Detail Letting Schedule for San Augustine County (FY 2019)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
San Augustine County (FY 2019) |
CCSJ: 0064-03-021 |
|||
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 147 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0064-03-021 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SHELBY COUNTY LINE | Fund Cat: | 8 |
Limits To: | 1.006 MILES NORTH OF FM 353 | ESTIMATE: | $51,983 |
Length: | 5.6 | Actual | $31,788 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0118-06-070 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 225 (W) | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $56,060 |
Length: | 12.8 | Actual | $61,404 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0119-02-021 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 0.366 MI EAST OF SAN AUGUSTINE CL | Fund Cat: | 8 |
Limits To: | 0.426 MILES EAST OF FM 330 | ESTIMATE: | $21,581 |
Length: | 4.4 | Actual | $21,801 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0119-03-028 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 0.426 MI EAST OF FM 330 | Fund Cat: | 8 |
Limits To: | 0.504 MI EAST OF SH 87 | ESTIMATE: | $32,588 |
Length: | 6.3 | Actual | $34,408 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0175-02-091 |
Description: | MILLED CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.334 MI W OF FM 2669 | Fund Cat: | 8 |
Limits To: | 0.547 MI W OF FM 2428 | ESTIMATE: | $61,961 |
Length: | 9.6 | Actual | $61,948 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 87 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0304-01-029 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 0.272 MI N OF SH 147 | Fund Cat: | 8 |
Limits To: | 1.55 MI S OF FM 353 | ESTIMATE: | $57,966 |
Length: | 12.4 | Actual | $62,387 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 87 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0304-03-027 |
Description: | PROFILE EDGELINE MARKINGS AND PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 21 | Fund Cat: | 8 |
Limits To: | FM 83 | ESTIMATE: | $50,501 |
Length: | 6.0 | Actual | $54,413 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 87 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0304-07-025 |
Description: | MILLED EDGELINE AND CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.553 MI S OF SS 470 | Fund Cat: | 8 |
Limits To: | US 96 | ESTIMATE: | $134,062 |
Length: | 14.5 | Actual | $113,511 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 7 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0336-02-027 |
Description: | MILLED EDGELINE RUMBLE STRIPS AND MILLED CENTERLINE RUMBLE | Handling Code: | |
Limits From: | 0.223 MI EAST OF FM 227 | Fund Cat: | 8 |
Limits To: | ANGELINA COUNTY LINE | ESTIMATE: | $93,019 |
Length: | 10.3 | Actual | $77,447 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 103 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0336-05-062 |
Description: | MILLED CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.855 MILES EAST OF FM 842 | Fund Cat: | 8 |
Limits To: | 0.078 MILES WEST OF NACOGDOCHES | ESTIMATE: | $90,285 |
Length: | 12.4 | Actual | $93,264 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 103 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0336-07-068 |
Description: | MILLED CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | NACOGDOCHES COUNTY LINE | Fund Cat: | 8 |
Limits To: | FM 3229 | ESTIMATE: | $73,591 |
Length: | 16.9 | Actual | $69,415 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 229 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0340-04-030 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 2544 | Fund Cat: | 8 |
Limits To: | SL 304 | ESTIMATE: | $60,528 |
Length: | 12.9 | Actual | $66,318 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0341-01-029 |
Description: | MILLED EDGELINE AND CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.372 MI WEST OF FM 2262 | Fund Cat: | 8 |
Limits To: | POLK COUNTY LINE | ESTIMATE: | $71,549 |
Length: | 8.3 | Actual | $58,729 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 156 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0403-01-045 |
Description: | MILLED CENTERLINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 0.474 MI S OF US 190 | Fund Cat: | 8 |
Limits To: | SH 150 | ESTIMATE: | $88,125 |
Length: | 13.8 | Actual | $91,368 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 230 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0475-08-013 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | WALKER COUNTY LINE | Fund Cat: | 8 |
Limits To: | 0.715 MI W OF SH 19 | ESTIMATE: | $17,179 |
Length: | 3.1 | Actual | $18,149 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 7 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0553-02-017 |
Description: | PROFILE EDGELEINE MARKINGS | Handling Code: | |
Limits From: | US 69 | Fund Cat: | 8 |
Limits To: | 3.361 MILES EAST OF US 69 | ESTIMATE: | $16,334 |
Length: | 3.4 | Actual | $16,649 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 228 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0635-03-024 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | BU 287-V | Fund Cat: | 8 |
Limits To: | ANDERSON COUNTY LINE | ESTIMATE: | $82,617 |
Length: | 10.4 | Actual | $91,718 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 414 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0743-03-018 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 8 |
Limits To: | 0.584 MI E OF CR 3267 | ESTIMATE: | $46,016 |
Length: | 6.7 | Actual | $50,747 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2693 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0756-04-012 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 3.885 MI N OF SH 150 | Fund Cat: | 8 |
Limits To: | SH 150 | ESTIMATE: | $35,378 |
Length: | 3.9 | Actual | $38,310 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 699 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0809-01-034 |
Description: | PROFILE EDGELINE MARKINGS, AND PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | US 84 | Fund Cat: | 8 |
Limits To: | 0.208 MI NORTH OF FM 1656 | ESTIMATE: | $64,476 |
Length: | 8.1 | Actual | $70,319 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | SH 7 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0894-01-020 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 8 |
Limits To: | 0.040 MILES WEST OF US 69 | ESTIMATE: | $51,308 |
Length: | 6.6 | Actual | $56,600 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 357 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 0940-01-020 |
Description: | PROFILE EDGELINE MARKINGS AND PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 7 | Fund Cat: | 8 |
Limits To: | TRINITY COUNTY LINE | ESTIMATE: | $57,302 |
Length: | 7.7 | Actual | $63,970 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 942 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1193-01-034 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 62 | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $158,387 |
Length: | 20.2 | Actual | $177,291 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 943 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1194-01-023 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 146 | Fund Cat: | 8 |
Limits To: | HARDIN COUNTY LINE | ESTIMATE: | $143,688 |
Length: | 19.1 | Actual | $162,352 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 83 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1678-01-024 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 8 |
Limits To: | 0.197 MILES EAST OF FM 3382 (NE) | ESTIMATE: | $60,436 |
Length: | 7.5 | Actual | $65,868 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2971 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1678-02-006 |
Description: | PROFILE EDGELINE MARKINGS AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 83 | Fund Cat: | 8 |
Limits To: | 2.677 MI SOUTH OF FM 83 | ESTIMATE: | $24,635 |
Length: | 2.7 | Actual | $25,052 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 276 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1679-01-013 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 8 |
Limits To: | 0.010 MILES SE OF BEST LOOP | ESTIMATE: | $28,912 |
Length: | 4.9 | Actual | $28,444 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 1878 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1810-01-035 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SL 224 | Fund Cat: | 8 |
Limits To: | 2.395 MI EAST OF FM 2112 | ESTIMATE: | $60,679 |
Length: | 7.7 | Actual | $67,278 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 1988 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1876-02-017 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | US 59 (S) | Fund Cat: | 8 |
Limits To: | SH 146 | ESTIMATE: | $24,261 |
Length: | 5.2 | Actual | $25,417 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 1970 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 1964-02-011 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | PANOLA COUNTY LINE | Fund Cat: | 8 |
Limits To: | US 84 | ESTIMATE: | $29,790 |
Length: | 4.4 | Actual | $32,581 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2140 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2070-01-010 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 417 | Fund Cat: | 8 |
Limits To: | US 96 | ESTIMATE: | $21,486 |
Length: | 2.9 | Actual | $21,996 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2251 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2115-01-017 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 843 | Fund Cat: | 8 |
Limits To: | US 69 | ESTIMATE: | $21,022 |
Length: | 4.5 | Actual | $22,169 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2259 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2116-01-021 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SL 224 | Fund Cat: | 8 |
Limits To: | FM 226 | ESTIMATE: | $36,361 |
Length: | 8.0 | Actual | $38,958 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2426 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2268-01-017 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 1.008 MILES EAST OF FM 1 | Fund Cat: | 8 |
Limits To: | SH 87 | ESTIMATE: | $38,980 |
Length: | 8.3 | Actual | $40,815 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 980 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2443-02-017 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | WALKER COUNTY LINE | Fund Cat: | 8 |
Limits To: | 0.082 MILES NW OF US 190 | ESTIMATE: | $65,397 |
Length: | 14.9 | Actual | $71,633 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 1316 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2510-01-017 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SH 146 | Fund Cat: | 8 |
Limits To: | WD BOYCE ROAD | ESTIMATE: | $16,952 |
Length: | 2.2 | Actual | $17,913 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2609 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2590-01-029 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 941 | Fund Cat: | 8 |
Limits To: | SL 224 | ESTIMATE: | $30,312 |
Length: | 4.9 | Actual | $32,077 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2667 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2669-01-010 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 8 |
Limits To: | 3.347 MI S OF US 59 | ESTIMATE: | $27,663 |
Length: | 3.3 | Actual | $28,054 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 2863 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 2890-01-007 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SL 224 | Fund Cat: | 8 |
Limits To: | 2.783 MILES SOUTH OF SL 224 | ESTIMATE: | $22,985 |
Length: | 2.8 | Actual | $24,157 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 222 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 3038-01-012 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | 1.807 MILES SOUTH OF FM 3278 | Fund Cat: | 8 |
Limits To: | 0.964 MILES NORTH OF SH 150 (SE) | ESTIMATE: | $37,571 |
Length: | 5.5 | Actual | $40,177 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 3121 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 3170-01-013 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SH 21 | Fund Cat: | 8 |
Limits To: | FM 83 | ESTIMATE: | $26,978 |
Length: | 4.9 | Actual | $26,844 |
District: | LUFKIN | Let Date: | Oct 2018 |
Highway: | FM 3278 | Let Status: | Actual |
Project ID: | STP 2019(094)HES | CSJ: | 3198-02-015 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 222 | Fund Cat: | 8 |
Limits To: | 0.850 MI W OF FM 1988 | ESTIMATE: | $23,500 |
Length: | 3.6 | Actual | $25,457 |
Back... | Totals for 0064-03-021 | ||
---|---|---|---|
Length: | 333.6 | ||
Estimate: | $2,214,401 | ||
Actual: | $2,279,194 | ||
CCSJ: 0118-12-019 |
|||
District: | LUFKIN | Let Date: | Jan 2019 |
Highway: | FM 353 | Let Status: | Actual |
Project ID: | ER 2019(582) | CSJ: | 0118-12-019 |
Description: | EMERGENCY REPAIR ON CULVERT | Handling Code: | XX |
Limits From: | 3.15 MILES WEST OF SH 87 | Fund Cat: | 10 |
Limits To: | 3.11 MILES WEST OF SH 87 | ESTIMATE: | $212,884 |
Length: | 0.0 | Actual | $266,105 |
Back... | Totals for 0118-12-019 | ||
Length: | 0 | ||
Estimate: | $212,884 | ||
Actual: | $266,105 | ||
CCSJ: 0911-30-030 |
|||
District: | LUFKIN | Let Date: | Jul 2019 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2018(430) | CSJ: | 0911-30-030 |
Description: | Bridge Replacement | Handling Code: | |
Limits From: | CR 313 AT AYISH BAYOU RELIEF | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $455,000 |
Length: | 0.1 | Actual | $0 |
District: | LUFKIN | Let Date: | Jul 2019 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2018(431) | CSJ: | 0911-30-031 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | CR 205 AT BLACK CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $515,950 |
Length: | 0.1 | Actual | $0 |
District: | LUFKIN | Let Date: | Jul 2019 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2018(432) | CSJ: | 0911-30-032 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | CR 141 AT PALO GAUCHO BAYOU | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $514,810 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 0911-30-030 | ||
Length: | 0.3 | ||
Estimate: | $1,485,760 | ||
Actual: | |||
CCSJ: 1079-01-036 |
|||
District: | LUFKIN | Let Date: | Sep 2018 |
Highway: | FM 705 | Let Status: | Actual |
Project ID: | ER 2018(690) | CSJ: | 1079-01-036 |
Description: | BRIDGE EMBANKMENT AND CONCRETE RIPRAP RESTORED | Handling Code: | XX |
Limits From: | 6.442 MI N OF FM 83 | Fund Cat: | 10 |
Limits To: | 2.313 MI S OF SH 103 | ESTIMATE: | $72,132 |
Length: | 2.0 | Actual | $61,541 |
Back... | Totals for 1079-01-036 | ||
Length: | 2 | ||
Estimate: | $72,132 | ||
Actual: | $61,541 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |