Monthly State Let Construction Report For Abilene District As Of Jan 10, 2023 Page 1 Of 2

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
From0.38 MILES EAST OF US 87 RELIEF ROUTE
To.5 MILES WEST OF SH 350
CSJ0005-05-113
Proj IDF 2023(104)
Work TypeOVERLAY
 
7.4576309354.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-113
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233236
Totals6309354.480.000.000.0

CountyMITCHELL
HighwayIH 20
FromHOWARD COUNTY LINE
ToFM 670
CSJ0005-07-058
Proj IDNH 2021(178)
Work TypeOVERLAY
 
9.32813256487.7613611303.4199.9
CountyMITCHELL
HighwayIH 20
FromFM 670
To.636 MILES TO EAST
CSJ0005-08-108
Proj IDNH 2021(178)
Work TypeOVERLAY
 
0.6361421492.22741835.1952.1
CountyMITCHELL
HighwayBI 20-H
FromFM 670
ToBI 20H
CSJ0005-11-027
Proj IDSTP 2021(179)
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.00677490.0085755.6099.9
Work Order01-14-21
Work Began05-10-21
Work Completed
Time Computed04-14-21
Contract Working Days325
Addl Days Granted0
Working Days Charged317
Percent Time Used97
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-07-058
BARRICADES UNLIMITED (2.17)
CONTRACTORS SERVICE COMPANY (0.31)
DUSTY ALLEN, INC. (3.07)
HJC FARMS, INC. (2.19)
SCR CIVIL CONSTRUCTION, LLC (0.48)
TEXOP CONSTRUCTION (1.91)
W. S. CONSTRUCTION COMPANY (13.85)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
DUSTIN ALLEN, INC. (3.07)
Contract #12203004
Totals14755469.98355250.5814438894.2097.8

CountyNOLAN
HighwayIH 20
FromEAST OF CR 111
ToWEST OF LP 170
CSJ0006-02-114
Proj IDC 6-2-114
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
6.290115985812.196296706.141.4
CountyNOLAN
HighwayIH 20
FromEAST OF CR 111
ToWEST OF LP 170
CSJ0006-02-123
Proj IDNH 2B20(091)
Work TypeRIGHT OF WAY
 
6.290998587.000.000.0
Work Order09-15-22
Work Began01-03-23
Work Completed
Time Computed11-14-22
Contract Working Days829
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-114
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.03)
FUSION COMMUNICATIONS, LLC (0.08)
HB FARMER FOUNDATION, LLC (1.85)
JVH4 SERVICES, LLC (0.33)
MICA CORPORATION (1.88)
MICA CORPORATION (1.38)
TORO BRAVO CONSTRUCTION, LLC (0.71)
WILLIS ELECTRIC CO., LP (3.49)
DK CONTRACTING, LLC (0.19)
PINNACLE GRINDING AND GROOVING LLC (0.00)
TEX OP CONSTRUCTION, LP (0.27)
CHOCTAW ERECTORS, INC. (0.45)
SOUTHEAST GRINDING AND GROOVING LLC (0.03)
BARRICADES UNLIMITED (1.38)
Contract #08223202
Totals116984399.191105663.146296706.141.4

CountyNOLAN
HighwayIH 20
FromWEST BU20L
To.14 MILE WEST OF SH 70
CSJ0006-02-121
Proj IDNH 2020(618)
Work TypeOVERLAY
 
9.97720032973.6419302650.9396.3
Work Order06-18-20
Work Began09-25-20
Work Completed
Time Computed09-16-20
Contract Working Days604
Addl Days Granted4
Working Days Charged437
Percent Time Used71
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-121
RPV CONSTRUCTION, LLC (4.14)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
FC TRAFFIC CONTROL, INC. (0.79)
HJC FARMS, INC. (1.69)
HERITAGE MATERIALS, LLC (1.19)
MOBILE ENTERPRISES, INC. (0.36)
ACT SAW CUTTING & REMOVAL (0.39)
LINEAR TRAFFIC MARKINGS LLC (1.97)
DIAMOND C LOGISTICS TX LLC (4.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
TEX OP CONSTRUCTION, LP (1.21)
TEXAS M&A TRANSPORTATION LLC (1.24)
PEYSON TRANSPORT, LLC (0.49)
Contract #03203003
Totals20032973.64350917.7019302650.9396.3

CountyTAYLOR
HighwayIH 20
From.75 MI E OF HATER RD
ToWEST OF OLD ANSON ROAD
CSJ0006-05-117
Proj IDC 6-5-117
Work TypeOVERLAY
 
10.9409498596.323687335.7638.8
Work Order05-10-22
Work Began08-31-22
Work Completed
Time Computed06-10-22
Contract Working Days240
Addl Days Granted0
Working Days Charged68
Percent Time Used28
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-05-117
CONTRACTORS SERVICE, LTD. (0.56)
DOUBLE A CONTRACTING, L.P. (1.72)
HJC FARMS, INC. (21.26)
WEST TEXAS ROCK RESOURCES, LLC (0.46)
Contract #04223207
Totals9498596.3288743.303687335.7638.8

CountyTAYLOR
HighwayBI 20-R
FromLEGGETT DR
ToROSS AVE
CSJ0006-18-064
Proj IDF 2022(970)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
879467.9422335.192.5
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed01-20-23
Contract Working Days58
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223066
Totals879467.9416200.0022335.192.5

CountySTONEWALL
HighwayUS 83
FromKING COUNTY LINE
ToUS 380
CSJ0032-07-029
Proj IDSTP 1302(057)
Work TypeSUPER-2 HIGHWAY
 
17.54319299562.062135089.9511.0
Work Order02-16-22
Work Began04-14-22
Work Completed
Time Computed04-14-22
Contract Working Days432
Addl Days Granted0
Working Days Charged155
Percent Time Used35
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0032-07-029
4-WAY HAULERS, LLC (3.81)
BARRICADES UNLIMITED (2.19)
Contract #01223201
Totals19299562.06318310.912135089.9511.0

CountySTONEWALL
HighwayUS 83
FromUS 380
ToUS 83
CSJ0032-07-036
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1006571.70739863.8973.5
CountySTONEWALL
HighwayUS 83
FromUS 380
ToUS 83
CSJ0106-05-039
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
341606.55196379.5857.4
CountyNOLAN
HighwaySH 70
FromFM 153
ToFM 608
CSJ0264-02-030
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2233854.801403711.1662.8
Work Order06-10-21
Work Began08-09-21
Work Completed
Time Computed08-09-21
Contract Working Days172
Addl Days Granted72
Working Days Charged161
Percent Time Used65
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0032-07-036
CONTRACTORS SERVICE COMPANY (0.27)
L&H ELECTRICAL, LLC (15.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.23)
J & M CONTRACTING, COMPANY (3.25)
LEVI THOMPSON CONSTRUCTION, INC. (2.79)
RAYDON, INC. (2.47)
BARRICADES UNLIMITED (1.76)
DIIBS SPECIALISTS, LLC (1.36)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC (14.51)
Contract #05213017
Totals3582033.05246279.312339954.6365.3

CountySTONEWALL
HighwayUS 83
FromUS 380
ToFISHER COUNTY LINE
CSJ0033-01-038
Proj IDSTP 1302(058)
Work TypeSUPER-2 HIGHWAY
 
18.38914492854.111138804.007.8
Work Order02-16-22
Work Began04-28-22
Work Completed
Time Computed04-28-22
Contract Working Days396
Addl Days Granted0
Working Days Charged145
Percent Time Used36
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-01-038
DIIBS SPECIALISTS, LLC (2.90)
PINNACLE GRINDING AND GROOVING LLC (0.21)
FLAT LINE, INC. (1.64)
CONTRACTORS SERVICE, LTD. (0.36)
HJC FARMS, INC. (0.73)
Contract #01223001
Totals14492854.11120315.001138804.007.8

CountyJONES ETC
HighwayUS 83 ETC
FromNEAR 10TH ST
ToNEAR 13TH ST
CSJ0033-04-072
Proj IDF 2023(008)
Work TypeOVERLAY
 
5224759.640.000.0
Work Order10-06-22
Work Began01-03-23
Work Completed
Time Computed11-07-22
Contract Working Days114
Addl Days Granted0
Working Days Charged12
Percent Time Used10
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-072
TRAFFIC HIGHWAY MAINTENANCE, LLC (3.95)
Contract #09223205
Totals5224759.640.000.000.0

CountyNOLAN
HighwayFM 608
FromBI 20
ToFM 1170
CSJ0053-15-067
Proj IDF 2023(163)
Work TypeREHABILITATION OF EXISTING ROAD
 
8787859.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233206
Totals8787859.330.000.000.0

CountyHOWARD
HighwayUS 87
FromMARTIN CL
To4 MILES N FM 846
CSJ0068-07-051
Proj IDC 68-7-51
Work TypeOVERLAY
 
4.9157456743.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233006
Totals7456743.820.000.000.0

CountyHOWARD
HighwayUS 87
FromMARTIN COUNTY LINE
ToNORTH OF CR 50
CSJ0068-07-052
Proj IDF 2021(845)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.9141069252.871051892.9698.3
CountyHOWARD
HighwayUS 87
FromNORTH OF CR 50
ToFM 2230
CSJ0068-08-068
Proj IDF 2021(845)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.6991481545.131452724.2298.0
Work Order09-29-21
Work Began07-11-22
Work Completed
Time Computed07-11-22
Contract Working Days64
Addl Days Granted0
Working Days Charged64
Percent Time Used100
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-052
FUSION COMMUNICATIONS, LLC (2.43)
AREA WIDE PROTECTIVE, INC. (0.26)
J. H. ODEN CONTRACTING COMPANY (0.95)
WILLIS ELECTRIC CO., LP (21.02)
Contract #08213030
Totals2550798.008657.952504617.1898.1

CountySTONEWALL
HighwayUS 380
FromSALT FORK BRAZOS RIVER
To.
CSJ0106-04-036
Proj IDBR 2022(829)
Work TypeBRIDGE REPLACEMENT
 
8952032.000.000.0
CountyKENT
HighwaySH 208
FromSALT FORK BRAZOS RIVER
To.
CSJ2011-02-015
Proj IDBR 2022(829)
Work TypeBRIDGE REPLACEMENT
 
5710494.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days506
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0106-04-036
BARRICADES UNLIMITED (0.28)
CONTRACTORS SERVICE, LTD. (0.30)
LANCO TURF & SEEDING, INC. (0.15)
MARCOM"S MOWING SERVICE, LLC (0.15)
SCOTT DERR PAINTING CO, LLC (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.04)
Contract #08223006
Totals14662526.000.000.000.0

CountyHASKELL ETC
HighwaySH 6 ETC
FromRED PAINT CREEK
To.
CSJ0106-07-030
Proj IDBR 2022(761)
Work TypeBRIDGE MAINTENANCE
 
1729616.69214394.0512.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began11-15-22
Work Completed
Time Computed00-00-00
Contract Working Days124
Addl Days Granted0
Working Days Charged25
Percent Time Used20
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-07-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223058
Totals1729616.6996994.85214394.0512.3

CountyHASKELL
HighwayUS 277
FromJONES COUNTY
ToSOUTH Y IN HASKELL, NB LANES
CSJ0157-04-057
Proj IDC 157-4-57
Work TypeOVERLAY
 
11.6085473497.38564136.4410.3
Work Order02-15-22
Work Began05-02-22
Work Completed
Time Computed05-02-22
Contract Working Days103
Addl Days Granted0
Working Days Charged8
Percent Time Used7
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-04-057
HJC FARMS, INC. (4.72)
W. S. CONSTRUCTION COMPANY (3.54)
DOUBLE A CONTRACTING, L.P. (2.01)
MARCOM"S MOWING SERVICE, LLC (2.04)
CONTRACTORS SERVICE, LTD. (0.19)
Contract #01223007
Totals5473497.3874644.07564136.4410.3

CountyHASKELL
HighwayUS 277
FromNORTH Y
ToSOUTH Y
CSJ0157-09-004
Proj IDF 2023(083)
Work TypeOVERLAY
 
5.2465949105.890.000.0
Work Order11-16-22
Work Began00-00-00
Work Completed
Time Computed12-16-22
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-09-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223017
Totals5949105.890.000.000.0

CountyKENT ETC
HighwayUS 380 ETC
FromSH 70
ToSH 70
CSJ0263-01-021
Proj IDF 2023(256)
Work TypeSEAL COAT
 
107.27410460911.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0263-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223005
Totals10460911.960.000.000.0

CountyFISHER
HighwaySH 70
FromPLUM CREEK
To.
CSJ0263-05-024
Proj IDBR 2B20(044)
Work TypeBRIDGE REPLACEMENT
 
3716743.801401247.8337.7
Work Order08-04-22
Work Began09-07-22
Work Completed
Time Computed09-06-22
Contract Working Days196
Addl Days Granted0
Working Days Charged72
Percent Time Used36
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0263-05-024
BARRICADES UNLIMITED (0.71)
MORRIS COUNTY CONTRACTORS, L.L.C. (3.85)
FC TRAFFIC CONTROL, INC. (0.63)
Contract #06223423
Totals3716743.80182422.191401247.8337.7

CountyBORDEN
HighwayFM 669
From1300 FT NORTH OF FM 1785
To1300 FT SOUTH OF FM 1785
CSJ0558-03-027
Proj IDSTP 2022(830)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
271239.330.000.0
CountyBORDEN
HighwayFM 1785
FromHOWARD COUNTY
ToFM 669
CSJ1155-04-013
Proj IDSTP 2022(830)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4121151.70105539.052.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-22
Work Began11-28-22
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted0
Working Days Charged11
Percent Time Used5
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0558-03-027
BARRICADES UNLIMITED (4.07)
DUSTROL, INC. (0.51)
DK CONTRACTING, LLC (0.56)
W. S. CONSTRUCTION COMPANY (7.85)
J. H. ODEN CONTRACTING COMPANY (0.64)
DUKE ELECTRIC CO., INC. (1.78)
Contract #08223018
Totals4392391.0398199.41105539.052.4

page 1 | page 2