Letting Schedule for February, 2008 (FY 2008)
Letting Schedule for February, 2008 (FY 2008) | ||||
Last Update: Monday, February 2, 2009 |
February, 2008 (FY 2008) | (see Links) |
SEP 2007 | OCT 2007 | NOV 2007 | DEC 2007 | JAN 2008 | FEB 2008 | MAR 2008 | APR 2008 | MAY 2008 | JUN 2008 | JUL 2008 | AUG 2008 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0271-02-054 | Austin/ Yoakum |
IH 10 | Actual | $1,923,225 | 12 | WIDEN BRIDGES AND APPROACHES |
0231-03-120 | Bell/ Waco |
US 190 | Actual | $2,534,034 | 3 | REALIGN RAMPS AND WIDEN FRONTAGE ROADS |
0521-05-132 | Bexar/ San Antonio |
IH 410 | Actual | $2,777,187 | 11 | CONSTRUCT RAMP AND CONSTRUCT TURNAROUNDS AT MOURSUND ROAD |
0915-00-141 | Bexar/ San Antonio |
VA | Actual | $1,030,380 | 10 | COMMUNICATION LINK BTWN TXDOT TRANSPORTATION MANAGMENT CTRS |
1020-01-038 | Bowie/ Atlanta |
FM 559 | Actual | $11,515,994 | 8 | RECONSTRUCT 2 LANE RURAL TO 4 LANE DIVIDED URBAN HIGHWAY |
1198-02-017 | Burnet/ Austin |
RM 963 | Actual | $471,751 | 6 | REPLACE BRIDGE AND APPROACHES |
0248-08-007 | Camp/ Atlanta |
FM 3384 | Actual | $1,363,513 | 6 | REPLACE BRIDGE AND APPROACHES |
0047-14-063 | Collin/ Dallas |
US 75 | Actual | $25,662,948 | 7 | RECONSTRUCT INTERCHANGE |
0535-08-076 | Colorado/ Yoakum |
IH 10 | Actual | $14,883,755 | 6 | CONSTRUCT ADDITIONAL LANES (E & W) |
2374-02-128 | Dallas/ Dallas |
IH 635 | Actual | $15,926 | 10 | LANDSCAPE DEVELOPMENT |
0918-46-064 | Denton/ Dallas |
CR | Actual | $444,201 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-130 | Denton/ Dallas |
VA | Actual | $170,100 | 9 | LANDSCAPING AND IRRIGATION OF MORRIS ROAD MEDIAN FOR APPROX |
2980-01-008 | Denton/ Dallas |
FM 2934 | Actual | $21,211,560 | 10 | WIDEN EXISTING 2 LANE RURAL TO 6 LANE DIVIDED URBAN HIGHWAY |
0906-00-116 | Ector/ Odessa |
VA | Actual | $984,399 | 10 | CURB RAMPS |
0535-07-044 | Fayette/ Yoakum |
IH 10 | Actual | $1,485,225 | 12 | WIDEN 2 BRIDGES AND APPROACHES |
3302-01-013 | Grimes/ Bryan |
FM 2562 | Actual | $1,443,326 | 1 | RESTORE EXISTING ROAD CONSISTING OF GRADING, BASE, ONE CRSE |
0909-29-036 | Hamilton/ Waco |
CR | Actual | $677,705 | 6 | REPLACE BRIDGE AND APPROACHES |
0271-14-216 | Harris/ Houston |
IH 610 | Actual | $37,000 | 10 | INSTALL PIER PROTECTION FOR EXISTING BRIDGE COLUMNS, |
0912-00-354 | Harris/ Houston |
VA | Actual | $1,875,000 | 9 | PLANNING AND FEASIBILITY STUDIES FOR LIVABLE CENTERS |
0912-72-159 | Harris/ Houston |
VA | Actual | $449,753 | 1 | REPLACEMENT, ADDITION OR REMOVAL OF VERTICAL CLEARANCE SIGNS |
0912-72-165 | Harris/ Houston |
CS | Actual | $1,575,000 | 7 | ITS UPGRADES (FY 2009) |
0912-72-166 | Harris/ Houston |
CS | Actual | $1,653,750 | 7 | ITS UPGRADES (FY 2010) |
0912-72-167 | Harris/ Houston |
VA | Actual | $1,823,259 | 7 | ITS CAPITAL UPGRADES (FY 2011) |
0912-72-169 | Harris/ Houston |
VA | Actual | $607,753 | 7 | INSTALL EMERGENCY GENERATOR |
0912-72-170 | Harris/ Houston |
VA | Actual | $206,636 | 7 | UPGRADE TELEPHONE SWITCH |
0912-72-171 | Harris/ Houston |
VA | Actual | $230,946 | 7 | INSTALL TELECONFERENCING, VIDEOCONFERENCING AND MANAGEMENT |
0912-72-172 | Harris/ Houston |
VA | Actual | $2,625,000 | 7 | TRANSTAR COMPUTER ROOM EXPANSION |
3256-01-091 | Harris/ Houston |
BW 8 | Actual | $142,831 | 1 | REPAIR BRIDGE |
0495-10-078 | Harrison/ Atlanta |
IH 20 | Actual | $1,846,854 | 6 | REHABILITATE BRIDGE AND APPROACHES |
0862-01-041 | Hidalgo/ Pharr |
FM 492 | Actual | $786,799 | 1 | WIDEN TO 4 LANE DIVIDED |
0920-00-084 | Jefferson/ Beaumont |
VA | Actual | $348,302 | 11 | RESTRIPING OF EXISTING ROADWAY, ON STATE - SYSTEM |
1091-01-017 | Kaufman/ Dallas |
FM 740 | Actual | $342,185 | 1 | CONSTRUCT RIGHT TURN LANE AND SIGNAL UPGRADES |
0762-02-040 | Liberty/ Beaumont |
FM 1409 | Actual | $3,615,600 | 6 | REPLACE BRIDGE AND APPROACHES |
0905-06-051 | Lubbock/ Lubbock |
VA | Actual | $2,768,679 | 1 | BRIDGE REPLACEMENT, STRUCTURE REPAIR AND PAINTING |
2060-01-033 | McLennan/ Waco |
FM 2113 | Actual | $799,153 | 1 | ADDITION OF TURN LANES AND TRAFFIC SIGNALS |
2263-02-079 | Nueces/ Corpus Christi |
SH 361 | Actual | $10,883,927 | 1 | REPLACE BRIDGE AND APPROACHES |
0003-06-083 | Reeves/ Odessa |
IH 20 | Actual | $3,849,849 | 1 | PAVEMENT OVERLAY |
0917-18-039 | Robertson/ Bryan |
VA | Actual | $894,600 | 9 | TRANSPORTATION ENHANCEMENT PROJECT CONSISTING OF THE |
0345-01-054 | Smith/ Tyler |
SH 110 | Actual | $2,034,700 | 1 | RESTORE PAVEMENT & RESURFACE ROADWAY |
0495-04-059 | Smith/ Tyler |
IH 20 | Actual | $266,792 | 1 | CLEAN AND SEAL BRIDGE JOINTS |
0570-02-021 | Stephens/ Brownwood |
FM 207 | Actual | $760,577 | 1 | WIDEN, BASE OVERLAY, ONE COURSE SURFACE TREATMENT |
0923-22-018 | Stephens/ Brownwood |
VA | Actual | $394,754 | 11 | GUARDRAIL AND BRIDGE RAIL REPLACEMENT |
0172-06-068 | Tarrant/ Fort Worth |
US 287 | Actual | $2,898,949 | 1 | REHABILITATE BRIDGE |
2266-02-127 | Tarrant/ Fort Worth |
SH 360 | Actual | $55,975,101 | 6 | RECONSTRUCT FREEWAY INTERCHANGE WITH SH 180 INCLUDING |
0054-01-022 | Taylor/ Abilene |
US 84 | Actual | $7,528,118 | 6 | REHABILITATE BRIDGE |
0907-00-073 | Tom Green/ San Angelo |
VA | Actual | $1,053,244 | 10 | CONSTRUCT CURB RAMPS |
2102-01-059 | Travis/ Austin |
RM 2244 | Actual | $593,102 | 1 | OVERLAY & FULL DEPTH REPAIR |
0675-07-082 | Walker/ Bryan |
IH 45 | Actual | $13,777,980 | 1 | UPGRADING OF A FREEWAY FACILITY CONSISTING OF GRADING, |
0917-27-029 | Walker/ Bryan |
CR | Actual | $682,628 | 6 | REPLACEMENT OF AN EXISTING BRIDGE FACILITY CONSISTING OF |
0156-03-044 | Wichita/ Wichita Falls |
SH 240 | Actual | $1,736,639 | 1 | NOVACHIP |
0156-09-014 | Wichita/ Wichita Falls |
LP 267 | Actual | $1,053,858 | 11 | ADD CURB AND GUTTER, STORM SEWER, SET, SEAL COAT, HOT MIX |
0337-02-038 | Williamson/ Austin |
SH 29 | Actual | $980,856 | 1 | ADD CENTER TURN LANE AND ACCELERATION / DECELERATION LANES |
0986-01-040 | Williamson/ Austin |
FM 619 | Actual | $414,178 | 8 | PROVIDE ADD'TL PAVED SURFACE WIDTH |
|
|