Monthly State Let Construction Report For Abilene District As Of Nov 10, 2024 Page 3 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCALLAHAN
HighwayIH 20
FromVARIOUS LOCATIONS
To.
CSJ0908-00-131
Proj IDBR 2024(777)
Work TypeBRIDGE MAINTENANCE
 
562852.76514755.4891.4
Work Order04-11-24
Work Began05-13-24
Work Completed
Time Computed05-11-24
Contract Working Days144
Addl Days Granted0
Working Days Charged29
Percent Time Used20
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-131
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243225
Totals562852.760.00514755.4891.4

CountyKENT
HighwayCR
FromAT COOPER CREEK
To.
CSJ0908-27-006
Proj IDBR 2023(941)
Work TypeBRIDGE REPLACEMENT
 
0.069878015.00568002.2464.6
Work Order01-10-24
Work Began07-08-24
Work Completed
Time Computed02-09-24
Contract Working Days89
Addl Days Granted0
Working Days Charged81
Percent Time Used91
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0908-27-006
BARRICADES UNLIMITED (0.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.45)
V-TECH ENVIROMENTAL SERVICES (1.38)
Contract #12233216
Totals878015.00164900.47568002.2464.6

CountyJONES
HighwayFM 1082
FromWEST OF CHEYENNE CIRCLE
ToEAST OF DAM
CSJ0972-03-021
Proj IDF 2B23(134)
Work TypeNEW LOCATION NON-FREEWAY
 
1.3638867738.997987651.2590.0
Work Order09-07-23
Work Began10-27-23
Work Completed
Time Computed12-06-23
Contract Working Days261
Addl Days Granted0
Working Days Charged213
Percent Time Used81
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0972-03-021
ALAMO BROTHERS CONCRETE INC (4.35)
BARRICADES UNLIMITED (0.16)
BLACK JACK ENERGY SERVICES, LLC (38.55)
SCOTT DERR PAINTING CO, LLC (0.16)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.55)
MURRAY CONSTRUCTION (0.37)
HJC FARMS, INC. (2.66)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.41)
FLAT LINE, INC. (0.75)
PENHALL COMPANY (0.06)
TORO BRAVO CONSTRUCTION, LLC (0.06)
TORO BRAVO CONSTRUCTION, LLC (0.20)
Contract #08233216
Totals8867738.99691891.257987651.2590.0

CountyJONES
HighwayFM 1082
FromEAST OF DAM
ToFM 3522
CSJ0972-03-023
Proj IDF 2024(776)
Work TypeRESTORATION
 
4.1613582697.00997097.0027.8
Work Order04-18-24
Work Began07-29-24
Work Completed
Time Computed06-17-24
Contract Working Days141
Addl Days Granted0
Working Days Charged54
Percent Time Used38
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0972-03-023
AWP SAFETY (0.43)
CONTRACTORS SERVICE, LTD. (0.53)
FLAT LINE, INC. (1.76)
O. TREVINO CONSTRUCTION, LLC (27.39)
PROFESSIONAL TRAFFIC CONTROL LLC (0.32)
Contract #03243212
Totals3582697.00468320.00997097.0027.8

CountyHASKELL
HighwayFM 600
FromFM 2976
ToJONES COUNTY
CSJ0972-06-015
Proj IDF 2023(915)
Work TypeWIDEN NON-FREEWAY
 
4.5322844984.652958259.4399.9
Work Order07-19-23
Work Began10-09-23
Work Completed
Time Computed08-18-23
Contract Working Days120
Addl Days Granted0
Working Days Charged117
Percent Time Used97
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0972-06-015
FLAT LINE, INC. (1.51)
W. S. CONSTRUCTION COMPANY (8.48)
WEST TEXAS BARRICADE AND LIGHT CO. (0.69)
MURRAY CONSTRUCTION (1.76)
BARRICADES UNLIMITED (0.69)
WEST TEXAS ROCK RESOURCES, LLC (0.80)
Contract #06233014
Totals2844984.6586799.962958259.4399.9

CountyNOLAN
HighwayFM 419
FromFISHER COUNTY
ToBI-20
CSJ0983-03-030
Proj IDF 2024(170)
Work TypeOVERLAY
 
3360261.393389643.7599.9
Work Order02-21-24
Work Began04-22-24
Work Completed
Time Computed03-22-24
Contract Working Days94
Addl Days Granted0
Working Days Charged79
Percent Time Used84
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0983-03-030
FC TRAFFIC CONTROL, INC. (0.53)
CLEARFIELD CONSTRUCTION, LLC (7.91)
DOUBLE A CONTRACTING, L.P. (4.08)
HJC FARMS, INC. (3.14)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.45)
PRIMATE CONSTRUCTION, LP (0.51)
PROFESSIONAL TRAFFIC CONTROL LLC (0.33)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
Contract #10233214
Totals3360261.39120368.723389643.7599.9

CountySHACKELFORD
HighwayFM 576
FromFM 576
ToAT DEEP CREEK
CSJ1031-05-018
Proj IDBR 2024(663)
Work TypeBRIDGE REPLACEMENT
 
0.1172414951.88736865.7730.5
Work Order02-02-24
Work Began09-16-24
Work Completed
Time Computed05-02-24
Contract Working Days111
Addl Days Granted0
Working Days Charged22
Percent Time Used19
Contractor(s)
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1031-05-018
CONTRACTORS SERVICE, LTD. (0.40)
JVH4 SERVICES, LLC (1.23)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.93)
HJC FARMS, INC. (2.84)
J. R. (JOE) RAMON & SONS, INC. (3.17)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.47)
PENHALL COMPANY (0.21)
ZENITH SITE SERVICES (5.79)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (1.58)
J. H. STRAIN & SONS, INC. (6.25)
TORO BRAVO CONSTRUCTION, LLC (0.26)
Contract #01243227
Totals2414951.88439781.65736865.7730.5

CountyJONES
HighwayFM 1226
FromAT CALIFORNIA CREEK
To.
CSJ1360-01-030
Proj IDBR 2024(522)
Work TypeBRIDGE REPLACEMENT
 
1671853.751586178.6596.5
Work Order12-13-23
Work Began03-04-24
Work Completed
Time Computed01-12-24
Contract Working Days104
Addl Days Granted0
Working Days Charged137
Percent Time Used131
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1360-01-030
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
FC TRAFFIC CONTROL, INC. (0.48)
TORO BRAVO CONSTRUCTION, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.46)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.66)
PENHALL COMPANY (0.27)
TEXOP CONSTRUCTION (0.53)
BONTKE BROTHERS CONSTRUCTION COMPANY (9.16)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.49)
AWP SAFETY (0.19)
Contract #11233223
Totals1671853.7565494.751586178.6596.5

CountyJONES
HighwayFM 1226
FromFM 2702
ToUS 180
CSJ1360-01-031
Proj IDC 1360-1-31
Work TypeWIDEN NON-FREEWAY
 
9538047.57509435.265.3
Work Order06-26-24
Work Began10-14-24
Work Completed
Time Computed08-25-24
Contract Working Days289
Addl Days Granted0
Working Days Charged10
Percent Time Used3
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1360-01-031
CONTRACTORS SERVICE, LTD. (0.66)
DK CONTRACTING, LLC (0.80)
FLAT LINE, INC. (2.32)
HJC FARMS, INC. (2.88)
Contract #05243210
Totals9538047.57509435.26509435.265.3

CountyNOLAN
HighwayFM 608
From.010MI EAST OF SECOND ST IN MARYNEAL
ToSH 70
CSJ2033-01-013
Proj IDC 2033-1-13
Work TypeWIDEN NON-FREEWAY
 
10.1507895450.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days288
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2033-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243014
Totals7895450.240.000.000.0

CountyNOLAN
HighwayFM 1170
From5 MILES SOUTH OF FM 608
ToSH 70
CSJ2033-02-012
Proj IDC 2033-2-12
Work TypeRESTORATION
 
11.74911229184.128409538.8974.8
CountyNOLAN
HighwayFM 1170
FromOAK CREEK
To.
CSJ2033-02-013
Proj IDC 2033-2-13
Work TypeBRIDGE REPLACEMENT
 
0.0361230937.50984428.5979.9
Work Order06-14-23
Work Began10-09-23
Work Completed
Time Computed07-14-23
Contract Working Days269
Addl Days Granted0
Working Days Charged219
Percent Time Used81
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2033-02-012
CONTRACTORS SERVICE, LTD. (0.71)
FLAT LINE, INC. (1.18)
HJC FARMS, INC. (1.41)
DK CONTRACTING, LLC (1.41)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.27)
TORO BRAVO CONSTRUCTION, LLC (0.05)
Contract #05233011
Totals12460121.621180102.019393967.4875.3

CountySCURRY
HighwayFM 1673
FromFM 1673
ToUS 84
CSJ2189-01-020
Proj IDBR 2024(664)
Work TypeBRIDGE REPLACEMENT
 
7348904.502717943.8736.9
Work Order02-05-24
Work Began07-15-24
Work Completed
Time Computed03-06-24
Contract Working Days126
Addl Days Granted0
Working Days Charged69
Percent Time Used54
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2189-01-020
FC TRAFFIC CONTROL, INC. (0.08)
TRP CONSTRUCTION GROUP, LLC (0.15)
AWP SAFETY (0.07)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.42)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.25)
TORO BRAVO CONSTRUCTION, LLC (0.08)
S & S BRIDGE PAINTING, INC. (0.00)
Contract #01243019
Totals7348904.501228228.872717943.8736.9

CountyNOLAN
HighwayFM 608
FromFISHER COUNTY
ToBU 84-J
CSJ2379-02-010
Proj IDC 2379-2-10
Work TypeREHABILITATION OF EXISTING ROAD
 
5.2894084995.252292606.4156.1
Work Order10-25-23
Work Began06-10-24
Work Completed
Time Computed11-24-23
Contract Working Days134
Addl Days Granted0
Working Days Charged86
Percent Time Used64
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2379-02-010
CONTRACTORS SERVICE, LTD. (0.95)
FLAT LINE, INC. (2.30)
HJC FARMS, INC. (1.08)
Contract #09233014
Totals4084995.25637991.402292606.4156.1

CountyTAYLOR
HighwaySL 322
FromLYTLE CREEK
ToUS 83
CSJ2398-01-055
Proj IDSTP 2024(844)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1032617.50576424.4455.8
Work Order05-16-24
Work Began09-16-24
Work Completed
Time Computed05-25-24
Contract Working Days73
Addl Days Granted0
Working Days Charged28
Percent Time Used38
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2398-01-055
CONTRACTORS SERVICE, LTD. (1.25)
Contract #04243227
Totals1032617.50409695.87576424.4455.8

page 1 | page 2 | page 3