Detail Letting Schedule for Webb County (FY 2013)
Webb County (FY 2013) |
CCSJ: 0018-06-170 | |||
District: | Laredo | Let Date: | JUL 2013 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 0351(089) | CSJ: | 0018-06-170 |
Description: | CONCRETE PAVEMENT DIAMOND GRINDING | Handling Code: |
|
Limits From: | HIDALGO ST. | Fund Cat: | 1 |
Limits To: | 1.097 MI NORTH OF HIDALGO STREET | Estimate: | $402,233 |
Length: | 0.8 Miles | Actual: | $560,281 |
District: | Laredo | Let Date: | JUL 2013 |
Highway: | SL 20 | Let Status: | Actual |
Project ID: | STP 2013(859) | CSJ: | 0086-14-059 |
Description: | CONCRETE PAVEMENT DIAMOND GRINDING | Handling Code: |
|
Limits From: | 0.374 MI EAST OF GSA FACILITIES | Fund Cat: | 1 |
Limits To: | 0.402 MI EAST OF IH35/SL20 INTER | Estimate: | $625,183 |
Length: | 2.8 Miles | Actual: | $1,027,001 |
District: | Laredo | Let Date: | JUL 2013 |
Highway: | FM 1472 | Let Status: | Actual |
Project ID: | NH 2013(858) | CSJ: | 2150-04-058 |
Description: | CONCRETE PAVEMENT DIAMOND GRINDING | Handling Code: |
|
Limits From: | 0.15 MI SOUTH OF SL 20 | Fund Cat: | 1 |
Limits To: | 0.494 MI NORTH OF SL 20 | Estimate: | $199,769 |
Length: | 0.6 Miles | Actual: | $320,848 |
Back... |
Totals for 0018-06-170 | ||
---|---|---|---|
Length: | 4.2 Miles | ||
Estimate: | $1,227,185 | ||
Actual: | $1,908,130 | ||
CCSJ: 0018-06-171 | |||
District: | Laredo | Let Date: | AUG 2013 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 0351(090) | CSJ: | 0018-06-171 |
Description: | INSTALL DUAL LEFT TURN LANES | Handling Code: |
|
Limits From: | INT OF IH 35 AND SL 20 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $329,016 |
Length: | 0.1 Miles | Actual: | $457,814 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0037-03-079 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT OF US 83 WITH FM 65 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $144,271 |
Length: | 0.1 Miles | Actual: | $194,278 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0037-05-047 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | US 83 AT FM 1407 NORTH | Fund Cat: | 11 |
Limits To: | . | Estimate: | $15,836 |
Length: | 0.1 Miles | Actual: | $24,483 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0037-05-048 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | US 83 AT FM 1407 SOUTH | Fund Cat: | 11 |
Limits To: | . | Estimate: | $142,319 |
Length: | 0.1 Miles | Actual: | $180,262 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | NH 2013(970) | CSJ: | 0037-06-089 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT OF US 83 WITH FM 1557 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $16,080 |
Length: | 0.2 Miles | Actual: | $24,903 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | NH 2013(970) | CSJ: | 0037-06-090 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | US 83 AT FM 1917 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $27,529 |
Length: | 0.1 Miles | Actual: | $45,157 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | NH 2013(970) | CSJ: | 0037-06-091 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT OF US 83 WITH FM 190 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $135,775 |
Length: | 0.1 Miles | Actual: | $166,619 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2013(970) | CSJ: | 0300-03-064 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | US 277 AT LOOP 517 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $77,416 |
Length: | 0.1 Miles | Actual: | $93,329 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | FM 186 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0301-04-016 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT OF FM 186 WITH FM 3252 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $30,076 |
Length: | 0.1 Miles | Actual: | $48,261 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0483-01-047 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT SH 97 AND FM 469 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $16,568 |
Length: | 0.1 Miles | Actual: | $25,242 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | FM 624 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 0652-04-054 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INT OF FM 624 WITH FM 469 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $15,369 |
Length: | 0.1 Miles | Actual: | $23,891 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | FM 1021 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 1229-01-060 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | INTERSECTION OF FM 2030 EAST | Fund Cat: | 11 |
Limits To: | . | Estimate: | $15,434 |
Length: | 0.1 Miles | Actual: | $24,036 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | FM 468 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 1545-02-020 |
Description: | INTERSECTION IMPROVMENTS | Handling Code: |
|
Limits From: | INT OF FM 468 AND FM 469 | Fund Cat: | 11 |
Limits To: | . | Estimate: | $20,770 |
Length: | 0.1 Miles | Actual: | $33,312 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | FM 1472 | Let Status: | Actual |
Project ID: | STP 2013(969) | CSJ: | 2150-04-059 |
Description: | INSTALL DUAL LEFT TURN LANES | Handling Code: |
|
Limits From: | MILEPOINT 30.18 | Fund Cat: | 11 |
Limits To: | MILEPOINT 30.4 | Estimate: | $235,295 |
Length: | 0.2 Miles | Actual: | $482,865 |
Back... |
Totals for 0018-06-171 | ||
Length: | 1.6 Miles | ||
Estimate: | $1,221,754 | ||
Actual: | $1,824,452 | ||
CCSJ: 0038-01-074 | |||
District: | Laredo | Let Date: | DEC 2012 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | NH 2013(263) | CSJ: | 0038-01-074 |
Description: | MICROSEAL | Handling Code: |
|
Limits From: | 0.054 MI S OF KCS RAILROAD CROSSING | Fund Cat: | 1 |
Limits To: | CHACON CREEK BRIDGE | Estimate: | $354,106 |
Length: | 0.8 Miles | Actual: | $359,231 |
Official Notice Back... |
Totals for 0038-01-074 | ||
Length: | 0.8 Miles | ||
Estimate: | $354,106 | ||
Actual: | $359,231 | ||
CCSJ: 0086-14-057 | |||
District: | Laredo | Let Date: | DEC 2012 |
Highway: | SL 20 | Let Status: | Actual |
Project ID: | HP 2013(217) | CSJ: | 0086-14-057 |
Description: | FOR THE CONSTRUCTION OF INTERCHANGE FACILITY OVER MCPHERSON | Handling Code: |
|
Limits From: | 0.5 MI W OF MCPHERSON | Fund Cat: | 12 |
Limits To: | 0.5 MI E OF MCPHERSON | Estimate: | $11,082,762 |
Length: | 1.0 Miles | Actual: | $14,584,015 |
Back... |
Totals for 0086-14-057 | ||
Length: | 1.0 Miles | ||
Estimate: | $11,082,762 | ||
Actual: | $14,584,015 | ||
CCSJ: 0237-03-025 | |||
District: | Laredo | Let Date: | JAN 2013 |
Highway: | SH 44 | Let Status: | Actual |
Project ID: | STP 2013(344) | CSJ: | 0237-03-025 |
Description: | MILLING, OVERLAY, GUARDRAIL, AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | LA_SALLE COUNTY LINE | Fund Cat: | 1 |
Limits To: | 13.947 MI EAST | Estimate: | $5,361,590 |
Length: | 13.9 Miles | Actual: | $4,993,409 |
Back... |
Totals for 0237-03-025 | ||
Length: | 13.9 Miles | ||
Estimate: | $5,361,590 | ||
Actual: | $4,993,409 | ||
CCSJ: 0922-00-054 | |||
District: | Laredo | Let Date: | AUG 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2013(938)G | CSJ: | 0922-00-054 |
Description: | METAL BEAM GUARD FENCE AND SGT UPGRADE | Handling Code: |
|
Limits From: | DISTRICTWIDE | Fund Cat: | 11 |
Limits To: | WEBB COUNTY, ETC. | Estimate: | $573,629 |
Length: | 0.1 Miles | Actual: | $578,206 |
Back... |
Totals for 0922-00-054 | ||
Length: | 0.1 Miles | ||
Estimate: | $573,629 | ||
Actual: | $578,206 | ||
CCSJ: 0922-33-091 | |||
District: | Laredo | Let Date: | AUG 2013 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2006(089) | CSJ: | 0922-33-091 |
Description: | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING | Handling Code: |
|
Limits From: | ON LAS TIENDAS RD @ TEJONES CREEK, | Fund Cat: | 6 |
Limits To: | PALITO BLANCO ARROYO | Estimate: | $450,308 |
Length: | 0.4 Miles | Actual: | $476,271 |
Back... |
Totals for 0922-33-091 | ||
Length: | 0.4 Miles | ||
Estimate: | $450,308 | ||
Actual: | $476,271 | ||
CCSJ: 0922-33-135 | |||
District: | Laredo | Let Date: | AUG 2013 |
Highway: | CS | Let Status: | Actual |
Project ID: | CBI 2012(588) | CSJ: | 0922-33-133 |
Description: | NEW LOCATION NON - FREEWAY ROAD | Handling Code: |
LC |
Limits From: | AT CIELITO LINDO AVE | Fund Cat: | 3 |
Limits To: | SL 20 INTERSECTION | Estimate: | $2,102,992 |
Length: | 0.5 Miles | Actual: | $1,904,233 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | CS | Let Status: | Actual |
Project ID: | CBI 2012(589) | CSJ: | 0922-33-134 |
Description: | NEW LOCATION NON - FREEWAY ROAD | Handling Code: |
LC |
Limits From: | AT LOS PRESIDENTE BLVD | Fund Cat: | 3 |
Limits To: | SL 20 INTERSECTION | Estimate: | $167,452 |
Length: | 0.0 Miles | Actual: | $170,663 |
District: | Laredo | Let Date: | AUG 2013 |
Highway: | CS | Let Status: | Actual |
Project ID: | CBI 2012(590) | CSJ: | 0922-33-135 |
Description: | NEW LOCATION NON - FREEWAY ROAD | Handling Code: |
LC |
Limits From: | AT SOUTHGATE BLVD | Fund Cat: | 3 |
Limits To: | SL20 INTERSECTION | Estimate: | $3,034,957 |
Length: | 0.6 Miles | Actual: | $2,862,817 |
Back... |
Totals for 0922-33-135 | ||
Length: | 1.1 Miles | ||
Estimate: | $5,305,401 | ||
Actual: | $4,937,713 |
|