Detail Letting Schedule for Goliad County (FY 2019)

Last Update: Monday, November 13, 2017
Goliad County (FY 2019)

CCSJ: 0155-03-037

District:CORPUS CHRISTILet Date:May 2019
Highway:US 183Let Status:Tentative
Project ID:BR 1502(573)CSJ:0155-03-037
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:ON US 183 STR5 AT MANAHUILLA CREEKFund Cat:6
Limits To:2.3 MI. N. OF US 59ESTIMATE:$3,220,000
Length:0.1Actual$0
 
District:CORPUS CHRISTILet Date:May 2019
Highway:US 183Let Status:Tentative
Project ID:STP ( )HESCSJ:0155-02-031
Description:MODERNIZE BRIDGE RAIL AND APPROACH GUARDRAIL,IMPROVE GUARDRAHandling
Code:
 
Limits From:1.621 MI S OF FM 237Fund Cat:8
Limits To:SH 119 (INTERSECTION CB)ESTIMATE:$95,068
Length:7.1Actual$0
 
District:CORPUS CHRISTILet Date:May 2019
Highway:US 183Let Status:Tentative
Project ID:STP ( )HESCSJ:0155-03-041
Description:MODERNIZE BRIDGE RAIL AND APPROACH GUARDRAIL,IMPROVE GUARDRAHandling
Code:
 
Limits From:SH 119 (INTERSECTION CB)Fund Cat:8
Limits To:US 59ESTIMATE:$120,995
Length:8.9Actual$0
 
Back...
Totals for 0155-03-037
Length:16.1
Estimate:$3,436,063
Actual:

CCSJ: 0516-02-029

District:CORPUS CHRISTILet Date:Jun 2019
Highway:SH 239Let Status:Tentative
Project ID:STP ( )CSJ:0516-02-029
Description:REHAB AND WIDENHandling
Code:
 
Limits From:0.2 MI WEST OF FM 2442Fund Cat:1
Limits To:N INTERS. OF FM 2043ESTIMATE:$12,000,000
Length:7.4Actual$0
 
Back...
Totals for 0516-02-029
Length:7.4
Estimate:$12,000,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract