Monthly Local Let Maintenance Report For Amarillo District As Of Mar 10, 2023 Page 2 Of 4

Last Update: Friday, March 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6366-65-001
Proj IDRMC - 636665001
Work TypeON CALL GUARDRAIL REPAIR
 
0.001266690.00125304.5346.9
Work Order00-00-00
Work Began09-17-20
Work Completed
Time Computed09-10-20
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6366-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08200401
Totals266690.0021519.53125304.5346.9

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6368-31-001
Proj IDRMC - 636831001
Work TypeBRIDGE REPAIR
 
0.00168920.0068904.0099.9
Work Order00-00-00
Work Began12-01-20
Work Completed
Time Computed10-15-20
Contract Working Days20
Addl Days Granted0
Working Days Charged4
Percent Time Used20
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6368-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09200401
Totals68920.0068904.0068904.0099.9

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6371-97-001
Proj IDRMC - 637197001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001184030.00346407.5099.9
Work Order00-00-00
Work Began02-22-21
Work Completed
Time Computed12-04-20
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6371-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11200401
Totals184030.000.00346407.5099.9

CountyRANDALL
HighwayUS0060
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-99-001
Proj IDRMC - 637399001
Work TypeROUTINE MAINTENANCE PROJECT
 
47343.0049002.0099.9
Work Order00-00-00
Work Began02-26-21
Work Completed
Time Computed01-11-21
Contract Working Days40
Addl Days Granted0
Working Days Charged5
Percent Time Used12
Contractor(s)
FOWLER CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6373-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12200402
Totals47343.0028100.0049002.0099.9

CountyPOTTER
HighwaySL0335
FromVARIOUS LOCATIONS SEE PLAN SHEETS
ToVARIOUS LOCATIONS SEE PLAN SHEETS
CSJ6376-35-001
Proj IDBPM - 637635001
Work TypeBRIDGE REPAIR
 
0.010130240.00128440.0098.6
Work Order00-00-00
Work Began07-08-21
Work Completed
Time Computed04-01-21
Contract Working Days40
Addl Days Granted0
Working Days Charged22
Percent Time Used55
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02210401
Totals130240.00128440.00128440.0098.6

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS SEE PLAN SHEETS
ToVARIOUS LOCATIONS SEE PLAN SHEETS
CSJ6381-91-001
Proj IDSUP - 638191001
Work TypeLITTER REMOVAL
 
0.010263078.02369551.1699.9
Work Order00-00-00
Work Began05-03-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted365
Working Days Charged669
Percent Time Used91
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6381-91-001
FRESH START OF MONROE INC. (0.00)
Contract #04210420
Totals263078.0215653.71369551.1699.9

CountyHARTLEY
HighwayFM0807
From6382-35 DISTRICT WIDE IN-HOUSE FLEX BASE
To6382-35 DISTRICT WIDE IN-HOUSE FLEX BASE
CSJ6382-35-001
Proj IDMMC - 638235001
Work TypeFLEXIBLE BASE
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
B & G ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 6382-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03220440
Totals0.000.000.000.0

CountyGRAY
HighwaySH0070
FromPAMPA AREA WWM BOTTOM ASH
ToPAMPA AREA WWM BOTTOM ASH
CSJ6382-49-001
Proj IDMMC - 638249001
Work TypeWINTER WEATHER MATERIAL
 
0.010161327.2555185.5734.2
Work Order00-00-00
Work Began03-01-22
Work Completed
Time Computed02-09-22
Contract Working Days120
Addl Days Granted240
Working Days Charged359
Percent Time Used99
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6382-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220442
Totals161327.250.0055185.5734.2

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS SEE PLAN SHEETS
ToVARIOUS LOCATIONS SEE PLAN SHEETS
CSJ6385-06-001
Proj IDRMC - 638506001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010257535.00329345.0099.9
Work Order00-00-00
Work Began09-27-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged339
Percent Time Used92
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6385-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07210401
Totals257535.000.00329345.0099.9

CountyGRAY
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6388-45-001
Proj IDRMC - 638845001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010127933.06167197.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-18-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged499
Percent Time Used68
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09210401
Totals127933.060.00167197.7999.9

CountyMOORE
HighwayFM2203
FromDUMAS AE AND MAINTENANCE OFFICE
ToDUMAS AE AND MAINTENANCE OFFICE
CSJ6390-21-001
Proj IDSUP - 639021001
Work TypeJANITORIAL MAINTENANCE
 
0.01015341.8814632.3295.3
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-21-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08210423
Totals15341.88994.6714632.3295.3

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6391-09-001
Proj IDRMC - 639109001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010349351.00125791.0036.0
Work Order00-00-00
Work Began11-17-21
Work Completed
Time Computed11-22-21
Contract Working Days365
Addl Days Granted0
Working Days Charged349
Percent Time Used95
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6391-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10210401
Totals349351.004770.00125791.0036.0

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6392-02-001
Proj IDSUP - 639202001
Work TypePICNIC AREA MAINTENANCE
 
0.010156689.12117506.5474.9
Work Order00-00-00
Work Began10-01-21
Work Completed
Time Computed10-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6392-02-001
FRESH START OF MONROE INC. (0.00)
Contract #09210420
Totals156689.1213874.86117506.5474.9

CountyGRAY
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6393-16-001
Proj IDRMC - 639316001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010369250.00319738.9086.5
Work Order00-00-00
Work Began02-15-22
Work Completed
Time Computed01-03-22
Contract Working Days365
Addl Days Granted59
Working Days Charged393
Percent Time Used92
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6393-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210401
Totals369250.0034590.00319738.9086.5

CountyGRAY
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6393-31-001
Proj IDRMC - 639331001
Work TypeTREE REMOVAL
 
0.010232615.00248065.0099.9
Work Order00-00-00
Work Began01-24-22
Work Completed
Time Computed12-20-21
Contract Working Days60
Addl Days Granted0
Working Days Charged52
Percent Time Used86
Contractor(s)
GV LANDSCAPE AND CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210403
Totals232615.0042095.00248065.0099.9

CountyPOTTER
HighwayIH0040
FromAMARILLO DISTRICT PAVEMENT MARKINGS
ToAMARILLO DISTRICT PAVEMENT MARKINGS
CSJ6395-18-001
Proj IDMMC - 639518001
Work TypePAVEMENT MARKINGS
 
0.010152815.0024716.5016.1
Work Order00-00-00
Work Began03-01-22
Work Completed
Time Computed02-09-22
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6395-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220443
Totals152815.000.0024716.5016.1

CountyARMSTRONG
HighwayUS0287
FromAMARILLO AREA MAINT SECT. SEAL COAT AGGR
ToAMARILLO AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-90-001
Proj IDMMC - 639590001
Work TypeSEAL COAT
 
0.010328343.50336055.8399.9
Work Order00-00-00
Work Began03-10-22
Work Completed
Time Computed03-15-22
Contract Working Days120
Addl Days Granted240
Working Days Charged354
Percent Time Used98
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220440
Totals328343.5023421.91336055.8399.9

CountyDALLAM
HighwayUS0054
FromDUMAS AREA MAINT SECT. SEAL COAT AGGR
ToDUMAS AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-91-001
Proj IDMMC - 639591001
Work TypeSEAL COAT
 
0.010333845.45272480.1981.6
Work Order00-00-00
Work Began03-10-22
Work Completed
Time Computed03-10-22
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220441
Totals333845.450.00272480.1981.6

CountyCARSON
HighwayIH0040
FromPAMPA AREA MAINT SECT. SEAL COAT AGGR
ToPAMPA AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-92-001
Proj IDMMC - 639592001
Work TypeSEAL COAT
 
0.010332334.00449262.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-10-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged354
Percent Time Used98
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220442
Totals332334.00170011.63449262.7999.9

CountyDEAF SMITH
HighwayUS0385
FromAMARILLO AREA MAINT SECTIONS HMAC PU/DEL
ToAMARILLO AREA MAINT SECTIONS HMAC PU/DEL
CSJ6395-93-001
Proj IDMMC - 639593001
Work TypeHOT MIX
 
0.010281390.000.000.0
Work Order00-00-00
Work Began04-13-22
Work Completed
Time Computed04-13-22
Contract Working Days120
Addl Days Granted240
Working Days Charged322
Percent Time Used89
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6395-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220443
Totals281390.000.000.000.0

page 1 | page 2 | page 3 | page 4