Monthly State Let Construction Report For Wichita Falls District As Of Jul 14, 2017 Page 2 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwayUS 82
From0.54 MILES WEST OF BU 82F
ToBU 82F
CSJ0156-05-058
Proj IDNH 1602(200)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.3581761197.181954153.13100.0
Work Order07-28-16
Work Began04-27-17
Work Completed07-07-17
Time Computed08-27-16
Contract Working Days32
Addl Days Granted4
Working Days Charged107
Percent Time Used297
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-058
CONTRACTORS SERVICE COMPANY (0.32)
PENHALL COMPANY (0.40)
COTHRAN TRUCKING, LLC (2.69)
BARRICADES UNLIMITED (2.66)
Contract #06163028
Totals1761197.18595376.951954153.13100.0

CountyWICHITA
HighwayIH 44
From0.023 MI. S OF SH 240
ToOKLAHOMA STATE LINE
CSJ0156-07-109
Proj IDSTP 1702(401)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.5001167403.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-07-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173038
Totals1167403.500.000.000.0

CountyCOOKE
HighwayIH 35 ETC
FromON IH 35
ToAT FM 51 (NB & SB)
CSJ0195-01-099
Proj IDNH 1502(347)
Work TypeMISCELLANEOUS
 
1.0392144827.682234817.0799.9
Work Order11-10-15
Work Began01-25-16
Work Completed
Time Computed11-10-15
Contract Working Days200
Addl Days Granted31
Working Days Charged261
Percent Time Used112
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-099
ALTUS TRAFFIC MANAGEMENT LLC (0.78)
EROSION CONTROL MANAGEMENT SERVICES (0.22)
STRIPING TECHNOLOGY, L.P. (4.11)
S & S BRIDGE PAINTING, INC. (9.11)
HJC FARMS, INC. (18.98)
TEXAS CUTTING & CORING, INC. (1.37)
PENHALL COMPANY (0.31)
Contract #06153016
Totals2144827.6867187.812234817.0799.9

CountyWICHITA ETC
HighwayUS 281 ETC
From0.1 MI W OF WINDTHORST RD
ToUS 281 CONNECTOR
CSJ0249-01-045
Proj IDNH 2016(381)
Work TypeOVERLAY
 
10.4802947967.383522048.5199.9
Work Order03-02-16
Work Began10-24-16
Work Completed
Time Computed04-01-16
Contract Working Days59
Addl Days Granted19
Working Days Charged151
Percent Time Used193
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0249-01-045
COTHRAN TRUCKING, LLC (1.52)
COWBELL TRAFFIC SERVICES, INC. (0.22)
ALTUS TRAFFIC MANAGEMENT LLC (0.55)
TEX OP CONSTRUCTION, LP (1.11)
PAVEMENT MARKINGS INC. (2.97)
WOLFE CONSTRUCTION GROUP, INC. (0.44)
Contract #01163008
Totals2947967.385484.653522048.5199.9

CountyARCHER
HighwayUS 281
FromSH 25
ToJACK COUNTY LINE
CSJ0249-04-039
Proj IDSTP 2013(624)
Work TypeREHABLIITAITION OF EXISTING ROAD
 
8.73710168493.2210065303.0798.9
Work Order05-08-15
Work Began07-13-15
Work Completed
Time Computed05-24-15
Contract Working Days345
Addl Days Granted3
Working Days Charged318
Percent Time Used91
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
W.S. CONSTRUCTION COMPANY (6.30)
CROSSROADS, L.P. (0.23)
STRIPING TECHNOLOGY, L.P. (1.55)
DUSTROL, INC. (2.47)
WOLFE CONSTRUCTION GROUP, INC. (0.85)
MARCOM"S MOWING SERVICE, LLC (0.35)
WEST TEXAS RUMBLE STRIP (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30)
TRP CONSTRUCTION GROUP, LLC (0.73)
Contract #03153034
Totals10168493.2210283.1610065303.0798.9

CountyCOOKE
HighwayFM 51
FromELM FORK TRINITY RIVER
ToONE HORSE LANE
CSJ0312-01-078
Proj IDSTP 2017(403)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.467706189.820.000.0
Work Order05-18-17
Work Began00-00-00
Work Completed
Time Computed06-17-17
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173233
Totals706189.820.000.000.0

CountyCLAY
HighwayFM 810
FromFM 171
ToSH 79
CSJ0391-02-018
Proj IDSTP 1702(124)
Work TypeREHABLITATION OF EXISTING ROAD
 
15.9031895820.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0391-02-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173003
Totals1895820.800.000.000.0

CountyYOUNG
HighwayFM 61
FromUS 380
ToFM 3003
CSJ0529-01-023
Proj IDSTP 1602(001)
Work TypeOVERLAY
 
8.7974288948.682944800.1968.6
Work Order06-24-16
Work Began08-03-16
Work Completed
Time Computed07-24-16
Contract Working Days186
Addl Days Granted19
Working Days Charged167
Percent Time Used81
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0529-01-023
W.S. CONSTRUCTION COMPANY (10.39)
DALLAS LITE AND BARRICADE INC. (0.41)
BARRICADES UNLIMITED (2.30)
HJC FARMS, INC. (1.63)
ZACK BURKETT CO. (29.82)
Contract #04163003
Totals4288948.6846312.502944800.1968.6

CountyWICHITA
HighwayFM 171
FromFM 890
ToCLAY COUNTY LINE
CSJ0681-01-021
Proj IDSTP 2015(875)HES
Work TypeREHABILITATION OF EXISTING ROADWAY
 
6.5774534926.904003833.3789.0
Work Order06-01-15
Work Began07-07-15
Work Completed
Time Computed07-02-15
Contract Working Days170
Addl Days Granted18
Working Days Charged224
Percent Time Used119
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0681-01-021
ALTUS TRAFFIC MANAGEMENT LLC (0.22)
W.S. CONSTRUCTION COMPANY (28.48)
BARRICADES UNLIMITED (1.45)
MARCOM"S MOWING SERVICE, LLC (0.40)
JE CASEY, LLC (2.03)
ZACK BURKETT CO. (27.96)
LONE STAR BARRIER SERVICES, LLC (0.57)
Contract #04153244
Totals4534926.900.004003833.3789.0

CountyWILBARGER
HighwayFM 91
FromFM 91 AT WANDERERS CREEK
To.
CSJ0702-01-014
Proj IDBR 2016(928)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7672458571.501797819.0273.1
Work Order06-02-16
Work Began09-13-16
Work Completed
Time Computed07-02-16
Contract Working Days187
Addl Days Granted0
Working Days Charged176
Percent Time Used94
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.47)
DALLAS LITE AND BARRICADE INC. (0.76)
BARRICADES UNLIMITED (1.40)
HOUSTON SAWING & DRILLING (0.30)
LANCO TURF & SEEDING, INC. (2.01)
MCL CONTRACTING, LLC (0.57)
Contract #04163019
Totals2458571.50112082.321797819.0273.1

CountyWICHITA
HighwayFM 369
FromAT FAIRWAY INT, NEAR HUGHES ST
ToNEAR MCNIEL AVE
CSJ0802-02-052
Proj IDSTP 2013(622)
Work TypeMISCELLANEOUS WORK
 
0.3311792483.501812890.4999.9
Work Order07-24-15
Work Began03-14-16
Work Completed
Time Computed08-23-15
Contract Working Days202
Addl Days Granted17
Working Days Charged213
Percent Time Used97
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-052
ALTUS TRAFFIC MANAGEMENT LLC (0.41)
OSCAR ORDUNO, INC. (2.96)
PEACHTREE CONSTRUCTION, LTD. (4.50)
J. E. GUZMAN CONSTRUCTION, INC. (3.90)
WOLFE CONSTRUCTION GROUP, INC. (0.29)
KLP COMMERCIAL, LLC (22.26)
LANCO TURF & SEEDING, INC. (0.27)
Contract #05153250
Totals1792483.505846.911812890.4999.9

CountyWICHITA
HighwayFM 369
FromNEAR US 82/277
ToLP 473/ SH 79 INTERCHANGE
CSJ0802-02-066
Proj IDNH 1602(002)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9412496814.421631199.1265.3
Work Order09-20-16
Work Began12-06-16
Work Completed
Time Computed10-20-16
Contract Working Days268
Addl Days Granted0
Working Days Charged126
Percent Time Used47
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-066
ALTUS TRAFFIC MANAGEMENT LLC (0.95)
W.O.E. CONSTRUCTION (0.38)
TRP CONSTRUCTION GROUP, LLC (11.76)
PEACHTREE CONSTRUCTION, LTD. (7.19)
LANCO TURF & SEEDING, INC. (1.23)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (25.12)
DOUBLE S CONSTRUCTION (0.52)
Contract #07163033
Totals2496814.4246221.991631199.1265.3

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
ToVARIOUS LOCATIONS DISTRICTWIDE
CSJ0903-00-083
Proj IDSTP 1702(126)
Work TypeTRAFFIC MANAGEMENT
 
1.000938930.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173214
Totals938930.000.000.000.0

CountyWICHITA
HighwayCS
FromON MAPLEWOOD AVENUE SOUTH BOUND AT
ToDRAINAGE DITCH
CSJ0903-03-083
Proj IDBR 2006(550)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2001293885.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173206
Totals1293885.000.000.000.0

CountyCOOKE
HighwayCR
FromCR 145 (CR 411) AT SOUTH FISH CREEK
To.
CSJ0903-15-082
Proj IDBR 2006(653)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.200837893.66653669.8078.0
Work Order01-25-17
Work Began03-13-17
Work Completed
Time Computed02-24-17
Contract Working Days107
Addl Days Granted0
Working Days Charged63
Percent Time Used58
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-082
TOTAL HIGHWAY MAINTENANCE, LLC (0.45)
WOLFE CONSTRUCTION GROUP, INC. (1.81)
MORRIS COUNTY CONTRACTORS, L.L.C. (5.40)
TEXAS SHAFTS, INC. (11.89)
Contract #12163034
Totals837893.66150469.00653669.8078.0

CountyYOUNG
HighwayFM 209
FromFM 578
To3.69 MI WEST OF SH 67
CSJ1076-02-040
Proj IDSTP 2017(881)
Work TypeRESTORATION
 
14.0332333357.95154577.956.6
Work Order04-19-17
Work Began06-16-17
Work Completed
Time Computed05-19-17
Contract Working Days213
Addl Days Granted0
Working Days Charged10
Percent Time Used4
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1076-02-040
W.S. CONSTRUCTION COMPANY (40.00)
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
COMEN ENTERPRISE LLC (3.42)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
Contract #03173036
Totals2333357.95154577.95154577.956.6

CountyMONTAGUE
HighwayFM 455
From1.056 MI WEST OF FM 730
To0.056 MI WEST OF FM 730
CSJ1352-02-021
Proj IDSTP 1702(127)HES
Work TypeHAZARD ELIMINATION SAFETY
 
1.000554791.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1352-02-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173205
Totals554791.650.000.000.0

CountyCOOKE
HighwayFM 1201
FromCR 406 NORTH OF MOSS LAKE
ToFM 1200
CSJ1356-01-027
Proj IDSTP 2017(273)
Work TypeRESTORATION
 
15.9171250025.00441140.0035.2
Work Order12-12-16
Work Began01-31-17
Work Completed
Time Computed01-11-17
Contract Working Days82
Addl Days Granted0
Working Days Charged65
Percent Time Used79
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1356-01-027
EROSION CONTROL MANAGEMENT SERVICES (2.60)
TOTAL HIGHWAY MAINTENANCE, LLC (1.68)
PEACHTREE CONSTRUCTION, LTD. (5.22)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
COMEN ENTERPRISE LLC (3.02)
Contract #11163017
Totals1250025.00112704.00441140.0035.2

CountyCOOKE
HighwayFM 678
FromFM 3164
To0.339 MILES SOUTH OF US 82.
CSJ1357-02-012
Proj IDSTP 1602(201)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
2.5451677816.781379806.7682.2
Work Order08-17-16
Work Began10-24-16
Work Completed
Time Computed09-16-16
Contract Working Days125
Addl Days Granted0
Working Days Charged104
Percent Time Used83
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1357-02-012
ALTUS TRAFFIC MANAGEMENT LLC (0.49)
W.S. CONSTRUCTION COMPANY (12.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
MARCOM"S MOWING SERVICE, LLC (0.52)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (8.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.52)
OSCAR ORDUNO, INC. (2.62)
Contract #06163009
Totals1677816.78482412.691379806.7682.2

CountyWICHITA
HighwayFM 2650
FromFM 369
ToARCHER COUNTY LINE
CSJ2644-01-010
Proj IDSTP 2013(623)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
3.4934231186.984195262.9699.1
Work Order07-22-15
Work Began01-18-16
Work Completed
Time Computed08-07-15
Contract Working Days149
Addl Days Granted80
Working Days Charged222
Percent Time Used96
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2644-01-010
ALTUS TRAFFIC MANAGEMENT LLC (0.18)
BARRICADES UNLIMITED (0.80)
HJC FARMS, INC. (1.87)
ZACK BURKETT CO. (33.52)
W.S. CONSTRUCTION COMPANY (5.56)
Contract #05153050
Totals4231186.982309.714195262.9699.1

page 1 | page 2 | page 3