Monthly State Let Construction Report For Wichita Falls District As Of Dec 10, 2014 Page 2 Of 2

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWICHITA
Highway SH 258
From 0.2 MILES WEST OF FM 2226
To US 82
CSJ 0544-01-020
Proj ID STP 2013(903)HES
Work Type REHABILITATION OF EXISTING ROAD
 
7.000 3882193.04 73652.40 1656216.40 42.6
CountyWICHITA
Highway SH 258
From SH 25
To 0.2 MILES WEST OF FM 2226
CSJ 0544-01-021
Proj ID STP 2013(904)
Work Type REHABILITATION OF EXISTING ROAD
 
3.353 1941339.06 16822.80 440910.50 22.7
Work Order 12-19-13
Work Began 03-06-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 150
Addl Days Granted 12
Working Days Charged 153
Percent Time Used 94
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
ZACK BURKETT CO. ( 42.92%)
FLAT LINE, INC.(0.83%)
J.V. CONCRETE CONSTRUCTION ( 15.86%)
MARCOM"S MOWING SERVICE, LLC (2.74%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 09133206
Totals 5823532.10 90475.20 2097126.90 36.0

CountyBAYLOR
Highway FM 422
From US 82
To EAST CITY LIMITS OF SEYMOUR
CSJ 0814-01-027
Proj ID C 814-1-27
Work Type UPGRADING OF A NON - FREEWAY FACILITY
 
0.847 3332046.95 0.00 3509311.78 99.9
Work Order 09-13-12
Work Began 02-11-13
Work Completed  
Time Computed 02-11-13
Contract Working Days 245
Addl Days Granted 21
Working Days Charged 255
Percent Time Used 95
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-027
W.S. CONSTRUCTION COMPANY( 37.37%)
CONTRACTORS SERVICE COMPANY(0.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.55%)
ZACK BURKETT CO. ( 26.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.02%)
WILLIS ELECTRIC CO., LP(8.41%)
Contract # 07123006
Totals 3332046.95 0.00 3509311.78 99.9

CountyMONTAGUE
Highway FM 455
From MONTAGUE
To FM 1749
CSJ 0845-01-016
Proj ID STP 2013(686)
Work Type REHABILTATION OF EXISTING ROADWAY
 
14.179 3371976.79 17351.12 3906632.75 99.9
Work Order 09-04-13
Work Began 11-13-13
Work Completed  
Time Computed 09-20-13
Contract Working Days 151
Addl Days Granted 30
Working Days Charged 115
Percent Time Used 63
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0845-01-016
CROSSROADS, L.P. (1.42%)
W.S. CONSTRUCTION COMPANY(1.54%)
MARCOM"S MOWING SERVICE, LLC (0.55%)
LANCO TURF & SEEDING, INC. (1.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.22%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (1.32%)
ALLIED DRILLING COMPANY(0.03%)
MCRYAN HAULING, INC. (1.01%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.12%)
Contract # 05133231
Totals 3371976.79 17351.12 3906632.75 99.9

CountyCOOKE
Highway FM 922
From MONTAGUE COUNTY LINE
To FM 373
CSJ 0845-03-056
Proj ID STP 2014(357)
Work Type RESTORATION
 
13.082 4230047.49 23281.90 50398.84 1.1
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 9
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.84%)
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
J.V. CONCRETE CONSTRUCTION (6.52%)
LONE STAR BARRIER SERVICES, LLC(3.84%)
MARCOM"S MOWING SERVICE, LLC (1.06%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.42%)
STORM WATER MANAGEMENT, INC. (0.96%)
Contract # 02143007
Totals 4230047.49 23281.90 50398.84 1.1

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-072
Proj ID STP 2014(086)
Work Type MISCELLANEOUS WORK
 
1.000 399924.61 14593.20 184339.57 46.0
Work Order 04-15-14
Work Began 08-25-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 52
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-072
ALTUS TRAFFIC MANAGEMENT LLC (2.07%)
Contract # 03143032
Totals 399924.61 14593.20 184339.57 46.0

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 0.00 0.00 0.0
Work Order 11-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-19-14
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143037
Totals 3132333.32 0.00 0.00 0.0

CountyWICHITA
Highway CR
From CR 126 (BOHNER ROAD) AT WILDHORSE
To CREEK
CSJ 0903-03-101
Proj ID BR 1102(538)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 323285.45 42400.00 118270.00 36.5
Work Order 08-13-14
Work Began 10-08-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-101
ALTUS TRAFFIC MANAGEMENT LLC (0.79%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.03%)
DUSTIN ALLEN, INC. (2.90%)
WOLFE CONSTRUCTION GROUP, INC. (1.61%)
Contract # 07143039
Totals 323285.45 42400.00 118270.00 36.5

CountyCLAY
Highway CR
From CR 151 (FRIENDSHIP ROAD) AT BUFFALO
To CREEK
CSJ 0903-06-017
Proj ID BR 2013(145)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.114 344865.50 0.00 0.00 0.0
Work Order 08-20-14
Work Began 12-09-14
Work Completed  
Time Computed 11-18-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-06-017
TEXAS ALTERNATIVE GRASSER, INC.(1.74%)
ODUM SERVICES, L.P.(3.69%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 06143011
Totals 344865.50 0.00 0.00 0.0

CountyCOOKE
Highway VA
From WITHIN LAKE RAY ROBERTS STATE PARK
To JOHNSON BRANCH UNIT
CSJ 0903-15-098
Proj ID C 903-15-98
Work Type RESTORATION
 
0.100 739395.08 0.00 752432.56 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-14
Work Began 07-15-14
Work Completed 09-22-14
Time Computed 03-29-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 78
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-098
TOTAL HIGHWAY MAINTENANCE, LLC (6.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.06%)
TEX OP CONSTRUCTION, LP(5.53%)
Contract # 02143207
Totals 739395.08 0.00 752432.56 100.0

CountyBAYLOR
Highway CR
From ON CR 113 (MOSS ROAD)
To AT BRANCH OF BRIAR CREEK
CSJ 0903-31-006
Proj ID BR 2012(779)
Work Type BRIDGE REPLACEMENT
 
0.200 400053.00 114405.24 313617.36 78.3
Work Order 07-18-14
Work Began 09-08-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 73
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-31-006
ALTUS TRAFFIC MANAGEMENT LLC (1.22%)
LANCO TURF & SEEDING, INC. (3.50%)
DUSTIN ALLEN, INC. (8.46%)
HOUSTON SAWING & DRILLING(0.37%)
Contract # 06143005
Totals 400053.00 114405.24 313617.36 78.3

CountyMONTAGUE
Highway FM 1758
From BISHOP STREET
To DARWIN STREET (IN SECTIONS)
CSJ 1610-01-011
Proj ID STP 2014(271)HRR
Work Type REHABILITATION OF EXISTING HIGHWAY
 
3.943 2069552.90 95978.41 1378200.55 66.5
CountyMONTAGUE
Highway FM 1758
From SH 59
To END OF PAVEMENT
CSJ 1610-01-013
Proj ID STP 2014(272)
Work Type REHABILITATION
 
7.600 1253596.53 39729.90 844387.31 67.3
Work Order 02-19-14
Work Began 03-25-14
Work Completed  
Time Computed 03-25-14
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 128
Percent Time Used 62
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1610-01-011
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.40%)
VANN/ELLI, INC.(0.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.25%)
W.S. CONSTRUCTION COMPANY( 10.93%)
BUYERS BARRICADES, INC.(0.57%)
DURABLE SPECIALTIES, INC.(0.13%)
Contract # 12133019
Totals 3323149.43 135708.31 2222587.86 66.8

CountyCOOKE
Highway FM 902
From 0.088 MILES SE OF KIOWA
To GRAYSON COUNTY LINE
CSJ 2459-01-021
Proj ID STP 2014(013)HES
Work Type REHABILTATION OF EXISTING ROAD
 
4.626 2939410.05 7141.21 2258130.78 76.8
Work Order 11-19-13
Work Began 01-07-14
Work Completed  
Time Computed 01-07-14
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 66
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2459-01-021
GJ SEEDING, LLC(2.44%)
J.V. CONCRETE CONSTRUCTION ( 10.21%)
MARCOM"S MOWING SERVICE, LLC (2.34%)
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
STRIPING TECHNOLOGY, L.P.(1.49%)
MELS ELECTRIC, L.P.(0.40%)
MIKE ALBERT, INC.(1.03%)
LJ TRUCKING(0.31%)
Contract # 09133011
Totals 2939410.05 7141.21 2258130.78 76.8

page 1 | page 2