Letting Schedule for January, 2015 (FY 2015)

Last Update: Monday, December 15, 2014
January, 2015 (FY 2015) (see Links)
SEP 2014 | OCT 2014 | NOV 2014 | DEC 2014 | JAN 2015 | FEB 2015 | MAR 2015 | APR 2015 | MAY 2015 | JUN 2015 | JUL 2015 | AUG 2015
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0910-08-062 Anderson/
Tyler
CR Approved $267,162 6 REPLACE BRIDGE AND APPROACHES
3409-01-004 Bell/
Waco
FM 3481 Approved $1,360,092 3 CONSTRUCT LEFT TURN LANE AT WAL - MART IN HARKER HEIGHTS
0915-12-439 Bexar/
San Antonio
CR Approved $567,010 6 REHABILITATE BRIDGE AND APPROACHES
0912-31-289 Brazoria/
Houston
CS Approved $27,244,344 3 WIDENING TO 4 LANES DIVIDED WITH RAISED MEDIAN
0117-01-046 Brazos/
Bryan
SH 21 Approved $2,493,955 1 SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING,
1316-01-059 Brazos/
Bryan
FM 1179 Approved $2,175,967 1 OVERLAY CONSISTING OF MILLING, HMA OVERLAY AND PAVEMENT
0925-00-063 Childress/
Childress
VA Approved $1,183,643 1 DISTRICT WIDE STRIPING
0016-04-109 Comal/
San Antonio
IH 35 Approved $1,053,178 8 INSTALL PROFILE PAVEMENT MARKINGS ALONG CENTERLINE
0183-01-037 Comanche/
Brownwood
SH 36 Approved $4,519,884 6 BASE OVERLAY AND 2 COURSE SURFACE TREATMENT
0044-07-068 Cooke/
Wichita Falls
US 82 Approved $139,829 3 LANDSCAPE
0195-01-098 Cooke/
Wichita Falls
IH 35 Approved $917,237 6 REPLACE BRIDGE DECK
0020-02-018 Culberson/
El Paso
US 90 Approved $4,839,449 1 ROADWAY REHABILITATION
0749-04-011 Delta/
Paris
FM 1533 Approved $2,103,544 1 REHAB EXISTING ROADWAY
0001-02-056 El Paso/
El Paso
SH 20 Approved $6,172,000 8 TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) , CENTERLINE T
0568-01-046 Ellis/
Dallas
SH 34 Approved $248,752 1 TEXTURE SHOULDERS AND CENTER LINE TEXTURING
1211-01-018 Ellis/
Dallas
FM 984 Approved $2,329,600 6 REPLACE BRIDGE AND APPROACHES
0535-07-048 Fayette/
Yoakum
IH 10 Approved $7,997,727 1 ASPHALTIC CONCRETE PAVEMENT
0453-07-013 Floyd/
Lubbock
SH 207 Approved $10,497,820 11 REHABILITATION OF EXISTING ROADWAY
0291-01-049 Gillespie/
San Antonio
SH 16 Approved $13,899,903 1 UPGRADE TO SUPER 2 AND ADD LEFT TURN LANES
0143-06-029 Gonzales/
Yoakum
US 87 Approved $5,341,432 1 PAVEMENT REPAIR AND SURFACING
0348-01-013 Gonzales/
Yoakum
SH 80 Approved $2,889,225 1 RESTORE ROADWAY
0913-22-043 Gonzales/
Yoakum
CR Approved $284,750 6 REPLACE BRIDGE AND APPROACHES
0397-01-043 Gray/
Amarillo
SH 152 Approved $6,366,095 1 OVERLAY
0704-03-014 Hall/
Childress
FM 94 Approved $5,595,382 1 WIDENING OF NON - FREEWAY FACILITY
0467-01-008 Hamilton/
Waco
SH 220 Approved $506,376 1 SEAL / INLAY
0051-02-088 Harris/
Houston
SH 3 Approved $842,383 1 DRAINAGE IMPROVEMENTS
0508-07-286 Harris/
Houston
SS 330 Approved $1,491,436 3 LEFT TURN LANE IMPROVEMENTS AT VARIOUS LOCATIONS ON THE
0912-71-003 Harris/
Houston
CS Approved $9,921,336 3 ROADWAY RECONSTRUCTION
0912-72-072 Harris/
Houston
CS Approved $10,200,000 3 RECONSTRUCT & WIDEN TO 6 LANES INCLUDING 10 FT SHARED - USE
0912-72-289 Harris/
Houston
CS Approved $1,827,969 3 CONSTRUCTING A PEDESTRIAN BRIDGE AT BRINGHURST STREET IN
1812-01-021 Harris/
Houston
FM 1942 Approved $1,269,235 1 CONSTRUCT LEFT TURN LANE
0286-01-055 Hays/
Austin
SH 80 Approved $245,021 10 LANDSCAPING AND IRRIGATION
0030-05-063 Hemphill/
Amarillo
US 83 Approved $8,246,988 1 OVERLAY, JRCP JOINT REPAIR
0342-01-087 Hidalgo/
Pharr
SH 107 Approved $3,576,792 1 OVERLAY
0768-02-020 Hunt/
Paris
FM 513 Approved $1,469,902 1 REHAB EXISTING ROADWAY
1494-02-008 Kaufman/
Dallas
FM 1565 Approved $1,799,800 1 PROVIDE ADDITIONAL PAVEMENT SURFACE AND OVERLAY
0102-06-030 Kleberg/
Corpus Christi
SH 285 Approved $13,486,634 8 MILL, FILL MAINLANES, SEAL COAT FULL WIDTH
0254-01-137 Live Oak/
Corpus Christi
US 281 Approved $4,925,624 1 SPOT BASE REPAIR AND OVERLAY
0905-06-093 Lubbock/
Lubbock
VA Approved $1,603,415 11 MISCELLANEOUS CONSTRUCTION
1155-01-016 Martin/
Odessa
FM 846 Approved $7,859,515 1 ROADWAY RESTORATION
2174-01-016 McLennan/
Waco
FM 2311 Approved $3,599,329 1 WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND
1259-01-039 Montgomery/
Houston
FM 1097 Approved $4,542,506 1 BASE REPAIR AND 1.5" ACP O / L
0355-04-039 Ochiltree/
Amarillo
SH 15 Approved $11,534,046 1 2" OVERLAY
0920-30-067 Orange/
Beaumont
VA Approved $602,173 3 UPGRADE THE RAIL WITHIN THE PORT
0176-05-177 Polk/
Lufkin
US 59 Approved $1,807,267 1 PLANE, SEAL AND RESURFACE WITH PFC (SB LANES ONLY)
0003-06-087 Reeves/
Odessa
IH 20 Approved $5,179,005 1 SEAL COAT & PAVEMENT MARKINGS
0123-05-014 Rusk/
Tyler
US 84 Approved $953,871 1 PLANE & RESURFACE ROADWAY
0231-14-017 San Saba/
Brownwood
FM 580 Approved $4,992,220 1 REHAB EXISTING ROAD, PROVIDE ADDITIONAL PAVED SURFACE WIDTH,
1873-02-022 Scurry/
Abilene
FM 1269 Approved $3,575,464 1 REHAB & WIDEN
0790-03-023 Sherman/
Amarillo
SH 15 Approved $2,157,502 1 REHABILITATION AND RE - DESIGNATION OF CR TO SH
0106-06-033 Stonewall/
Abilene
SH 283 Approved $7,121,939 1 SEAL COAT
0006-04-071 Taylor/
Abilene
IH 20 Approved $4,280,317 1 PLANING EXISTING SURFACE, FLEXIBLE PAVEMENT STRUCTURE REPAIR
2150-04-062 Webb/
Laredo
FM 1472 Approved $10,091,760 1 RESURFACE OF EXISTING HIGHWAY
0913-09-061 Wharton/
Yoakum
CR Approved $820,600 6 REPLACE BRIDGE AND APPROACHES
0761-01-019 Wheeler/
Childress
FM 592 Approved $7,604,183 1 WIDENING OF A NON FREEWAY FACILITY
0013-06-042 Wise/
Fort Worth
US 81 Approved $3,805,870 8 2" HMAC OVERLAY SB LANES, 2 CST SHOULDERS, SPOT SHLDR REPAIR
0902-20-109 Wise/
Fort Worth
VA Approved $5,687,572 1 CONSTRUCT DECEL / ACCEL LANES; INTERSECTION IMPROVEMENTS
0190-02-038 Wood/
Tyler
SH 37 Approved $7,037,813 1 REPAIR PAVEMENT & RESURFACE ROADWAY
0297-01-012 Yoakum/
Lubbock
US 380 Approved $12,273,667 11 REHABILITATION OF EXISTING ROAD
0297-02-015 Yoakum/
Lubbock
US 82 Approved $10,183,494 11 REHABILITATION OF EXISTING ROAD


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract