Monthly Local Let Maintenance Report For Amarillo District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6191-59-001
Proj IDRMC - 619159001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.001276000.00424600.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-10
Work Began04-05-10
Work Completed
Time Computed04-05-10
Contract Working Days730
Addl Days Granted790
Working Days Charged1,487
Percent Time Used97
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02100401
Totals276000.000.00424600.0099.9

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6191-88-001
Proj IDRMC - 619188001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001289367.38558483.97100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-04-10
Work Began10-04-10
Work Completed07-20-14
Time Computed10-04-10
Contract Working Days146
Addl Days Granted0
Working Days Charged114
Percent Time Used78
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05100406
Totals289367.380.00558483.97100.0

CountyGRAY
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6191-93-001
Proj IDRMC - 619193001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001335852.72663814.2499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-10
Work Began10-11-10
Work Completed
Time Computed10-11-10
Contract Working Days207
Addl Days Granted207
Working Days Charged235
Percent Time Used56
Contractor(s)
3JB CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6191-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05100409
Totals335852.720.00663814.2499.9

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6224-70-001
Proj IDRMC - 622470001
Work TypeON CALL STRIPING
 
0.001292000.68291224.78100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-11
Work Began06-14-11
Work Completed08-31-11
Time Computed06-15-11
Contract Working Days100
Addl Days Granted0
Working Days Charged33
Percent Time Used33
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6224-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05110404
Totals292000.680.00291224.78100.0

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6245-10-001
Proj IDRMC - 624510001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001175332.44118771.1867.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-12
Work Began11-12-12
Work Completed
Time Computed11-12-12
Contract Working Days72
Addl Days Granted10
Working Days Charged76
Percent Time Used92
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07120401
Totals175332.440.00118771.1867.7

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6245-11-001
Proj IDRMC - 624511001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001245032.00234833.4096.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-12
Work Began10-18-12
Work Completed
Time Computed10-18-12
Contract Working Days139
Addl Days Granted0
Working Days Charged47
Percent Time Used33
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6245-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07120402
Totals245032.000.00234833.4096.4

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6252-37-001
Proj IDRMC - 625237001
Work TypeTRAFFIC CONTROL
 
0.001192016.5075269.9539.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-13
Work Began01-21-13
Work Completed
Time Computed01-21-13
Contract Working Days365
Addl Days Granted0
Working Days Charged131
Percent Time Used35
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12120401
Totals192016.500.0075269.9539.1

CountyHUTCHINSON
HighwaySH0207
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6276-78-001
Proj IDSUP - 627678001
Work TypeBORGER JANITORIAL
 
0.0016491.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08140421
Totals6491.730.000.000.0

CountyHARTLEY
HighwayFM0807
From6382-35 DISTRICT WIDE IN-HOUSE FLEX BASE
To6382-35 DISTRICT WIDE IN-HOUSE FLEX BASE
CSJ6382-35-001
Proj IDMMC - 638235001
Work TypeFLEXIBLE BASE
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
B & G ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 6382-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03220440
Totals0.000.000.000.0

CountyOLDHAM
HighwayIH0040
FromAMARILLO AREA LIMESTONE ROCK ASPHALT
ToAMARILLO AREA LIMESTONE ROCK ASPHALT
CSJ6396-06-001
Proj IDMMC - 639606001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03220441
Totals0.000.000.000.0

CountyMOORE
HighwayUS0087
FromDUMAS AREA LIMESTONE ROCK ASPHALT
ToDUMAS AREA LIMESTONE ROCK APSHALT
CSJ6396-07-001
Proj IDMMC - 639607001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03220442
Totals0.000.000.000.0

CountyOCHILTREE
HighwaySH0015
FromPAMPA AREA LIMESTONE ROCK ASPHALT
ToPAMPA AREA LIMESTONE ROCK ASPHALT
CSJ6396-08-001
Proj IDMMC - 639608001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03220443
Totals0.000.000.000.0

CountyHANSFORD
HighwaySH0015
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6397-74-001
Proj IDMMC - 639774001
Work TypeHOT MIX
 
0.010233250.00854068.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-23
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted240
Working Days Charged480
Percent Time Used100
Contractor(s)
BIG CREEK SAND & GRAVEL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230442
Totals233250.003653.64854068.6699.9

CountyHEMPHILL
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6397-75-001
Proj IDMMC - 639775001
Work TypeHOT MIX
 
0.010233250.001652299.7199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-18-23
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted240
Working Days Charged480
Percent Time Used100
Contractor(s)
BIG CREEK SAND & GRAVEL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230443
Totals233250.000.001652299.7199.9

CountyPOTTER
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6417-16-001
Proj IDRMC - 641716001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010229127.77438826.1699.9
Work Order00-00-00
Work Began09-21-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged711
Percent Time Used97
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6417-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08220401
Totals229127.770.00438826.1699.9

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6431-85-001
Proj IDRMC - 643185001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010250430.00424107.5599.9
Work Order00-00-00
Work Began02-20-23
Work Completed
Time Computed02-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged620
Percent Time Used84
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6431-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01230401
Totals250430.000.00424107.5599.9

CountyRANDALL
HighwayIH0027
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6453-40-001
Proj IDSUP - 645340001
Work TypeJANITORIAL MAINTENANCE
 
0.01083294.6682103.6298.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-40-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08230420
Totals83294.666407.4782103.6298.5

CountyRANDALL
HighwayFM1541
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6453-42-001
Proj IDSUP - 645342001
Work TypeJANITORIAL MAINTENANCE
 
0.01022535.5216023.0971.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-42-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08230421
Totals22535.521486.9416023.0971.1

CountyMOORE
HighwayFM2203
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6453-44-001
Proj IDSUP - 645344001
Work TypeJANITORIAL MAINTENANCE
 
0.01015802.0814760.4693.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-44-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08230422
Totals15802.081170.6714760.4693.4

CountyGRAY
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6453-63-001
Proj IDRMC - 645363001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010159649.88175566.5799.9
Work Order00-00-00
Work Began10-04-23
Work Completed
Time Computed10-09-23
Contract Working Days366
Addl Days Granted365
Working Days Charged394
Percent Time Used53
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09230401
Totals159649.8833618.73175566.5799.9