Monthly State Let Maintenance Report For Atlanta District As Of Jul 13, 2021 Page 1 Of 2

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.0012820782.2199.9
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged1,398
Percent Time Used95
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.00368762.2512820782.2199.9

CountyBOWIE
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTH ATL DIST
To.
CSJ6324-84-001
Proj IDRMC - 632484001
Work TypeCALLOUT MILL & INLAY (NORTH)
 
0.0014231200.004178138.7398.7
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged58
Percent Time Used38
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-84-001
STRIPING TECHNOLOGY, L.P. (0.43)
Contract #09184021
Totals4231200.00327699.434178138.7398.7

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATION IN SOUTH ATL DIST
To.
CSJ6324-85-001
Proj IDRMC - 632485001
Work TypeCALLOUT MILL & INLAY (SOUTH)
 
0.0013931850.004898115.4399.9
Work Order12-06-18
Work Began12-11-18
Work Completed
Time Computed12-11-18
Contract Working Days150
Addl Days Granted0
Working Days Charged35
Percent Time Used23
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-85-001
STRIPING TECHNOLOGY, L.P. (0.58)
Contract #09184218
Totals3931850.000.004898115.4399.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6332-57-001
Proj IDRMC - 633257001
Work TypeCALLOUT PREFABRICATED PAVEMENT MARKINGS
 
0.001503830.00305798.51100.0
Work Order00-00-00
Work Began12-18-18
Work Completed01-26-21
Time Computed11-01-18
Contract Working Days254
Addl Days Granted254
Working Days Charged492
Percent Time Used96
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6332-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184015
Totals503830.000.00305798.51100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS -ATL DISTRICT
ToDISTRICT WIDE
CSJ6333-11-001
Proj IDRMC - 633311001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001899825.001027728.17100.0
Work Order00-00-00
Work Began12-19-18
Work Completed02-08-21
Time Computed12-19-18
Contract Working Days254
Addl Days Granted254
Working Days Charged493
Percent Time Used97
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-11-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
CATOCON, INC. (2.33)
CARTHAGE DRILLING, INC. (1.02)
Contract #09184013
Totals899825.000.001027728.17100.0

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS LOCATIONS - ATLANTA DISTRICT
CSJ6333-91-001
Proj IDRMC - 633391001
Work TypeCALLOUT RAISED PAVEMENT MARKERS
 
0.001286695.00624051.99100.0
Work Order00-00-00
Work Began02-04-19
Work Completed05-26-21
Time Computed12-10-18
Contract Working Days254
Addl Days Granted254
Working Days Charged504
Percent Time Used99
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184213
Totals286695.000.00624051.99100.0

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.00139005.70100.0
Work Order00-00-00
Work Began02-12-19
Work Completed06-30-20
Time Computed02-12-19
Contract Working Days306
Addl Days Granted123
Working Days Charged376
Percent Time Used87
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0017895.00139005.70100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE
ToATLANTA DISTRICT
CSJ6338-78-001
Proj IDBPM - 633878001
Work TypeCALLOUT BRIDGE PREVENTATIVE MAINTENANCE
 
0.0012098950.001411638.6867.2
Work Order00-00-00
Work Began02-06-20
Work Completed
Time Computed02-03-20
Contract Working Days200
Addl Days Granted0
Working Days Charged178
Percent Time Used89
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-78-001
PANOLA SIGN & BARRICADE, INC. (0.17)
STRIPING TECHNOLOGY, L.P. (0.55)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.14)
Contract #11194002
Totals2098950.006858.001411638.6867.2

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6339-46-001
Proj IDRMC - 633946001
Work TypeGUIDE & CALL-OUT SIGN INSTALLATION
 
0.001576575.001284761.5199.9
Work Order00-00-00
Work Began05-06-19
Work Completed
Time Computed04-01-19
Contract Working Days254
Addl Days Granted254
Working Days Charged483
Percent Time Used95
Contractor(s)
CREATIVE DESIGN CONCEPTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6339-46-001
TIME STRIPING, INC. (6.06)
Contract #12184202
Totals576575.00126043.501284761.5199.9

CountyUPSHUR
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToCAMP,CASS,MARION,MORRIS,TITUS & UPSHUR
CSJ6348-27-001
Proj IDRMC - 634827001
Work TypeTREE AND STUMP REMOVAL (W)
 
0.001482054.00430783.00100.0
Work Order00-00-00
Work Began01-06-20
Work Completed02-10-21
Time Computed01-06-20
Contract Working Days185
Addl Days Granted0
Working Days Charged185
Percent Time Used100
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6348-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194224
Totals482054.008100.00430783.00100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ATL DISTRICT
ToDISTRICTWIDE
CSJ6349-19-001
Proj IDRMC - 634919001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.0011061430.00261609.2024.6
Work Order00-00-00
Work Began02-12-21
Work Completed
Time Computed02-02-21
Contract Working Days254
Addl Days Granted0
Working Days Charged102
Percent Time Used40
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6349-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204001
Totals1061430.0054114.75261609.2024.6

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN THE NORTH AREA
To.
CSJ6351-00-001
Proj IDRMC - 635100001
Work TypeTREE TRIMMING - NORTH
 
180.149334370.92197297.9659.0
Work Order00-00-00
Work Began12-18-20
Work Completed
Time Computed12-14-20
Contract Working Days182
Addl Days Granted0
Working Days Charged47
Percent Time Used25
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6351-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204001
Totals334370.920.00197297.9659.0

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS IN DISTRICT 19
ToVARIOUS ROADWAYS IN DISTRICT 19
CSJ6356-67-001
Proj IDRMC - 635667001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0015399700.002981282.9955.2
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days300
Addl Days Granted0
Working Days Charged148
Percent Time Used49
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6356-67-001
GHB EQUIPMENT COMPANY, L.L.C. (1.24)
Contract #03204001
Totals5399700.000.002981282.9955.2

CountyBOWIE
HighwayUS0059
FromBOWIE & CASS COUNTIES
To.
CSJ6357-08-001
Proj IDRMC - 635708001
Work TypeCALLOUT MBGF REPAIR - NORTH
 
0.001702035.00190677.5027.1
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged253
Percent Time Used41
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204013
Totals702035.0023996.25190677.5027.1

CountyHARRISON
HighwayUS0059
FromHARRISON, PANOLA & MARION COUNTIES
To.
CSJ6357-09-001
Proj IDRMC - 635709001
Work TypeCALLOUT MBGF REPAIR - SOUTH
 
0.001852050.00463400.4054.3
Work Order06-26-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged233
Percent Time Used38
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204014
Totals852050.0018277.50463400.4054.3

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6357-10-001
Proj IDRMC - 635710001
Work TypeCALLOUT MBGF REPAIR - WEST
 
0.001713880.00405409.8556.7
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged305
Percent Time Used49
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204015
Totals713880.0030292.00405409.8556.7

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6362-04-001
Proj IDRMC - 636204001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0108486300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214001
Totals8486300.000.000.000.0

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6363-87-001
Proj IDRMC - 636387001
Work TypePAVEMENT MARKINGS
 
0.010378145.86211759.2155.9
Work Order00-00-00
Work Began05-24-21
Work Completed
Time Computed05-24-21
Contract Working Days254
Addl Days Granted0
Working Days Charged22
Percent Time Used8
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6363-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214001
Totals378145.86159649.61211759.2155.9

page 1 | page 2