORDUNO, INC. (2.96%)
PEACHTREE CONSTRUCTION, LTD. (4.50%)
J. E. GUZMAN CONSTRUCTION, INC.(3.90%)
WOLFE CONSTRUCTION GROUP, INC. (0.29%)
Contract # 05153250
Totals 1792483.50 430332.80 1096471.80 61.1

CountyCOOKE
Highway FM 373
From AT DRY ELM CREEK
To .
CSJ 0823-01-031
Proj ID BR 2015(601)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.241 1612050.20 19136.00 1468520.70 91.0
Work Order 04-02-15
Work Began 06-09-15
Work Completed  
Time Computed 04-18-15
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 236
Percent Time Used 99
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0823-01-031
N-LINE TRAFFIC MAINTENANCE, L.P. (2.33%)
STRIPING TECHNOLOGY, L.P.(1.55%)
MORRIS COUNTY CONTRACTORS, L.L.C.(6.69%)
PENHALL COMPANY(0.19%)
PEACHTREE CONSTRUCTION, LTD. ( 12.29%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
DUSTROL, INC.(0.47%)
Contract # 02153003
Totals 1612050.20 19136.00 1468520.70 91.0

CountyCLAY
Highway FM 172
From 3.181 MI W OF FM 1883
To 3.876 MI E OF FM 1883
CSJ 0824-03-016
Proj ID STP 1502(099)HES
Work Type HAZARD ELIMINATION SAFETY
 
7.112 1215642.62 7764.80 1168734.34 96.1
Work Order 06-30-15
Work Began 08-17-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 84
Addl Days Granted 7
Working Days Charged 87
Percent Time Used 95
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0824-03-016
WOLFE CONSTRUCTION GROUP, INC. (1.10%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
TRANSPORT TRUST(2.42%)
MARCOM"S MOWING SERVICE, LLC (0.70%)
TRP CONSTRUCTION GROUP, LLC(2.15%)
W.S. CONSTRUCTION COMPANY(6.04%)
THE LANE CONSTRUCTION CORPORATION( 19.65%)
AAJ CONCRETE CONSTRUCTION(0.52%)
Contract # 05153212
Totals 1215642.62 7764.80 1168734.34 96.1

CountyCOOKE
Highway FM 922
From MONTAGUE COUNTY LINE
To FM 373
CSJ 0845-03-056
Proj ID STP 2014(357)
Work Type RESTORATION
 
13.082 4230047.49 445129.47 2799260.06 66.1
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 213
Addl Days Granted 8
Working Days Charged 197
Percent Time Used 89
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.84%)
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
J.V. CONCRETE CONSTRUCTION (6.52%)
LONE STAR BARRIER SERVICES, LLC(3.84%)
MARCOM"S MOWING SERVICE, LLC (1.06%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.42%)
STORM WATER MANAGEMENT, INC. (0.96%)
MIKE ALBERT, INC.(3.19%)
Contract # 02143007
Totals 4230047.49 445129.47 2799260.06 66.1

CountyCOOKE
Highway FM 922
From AT FM 51
To .
CSJ 0845-03-060
Proj ID STP 2016(847)
Work Type REHABILITATION OF EXISTING ROAD
 
0.248 332007.54 0.00 0.00 0.0
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 05-07-16
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163209
Totals 332007.54 0.00 0.00 0.0

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-073
Proj ID STP 2015(753)
Work Type SIGN UPGRADE
 
1.000 574221.00 22435.05 569581.00 99.7
Work Order 04-28-15
Work Began 08-17-15
Work Completed  
Time Computed 05-29-15
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 108
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153029
Totals 574221.00 22435.05 569581.00 99.7

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 0.00 2926985.76 94.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 01-07-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 248
Percent Time Used 111
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
W.S. CONSTRUCTION COMPANY(7.60%)
MELS ELECTRIC, L.P.(5.66%)
STRIPING TECHNOLOGY, L.P.(0.74%)
BTA SERVICES, LTD. (1.00%)
Contract # 09143037
Totals 3132333.32 0.00 2926985.76 94.2

CountyWICHITA
Highway CR
From CR 155 (ENTERPRISE ROAD) AT CHINA
To CREEK
CSJ 0903-03-081
Proj ID BR 2006(198)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.280 1519578.50 177734.20 1012989.08 66.6
Work Order 07-31-15
Work Began 12-09-15
Work Completed  
Time Computed 08-01-15
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 50
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-081
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.98%)
GARY A. CRAIN, INC.(0.12%)
S & S BRIDGE PAINTING, INC.(5.94%)
DUSTIN ALLEN, INC. (5.05%)
LANCO TURF & SEEDING, INC. (1.65%)
CONTRACTORS SERVICE COMPANY(0.73%)
MCL CONTRACTING, LLC (0.45%)
Contract # 06153258
Totals 1519578.50 177734.20 1012989.08 66.6

CountyCOOKE
Highway CR
From CR 145 (CR 411) AT BLACK HOLLOW CRK
To .
CSJ 0903-15-081
Proj ID BR 2006(652)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.300 1009366.40 152391.92 912195.66 90.3
Work Order 03-26-15
Work Began 06-18-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 63
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-081
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
MORRIS COUNTY CONTRACTORS, L.L.C.(6.54%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
Contract # 02153238
Totals 1009366.40 152391.92 912195.66 90.3

CountyYOUNG
Highway CR
From CR 108 (HALL ROAD) AT SALT CREEK
To .
CSJ 0903-27-026
Proj ID BR 2009(196)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.132 685496.10 12228.20 701613.64 99.9
Work Order 06-15-15
Work Began 07-13-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 102
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-27-026
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.89%)
ALTUS TRAFFIC MANAGEMENT LLC (0.82%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
PEACHTREE CONSTRUCTION, LTD. (2.96%)
ODUM SERVICES, L.P.(3.97%)
HYPOWORKS(1.04%)
Contract # 04153246
Totals 685496.10 12228.20 701613.64 99.9

page 1 | page 2 | page 3