Monthly State Let Construction Report For Wichita Falls District As Of Apr 10, 2015 Page 2 Of 3

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBAYLOR
Highway US 277
From KNOX COUNTY LINE
To 2.155 MILES WEST OF US 183
CSJ 0157-01-062
Proj ID NH 2013(235)
Work Type WIDEN NON - FREEWAY
 
11.161 11926754.60 0.00 11616158.43 97.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-06-13
Work Began 03-25-13
Work Completed  
Time Computed 03-25-13
Contract Working Days 385
Addl Days Granted 3
Working Days Charged 341
Percent Time Used 87
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-062
W.S. CONSTRUCTION COMPANY(5.68%)
CONTRACTORS SERVICE COMPANY(0.34%)
WEST TEXAS RUMBLE STRIP(0.07%)
ZACK BURKETT CO. ( 26.21%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.40%)
WILLIS ELECTRIC CO., LP(0.84%)
Contract # 12123202
Totals 11926754.60 0.00 11616158.43 97.3

CountyBAYLOR
Highway US 277
From NEAR SEYMOUR
To KNOX COUNTY LINE (NB LANES)
CSJ 0157-01-071
Proj ID NH 2014(791)
Work Type OVERLAY
 
11.862 2581730.36 15265.18 2697574.66 99.9
Work Order 07-10-14
Work Began 12-15-14
Work Completed  
Time Computed 07-26-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 60
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-071
COTHRAN TRUCKING, LLC(2.44%)
CONTRACTORS SERVICE COMPANY(0.13%)
DUSTROL, INC.(0.52%)
TRP CONSTRUCTION GROUP, LLC(2.31%)
Contract # 06143205
Totals 2581730.36 15265.18 2697574.66 99.9

CountyCOOKE
Highway IH 35
From ON IH 35
To AT ELM FORK TRINITY RIVER (NB)
CSJ 0195-01-098
Proj ID BR 2015(470)
Work Type BRIDGE MAINTENANCE
 
0.106 1473644.00 390369.48 390369.48 26.4
Work Order 03-12-15
Work Began 03-23-15
Work Completed  
Time Computed 03-28-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 6
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-098
N-LINE TRAFFIC MAINTENANCE, L.P. (8.41%)
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
MORRIS COUNTY CONTRACTORS, L.L.C.(3.29%)
S & S BRIDGE PAINTING, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.45%)
TEXOMA CONCRETE CUTTING, LLC (0.10%)
PENHALL COMPANY(0.30%)
WEBBER BARRIER SERVICES, LLC.(8.08%)
Contract # 01153009
Totals 1473644.00 390369.48 390369.48 26.4

CountyCLAY
Highway US 287
From NEAR LONE STAR ROAD
To APPROX. 0.5 MI S OF HAPGOOD LN
CSJ 0224-02-043
Proj ID SFT 224-2-43
Work Type HAZARD ELIMINATION SAFETY
 
0.923 612771.50 0.00 0.00 0.0
Work Order 11-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-28-14
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0224-02-043
TOTAL HIGHWAY MAINTENANCE, LLC (2.81%)
ZACH BURKETT CO. ( 38.56%)
Contract # 10143229
Totals 612771.50 0.00 0.00 0.0

CountyMONTAGUE
Highway SH 59
From SH 175
To FM 1758
CSJ 0239-02-034
Proj ID STP 2014(792)
Work Type REHABILITATION OF EXISTING ROAD
 
7.660 2026292.53 723834.83 1204771.38 59.4
Work Order 09-09-14
Work Began 02-09-15
Work Completed  
Time Computed 09-25-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 30
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0239-02-034
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
DUSTROL, INC.(0.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.29%)
STRIPING TECHNOLOGY, L.P.(2.48%)
BRENDA PRICE TRUCKING(0.53%)
Contract # 06143247
Totals 2026292.53 723834.83 1204771.38 59.4

CountyARCHER
Highway US 281
From SH 25
To JACK COUNTY LINE
CSJ 0249-04-039
Proj ID STP 2013(624)
Work Type REHABLIITAITION OF EXISTING ROAD
 
8.737 10168493.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153034
Totals 10168493.22 0.00 0.00 0.0

CountyCOOKE
Highway FM 51
From FM 1306
To FM 922
CSJ 0312-01-072
Proj ID STP 2013(469)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.855 2224039.60 2994.00 2366039.27 100.0
Work Order 07-31-13
Work Began 10-07-13
Work Completed 10-31-14
Time Computed 09-30-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 92
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-072
CROSSROADS, L.P. (0.13%)
DUSTROL, INC.(1.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
DALE BROWN, INC. (0.69%)
MCRYAN HAULING, INC. (0.79%)
Contract # 03133212
Totals 2224039.60 2994.00 2366039.27 100.0

CountyYOUNG
Highway SH 16
From GRAHAM CITY LIMITS
To PALO PINTO COUNTY LINE
CSJ 0362-01-046
Proj ID STP 2014(784)HES
Work Type HAZARD ELIMINATION AND SAFETY
 
10.385 183344.50 54637.00 165924.50 90.4
Work Order 07-10-14
Work Began 01-13-15
Work Completed  
Time Computed 07-26-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0362-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143044
Totals 183344.50 54637.00 165924.50 90.4

CountyWICHITA
Highway SH 258
From 0.2 MILES WEST OF FM 2226
To US 82
CSJ 0544-01-020
Proj ID STP 2013(903)HES
Work Type REHABILITATION OF EXISTING ROAD
 
7.000 3882193.04 9098.00 1843863.41 48.1
CountyWICHITA
Highway SH 258
From SH 25
To 0.2 MILES WEST OF FM 2226
CSJ 0544-01-021
Proj ID STP 2013(904)
Work Type REHABILITATION OF EXISTING ROAD
 
3.353 1941339.06 26769.75 672829.30 34.6
Work Order 12-19-13
Work Began 03-06-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 150
Addl Days Granted 12
Working Days Charged 183
Percent Time Used 112
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
ZACK BURKETT CO. ( 42.92%)
FLAT LINE, INC.(0.83%)
J.V. CONCRETE CONSTRUCTION ( 15.86%)
MARCOM"S MOWING SERVICE, LLC (2.74%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 09133206
Totals 5823532.10 35867.75 2516692.71 43.6

CountyWICHITA
Highway FM 171
From FM 890
To CLAY COUNTY LINE
CSJ 0681-01-021
Proj ID STP 2015(875)HES
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.577 4534926.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0681-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153244
Totals 4534926.90 0.00 0.00 0.0

CountyBAYLOR
Highway FM 422
From US 82
To EAST CITY LIMITS OF SEYMOUR
CSJ 0814-01-027
Proj ID C 814-1-27
Work Type UPGRADING OF A NON - FREEWAY FACILITY
 
0.847 3332046.95 0.00 3537521.78 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-12
Work Began 02-11-13
Work Completed 12-22-14
Time Computed 02-11-13
Contract Working Days 245
Addl Days Granted 21
Working Days Charged 255
Percent Time Used 95
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-027
W.S. CONSTRUCTION COMPANY( 37.37%)
CONTRACTORS SERVICE COMPANY(0.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.55%)
ZACK BURKETT CO. ( 26.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.02%)
WILLIS ELECTRIC CO., LP(8.41%)
Contract # 07123006
Totals 3332046.95 0.00 3537521.78 100.0

CountyCOOKE
Highway FM 373
From AT DRY ELM CREEK
To .
CSJ 0823-01-031
Proj ID BR 2015(601)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.241 1612050.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-15
Work Began 00-00-00
Work Completed  
Time Computed 04-18-15
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0823-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153003
Totals 1612050.20 0.00 0.00 0.0

CountyMONTAGUE
Highway FM 455
From MONTAGUE
To FM 1749
CSJ 0845-01-016
Proj ID STP 2013(686)
Work Type REHABILTATION OF EXISTING ROADWAY
 
14.179 3371976.79 45061.51 3971566.33 100.0
Work Order 09-04-13
Work Began 11-13-13
Work Completed 03-31-15
Time Computed 09-20-13
Contract Working Days 151
Addl Days Granted 30
Working Days Charged 115
Percent Time Used 63
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0845-01-016
CROSSROADS, L.P. (1.42%)
W.S. CONSTRUCTION COMPANY(1.54%)
MARCOM"S MOWING SERVICE, LLC (0.55%)
LANCO TURF & SEEDING, INC. (1.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.22%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (1.32%)
ALLIED DRILLING COMPANY(0.03%)
MCRYAN HAULING, INC. (1.01%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.12%)
Contract # 05133231
Totals 3371976.79 45061.51 3971566.33 100.0

CountyCOOKE
Highway FM 922
From MONTAGUE COUNTY LINE
To FM 373
CSJ 0845-03-056
Proj ID STP 2014(357)
Work Type RESTORATION
 
13.082 4230047.49 3500.00 335901.56 7.9
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 21
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.84%)
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
J.V. CONCRETE CONSTRUCTION (6.52%)
LONE STAR BARRIER SERVICES, LLC(3.84%)
MARCOM"S MOWING SERVICE, LLC (1.06%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.42%)
STORM WATER MANAGEMENT, INC. (0.96%)
Contract # 02143007
Totals 4230047.49 3500.00 335901.56 7.9

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-072
Proj ID STP 2014(086)
Work Type MISCELLANEOUS WORK
 
1.000 399924.61 24314.46 379196.70 94.8
Work Order 04-15-14
Work Began 08-25-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 92
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-072
ALTUS TRAFFIC MANAGEMENT LLC (2.07%)
Contract # 03143032
Totals 399924.61 24314.46 379196.70 94.8

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-073
Proj ID STP 2015(753)
Work Type SIGN UPGRADE
 
1.000 574221.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153029
Totals 574221.00 0.00 0.00 0.0

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 827900.35 1451495.56 46.3
Work Order 11-03-14
Work Began 01-07-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 17
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
W.S. CONSTRUCTION COMPANY(7.60%)
Contract # 09143037
Totals 3132333.32 827900.35 1451495.56 46.3

CountyWICHITA
Highway CR
From CR 126 (BOHNER ROAD) AT WILDHORSE
To CREEK
CSJ 0903-03-101
Proj ID BR 1102(538)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 323285.45 330.00 325664.70 99.9
Work Order 08-13-14
Work Began 10-08-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-101
ALTUS TRAFFIC MANAGEMENT LLC (0.79%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.03%)
DUSTIN ALLEN, INC. (2.90%)
WOLFE CONSTRUCTION GROUP, INC. (1.61%)
PEACHTREE CONSTRUCTION, LTD. (9.57%)
Contract # 07143039
Totals 323285.45 330.00 325664.70 99.9

CountyCLAY
Highway CR
From CR 151 (FRIENDSHIP ROAD) AT BUFFALO
To CREEK
CSJ 0903-06-017
Proj ID BR 2013(145)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.114 344865.50 45841.18 241907.00 70.1
Work Order 08-20-14
Work Began 12-09-14
Work Completed  
Time Computed 11-18-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 61
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-06-017
TEXAS ALTERNATIVE GRASSER, INC.(1.74%)
ODUM SERVICES, L.P.(3.69%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 06143011
Totals 344865.50 45841.18 241907.00 70.1

CountyCOOKE
Highway CR
From CR 145 (CR 411) AT BLACK HOLLOW CRK
To .
CSJ 0903-15-081
Proj ID BR 2006(652)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.300 1009366.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 00-00-00
Work Completed  
Time Computed 04-11-15
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153238
Totals 1009366.40 0.00 0.00 0.0

page 1 | page 2 | page 3