Detail Letting Schedule for San Augustine County (FY 2019)

Last Update: Monday, July 16, 2018
San Augustine County (FY 2019)

CCSJ: 0064-03-021

District:LUFKINLet Date:Oct 2018
Highway:SH 147Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0064-03-021
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SHELBY COUNTY LINEFund Cat:8
Limits To:1.006 MILES NORTH OF FM 353ESTIMATE:$63,468
Length:5.6Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 21Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0118-06-070
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 225 (W)Fund Cat:8
Limits To:US 59ESTIMATE:$63,290
Length:12.8Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 21Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0119-02-021
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:0.366 MI EAST OF SAN AUGUSTINE CLFund Cat:8
Limits To:0.426 MILES EAST OF FM 330ESTIMATE:$26,605
Length:4.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 21Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0119-03-028
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:0.426 MI EAST OF FM 330Fund Cat:8
Limits To:0.504 MI EAST OF SH 87ESTIMATE:$39,006
Length:6.3Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:US 84Let Status:Approved
Project ID:STP2019 (094)HESCSJ:0175-02-091
Description:MILLED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:0.334 MI W OF FM 2669Fund Cat:8
Limits To:0.547 MI W OF FM 2428ESTIMATE:$76,361
Length:9.6Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 87Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0304-01-029
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:0.272 MI N OF SH 147Fund Cat:8
Limits To:1.55 MI S OF FM 353ESTIMATE:$66,361
Length:12.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 87Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0304-03-027
Description:PROFILE EDGELINE MARKINGS AND PROFILE CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 21Fund Cat:8
Limits To:FM 83ESTIMATE:$58,609
Length:6.0Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 87Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0304-07-025
Description:MILLED EDGELINE AND CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:0.553 MI S OF SS 470Fund Cat:8
Limits To:US 96ESTIMATE:$153,319
Length:14.5Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 7Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0336-02-027
Description:MILLED EDGELINE RUMBLE STRIPS AND MILLED CENTERLINE RUMBLEHandling
Code:
 
Limits From:0.223 MI EAST OF FM 227Fund Cat:8
Limits To:ANGELINA COUNTY LINEESTIMATE:$107,960
Length:10.3Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 103Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0336-05-062
Description:MILLED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:0.855 MILES EAST OF FM 842Fund Cat:8
Limits To:0.078 MILES WEST OF NACOGDOCHESESTIMATE:$109,806
Length:12.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 103Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0336-07-068
Description:MILLED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:NACOGDOCHES COUNTY LINEFund Cat:8
Limits To:FM 3229ESTIMATE:$87,834
Length:16.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 229Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0340-04-030
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 2544Fund Cat:8
Limits To:SL 304ESTIMATE:$68,562
Length:12.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:US 287Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0341-01-029
Description:MILLED EDGELINE AND CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:0.372 MI WEST OF FM 2262Fund Cat:8
Limits To:POLK COUNTY LINEESTIMATE:$82,859
Length:8.3Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 156Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0403-01-045
Description:MILLED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:0.474 MI S OF US 190Fund Cat:8
Limits To:SH 150ESTIMATE:$106,729
Length:13.8Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 230Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0475-08-013
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:WALKER COUNTY LINEFund Cat:8
Limits To:0.715 MI W OF SH 19ESTIMATE:$21,390
Length:3.1Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 7Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0553-02-017
Description:PROFILE EDGELEINE MARKINGSHandling
Code:
 
Limits From:US 69Fund Cat:8
Limits To:3.361 MILES EAST OF US 69ESTIMATE:$19,852
Length:3.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 228Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0635-03-024
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:BU 287-VFund Cat:8
Limits To:ANDERSON COUNTY LINEESTIMATE:$92,455
Length:10.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 414Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0743-03-018
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SH 87Fund Cat:8
Limits To:0.584 MI E OF CR 3267ESTIMATE:$55,791
Length:6.7Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2693Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0756-04-012
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:3.885 MI N OF SH 150Fund Cat:8
Limits To:SH 150ESTIMATE:$41,061
Length:3.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 699Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0809-01-034
Description:PROFILE EDGELINE MARKINGS, AND PROFILE CENTERLINE MARKINGSHandling
Code:
 
Limits From:US 84Fund Cat:8
Limits To:0.208 MI NORTH OF FM 1656ESTIMATE:$73,914
Length:8.1Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:SH 7Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0894-01-020
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 103Fund Cat:8
Limits To:0.040 MILES WEST OF US 69ESTIMATE:$58,273
Length:6.6Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 357Let Status:Approved
Project ID:STP 2019(094)HESCSJ:0940-01-020
Description:PROFILE EDGELINE MARKINGS AND PROFILE CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 7Fund Cat:8
Limits To:TRINITY COUNTY LINEESTIMATE:$65,732
Length:7.7Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 942Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1193-01-034
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:FM 62Fund Cat:8
Limits To:US 59ESTIMATE:$174,216
Length:20.2Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 943Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1194-01-023
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 146Fund Cat:8
Limits To:HARDIN COUNTY LINEESTIMATE:$159,533
Length:19.1Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 83Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1678-01-024
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 87Fund Cat:8
Limits To:0.197 MILES EAST OF FM 3382 (NE)ESTIMATE:$69,056
Length:7.5Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2971Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1678-02-006
Description:PROFILE EDGELINE MARKINGS AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:FM 83Fund Cat:8
Limits To:2.677 MI SOUTH OF FM 83ESTIMATE:$29,852
Length:2.7Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 276Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1679-01-013
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SH 87Fund Cat:8
Limits To:0.010 MILES SE OF BEST LOOPESTIMATE:$35,088
Length:4.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 1878Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1810-01-035
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SL 224Fund Cat:8
Limits To:2.395 MI EAST OF FM 2112ESTIMATE:$68,595
Length:7.7Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 1988Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1876-02-017
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:US 59 (S)Fund Cat:8
Limits To:SH 146ESTIMATE:$28,485
Length:5.2Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 1970Let Status:Approved
Project ID:STP 2019(094)HESCSJ:1964-02-011
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:PANOLA COUNTY LINEFund Cat:8
Limits To:US 84ESTIMATE:$35,933
Length:4.4Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2140Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2070-01-010
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 417Fund Cat:8
Limits To:US 96ESTIMATE:$27,703
Length:2.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2251Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2115-01-017
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 843Fund Cat:8
Limits To:US 69ESTIMATE:$24,994
Length:4.5Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2259Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2116-01-021
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SL 224Fund Cat:8
Limits To:FM 226ESTIMATE:$41,879
Length:8.0Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2426Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2268-01-017
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:1.008 MILES EAST OF FM 1Fund Cat:8
Limits To:SH 87ESTIMATE:$45,556
Length:8.3Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 980Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2443-02-017
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:WALKER COUNTY LINEFund Cat:8
Limits To:0.082 MILES NW OF US 190ESTIMATE:$73,427
Length:14.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 1316Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2510-01-017
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SH 146Fund Cat:8
Limits To:WD BOYCE ROADESTIMATE:$21,314
Length:2.2Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2609Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2590-01-029
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 941Fund Cat:8
Limits To:SL 224ESTIMATE:$35,739
Length:4.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2667Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2669-01-010
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:US 59Fund Cat:8
Limits To:3.347 MI S OF US 59ESTIMATE:$32,082
Length:3.3Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 2863Let Status:Approved
Project ID:STP 2019(094)HESCSJ:2890-01-007
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SL 224Fund Cat:8
Limits To:2.783 MILES SOUTH OF SL 224ESTIMATE:$27,065
Length:2.8Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 222Let Status:Approved
Project ID:STP 2019(094)HESCSJ:3038-01-012
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:1.807 MILES SOUTH OF FM 3278Fund Cat:8
Limits To:0.964 MILES NORTH OF SH 150 (SE)ESTIMATE:$42,996
Length:5.5Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 3121Let Status:Approved
Project ID:STP 2019(094)HESCSJ:3170-01-013
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:SH 21Fund Cat:8
Limits To:FM 83ESTIMATE:$32,798
Length:4.9Actual$0
 
District:LUFKINLet Date:Oct 2018
Highway:FM 3278Let Status:Approved
Project ID:STP 2019(094)HESCSJ:3198-02-015
Description:PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:FM 222Fund Cat:8
Limits To:0.850 MI W OF FM 1988ESTIMATE:$30,485
Length:3.6Actual$0
 
Back...
Totals for 0064-03-021
Length:333.6
Estimate:$2,576,030
Actual:

CCSJ: 0911-30-030

District:LUFKINLet Date:Jul 2019
Highway:CRLet Status:Tentative
Project ID:BR 2018(430)CSJ:0911-30-030
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:CR 313 AT AYISH BAYOU RELIEFFund Cat:6
Limits To:.ESTIMATE:$282,100
Length:0.1Actual$0
 
District:LUFKINLet Date:Jul 2019
Highway:CRLet Status:Tentative
Project ID:BR 2018(431)CSJ:0911-30-031
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:CR 205 AT BLACK CREEKFund Cat:6
Limits To:.ESTIMATE:$515,950
Length:0.1Actual$0
 
District:LUFKINLet Date:Jul 2019
Highway:CRLet Status:Tentative
Project ID:BR 2018(432)CSJ:0911-30-032
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:CR 141 AT PALO GAUCHO BAYOUFund Cat:6
Limits To:.ESTIMATE:$514,810
Length:0.1Actual$0
 
Back...
Totals for 0911-30-030
Length:0.3
Estimate:$1,312,860
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract