Monthly State Let Maintenance Report For Atlanta District As Of May 10, 2023 Page 1 Of 2

Last Update: Wednesday, May 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.00139005.70100.0
Work Order00-00-00
Work Began02-12-19
Work Completed06-30-20
Time Computed02-12-19
Contract Working Days306
Addl Days Granted123
Working Days Charged376
Percent Time Used87
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0017895.00139005.70100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ATL DISTRICT
ToDISTRICTWIDE
CSJ6349-19-001
Proj IDRMC - 634919001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.0011061430.001321890.0599.9
Work Order00-00-00
Work Began02-12-21
Work Completed
Time Computed02-02-21
Contract Working Days254
Addl Days Granted254
Working Days Charged503
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6349-19-001
CARTHAGE DRILLING, INC. (0.61)
Contract #12204001
Totals1061430.000.001321890.0599.9

CountyHARRISON
HighwayUS0080
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6351-01-001
Proj IDRMC - 635101001
Work TypeTREE TRIMMING
 
422724.46194811.8446.0
Work Order00-00-00
Work Began11-15-22
Work Completed
Time Computed10-17-22
Contract Working Days161
Addl Days Granted0
Working Days Charged97
Percent Time Used60
Contractor(s)
FOWLER CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6351-01-001
TERRY ENTERPRISES (0.00)
Contract #04224208
Totals422724.4615841.61194811.8446.0

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS IN DISTRICT 19
ToVARIOUS ROADWAYS IN DISTRICT 19
CSJ6356-67-001
Proj IDRMC - 635667001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0015399700.006244139.3299.9
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days300
Addl Days Granted300
Working Days Charged396
Percent Time Used66
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6356-67-001
GHB EQUIPMENT COMPANY, L.L.C. (1.24)
Contract #03204001
Totals5399700.00126929.506244139.3299.9

CountyBOWIE
HighwayUS0059
FromBOWIE & CASS COUNTIES
To.
CSJ6357-08-001
Proj IDRMC - 635708001
Work TypeCALLOUT MBGF REPAIR - NORTH
 
0.001702035.00623419.4088.8
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged722
Percent Time Used58
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204013
Totals702035.000.00623419.4088.8

CountyHARRISON
HighwayUS0059
FromHARRISON, PANOLA & MARION COUNTIES
To.
CSJ6357-09-001
Proj IDRMC - 635709001
Work TypeCALLOUT MBGF REPAIR - SOUTH
 
0.001852050.001140597.9499.9
Work Order06-26-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged715
Percent Time Used58
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204014
Totals852050.0056274.051140597.9499.9

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6357-10-001
Proj IDRMC - 635710001
Work TypeCALLOUT MBGF REPAIR - WEST
 
0.001713880.00796461.6099.9
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged868
Percent Time Used70
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204015
Totals713880.0018081.00796461.6099.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6362-04-001
Proj IDRMC - 636204001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0108486300.008086445.7595.2
Work Order09-01-21
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days730
Addl Days Granted730
Working Days Charged606
Percent Time Used41
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-04-001
NIXON ENGINEERING (0.00)
Contract #07214001
Totals8486300.00384684.008086445.7595.2

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6367-55-001
Proj IDRMC - 636755001
Work TypeCALLOUT PAVEMENT MARKINGS (VARIOUS)
 
0.001773200.001578036.32100.0
Work Order00-00-00
Work Began04-12-21
Work Completed03-28-23
Time Computed02-01-21
Contract Working Days254
Addl Days Granted254
Working Days Charged507
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6367-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204002
Totals773200.000.001578036.32100.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS ROADWAYS
CSJ6367-56-001
Proj IDRMC - 636756001
Work TypeCALLOUT PREFABRICATED PAVEMENT MARKINGS
 
0.001447950.00298239.02100.0
Work Order00-00-00
Work Began02-01-21
Work Completed03-28-23
Time Computed02-01-21
Contract Working Days254
Addl Days Granted254
Working Days Charged508
Percent Time Used100
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6367-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204009
Totals447950.000.00298239.02100.0

CountyUPSHUR
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToCAMP,CASS,MARION,MORRIS,TITUS & UPSHUR
CSJ6369-72-001
Proj IDRMC - 636972001
Work TypeTREE & STUMP REMOVAL (WEST)
 
0.001406674.00885150.00100.0
Work Order00-00-00
Work Began03-03-21
Work Completed04-03-23
Time Computed02-17-21
Contract Working Days185
Addl Days Granted185
Working Days Charged270
Percent Time Used72
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204012
Totals406674.000.00885150.00100.0

CountyBOWIE
HighwaySH0008
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6370-80-001
Proj IDBPM - 637080001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010656799.00693357.72100.0
Work Order00-00-00
Work Began02-14-22
Work Completed01-06-23
Time Computed02-14-22
Contract Working Days93
Addl Days Granted0
Working Days Charged79
Percent Time Used84
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6370-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214002
Totals656799.000.00693357.72100.0

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6380-05-001
Proj IDRMC - 638005001
Work TypeMILL AND INLAY
 
0.0103880503.502386882.1061.5
Work Order00-00-00
Work Began08-08-22
Work Completed
Time Computed12-09-21
Contract Working Days150
Addl Days Granted0
Working Days Charged29
Percent Time Used19
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6380-05-001
STRIPING TECHNOLOGY, L.P. (0.94)
Contract #07214201
Totals3880503.500.002386882.1061.5

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6380-07-001
Proj IDRMC - 638007001
Work TypeMILL AND INLAY
 
0.0103873220.001481359.2838.2
Work Order00-00-00
Work Began12-06-21
Work Completed
Time Computed09-29-21
Contract Working Days150
Addl Days Granted0
Working Days Charged18
Percent Time Used12
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6380-07-001
DUSTROL, INC. (5.74)
STRIPING TECHNOLOGY, L.P. (0.43)
Contract #07214002
Totals3873220.000.001481359.2838.2

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6398-37-001
Proj IDRMC - 639837001
Work TypeRAISED PAVEMENT MARKERS
 
0.010945465.00461595.7948.8
Work Order00-00-00
Work Began07-22-22
Work Completed
Time Computed07-22-22
Contract Working Days254
Addl Days Granted0
Working Days Charged116
Percent Time Used45
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6398-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224005
Totals945465.000.00461595.7948.8

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6398-38-001
Proj IDRMC - 639838001
Work TypeLARGE SIGN REPLACEMENT
 
0.010667780.00142072.5021.2
Work Order00-00-00
Work Began09-27-22
Work Completed
Time Computed07-01-22
Contract Working Days254
Addl Days Granted0
Working Days Charged205
Percent Time Used80
Contractor(s)
CREATIVE DESIGN CONCEPTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224207
Totals667780.0019850.00142072.5021.2

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6399-87-001
Proj IDRMC - 639987001
Work TypePAVEMENT MARKINGS
 
0.0101118854.86431162.9638.5
Work Order00-00-00
Work Began09-07-22
Work Completed
Time Computed09-06-22
Contract Working Days80
Addl Days Granted0
Working Days Charged40
Percent Time Used50
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6399-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224201
Totals1118854.860.00431162.9638.5

CountyBOWIE
HighwayIH0030
From.
To.
CSJ6407-53-001
Proj IDMMC - 640753001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010780475.003708263.11100.0
Work Order08-24-22
Work Began09-26-22
Work Completed04-29-23
Time Computed09-01-22
Contract Working Days120
Addl Days Granted120
Working Days Charged240
Percent Time Used100
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6407-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224409
Totals780475.000.003708263.11100.0

page 1 | page 2