Letting Schedule for Lufkin District (FY 2015)

Last Update: Monday, August 18, 2014
Lufkin District (FY 2015)
Angelina | Houston | Nacogdoches | Polk | Sabine | San Augustine | Shelby | Trinity

Angelina County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0176-02-094 BU 59-G Approved SEP 2014 $11,391,400 6 REPLACE RAILROAD UNDERPASS
0176-13-006 FM 3439 Tentative JUL 2015 $403,122 1 RECONSTRUCT AND WIDEN PAVEMENT
0200-13-011 SS 278 Tentative JAN 2015 $838,846 3 DRAINAGE IMPROVEMENTS
0911-00-074 VA Tentative JUN 2015 $450,000 10 CONSTRUCT CURB RAMPS IN NACOGDOCHES, SAN AUGUSTINE, AND
0911-38-068 VA Tentative JAN 2015 $1,104,000 3 CONSTRUCT SIDEWALKS TO PROMOTE PEDESTRIAN TRAFFIC ALONG
2959-01-009 FM 706 Tentative MAY 2015 $747,623 8 SAFETY TREAT FIXED OBJECTS

Houston County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0117-07-040 SH 21 Tentative JUL 2015 $10,839,678 1 RECONSTRUCT PAVEMENT AND ADD PASSING LANES
0336-01-046 SH 7 Approved SEP 2014 $10,482,016 1 RECONSTRUCT PAVEMENT AND ADD PASSING LANES & SHLDRS
0911-28-031 CR Tentative JUN 2015 $591,000 6 REPLACE BRIDGE AND APPROACHES
0937-03-013 FM 227 Tentative JUN 2015 $1,249,400 6 REPLACE BRIDGES AND APPROACHES

Nacogdoches County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0706-03-020 FM 95 Tentative JUL 2015 $1,217,400 6 REPLACE BRIDGE AND APPROACHES
1810-01-028 FM 1878 Tentative FEB 2015 $1,406,000 11 WIDEN FROM 2 TO 4 LANES AND ADD CURB & GUTTER
3490-01-003 FM 3314 Tentative FEB 2015 $568,130 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH

Polk County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0176-05-177 US 59 Tentative JAN 2015 $1,545,000 11 PLANE, SEAL AND RESURFACE WITH PFC (SB LANES ONLY)
0911-04-056 CR Tentative FEB 2015 $748,000 6 REPLACE BRIDGE AND APPROACHES
0911-04-059 CR Tentative JUL 2015 $1,198,100 6 REPLACE BRIDGE AND APPROACHES
0911-04-060 CR Tentative JUL 2015 $954,200 6 REPLACE BRIDGE AND APPROACHES
0911-04-066 CR Tentative MAR 2015 $1,278,625 3 CONSTRUCT FUTURE FM ROADWAY TO THE GEORGIA PACIFIC FACILITY
1876-01-030 FM 1988 Tentative APR 2015 $2,400,300 6 REPLACE BRIDGE AND APPROACHES

Sabine County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0064-06-052 US 96 Approved DEC 2014 $1,919,000 1 RESURFACE WITH MICROSURFACING

San Augustine County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0118-10-055 SH 21 Approved SEP 2014 $3,313,588 1 INTERSECTION IMPROVEMENTS INCLUDING INSTALLATION OF TRAFFIC
0809-04-046 US 96 Tentative MAY 2015 $2,502,000 6 REPLACE BRIDGE AND APPROACHES
1079-01-031 FM 705 Approved DEC 2014 $639,528 8 SAFETY TREAT FIXED OBJECTS

Shelby County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0123-08-010 FM 415 Tentative JUL 2015 $848,200 6 REPLACE BRIDGE AND APPROACHES
0742-01-052 FM 139 Approved NOV 2014 $2,067,489 8 IMPROVE GUARDRAIL TO DESIGN STANDARDS AND SAFETY TREAT FIXED
0911-39-042 CR Tentative FEB 2015 $1,372,000 6 REPLACE BRIDGE AND APPROACHES

Trinity County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0109-07-050 SH 19 Approved NOV 2014 $8,030,601 1 RESURFACE WITH SEAL COAT
0319-01-063 SH 94 Approved OCT 2014 $1,009,372 8 SAFETY TREAT FIXED OBJECTS
0319-02-029 SH 94 Approved OCT 2014 $1,877,089 8 SAFETY TREAT FIXED OBJECTS


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract