Monthly State Let Maintenance Report For Atlanta District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.00139005.70100.0
Work Order00-00-00
Work Began02-12-19
Work Completed06-30-20
Time Computed02-12-19
Contract Working Days306
Addl Days Granted123
Working Days Charged376
Percent Time Used87
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0017895.00139005.70100.0

CountyBOWIE
HighwayUS0059
FromBOWIE & CASS COUNTIES
To.
CSJ6357-08-001
Proj IDRMC - 635708001
Work TypeCALLOUT MBGF REPAIR - NORTH
 
0.001702035.00957883.2899.9
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged1,107
Percent Time Used90
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204013
Totals702035.000.00957883.2899.9

CountyHARRISON
HighwayUS0059
FromHARRISON, PANOLA & MARION COUNTIES
To.
CSJ6357-09-001
Proj IDRMC - 635709001
Work TypeCALLOUT MBGF REPAIR - SOUTH
 
0.001852050.001768486.3999.9
Work Order06-26-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged1,095
Percent Time Used89
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204014
Totals852050.0024468.101768486.3999.9

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6357-10-001
Proj IDRMC - 635710001
Work TypeCALLOUT MBGF REPAIR - WEST
 
0.001713880.001045311.5599.9
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged1,110
Percent Time Used90
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204015
Totals713880.0020522.001045311.5599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6362-04-001
Proj IDRMC - 636204001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0108486300.0015376854.5099.9
Work Order09-01-21
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days730
Addl Days Granted730
Working Days Charged1,147
Percent Time Used78
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-04-001
NIXON ENGINEERING (0.00)
Contract #07214001
Totals8486300.00481147.5015376854.5099.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6398-37-001
Proj IDRMC - 639837001
Work TypeRAISED PAVEMENT MARKERS
 
0.010945465.001386539.7699.9
Work Order00-00-00
Work Began07-22-22
Work Completed
Time Computed07-22-22
Contract Working Days254
Addl Days Granted254
Working Days Charged475
Percent Time Used93
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6398-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224005
Totals945465.0028945.401386539.7699.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6398-38-001
Proj IDRMC - 639838001
Work TypeLARGE SIGN REPLACEMENT
 
0.010667780.00659683.8098.7
Work Order00-00-00
Work Began09-27-22
Work Completed
Time Computed07-01-22
Contract Working Days254
Addl Days Granted254
Working Days Charged453
Percent Time Used89
Contractor(s)
CREATIVE DESIGN CONCEPTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224207
Totals667780.000.00659683.8098.7

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToBOWIE & CASS COUNTIES
CSJ6413-91-001
Proj IDRMC - 641391001
Work TypeTREE REMOVAL
 
0.010299104.00600332.0099.9
Work Order00-00-00
Work Began01-04-23
Work Completed
Time Computed01-02-23
Contract Working Days150
Addl Days Granted150
Working Days Charged137
Percent Time Used45
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224204
Totals299104.000.00600332.0099.9

CountyUPSHUR
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToCAMP,CASS,MARION,MORRIS,TITUS & UPSHUR
CSJ6413-95-001
Proj IDRMC - 641395001
Work TypeTREE REMOVAL
 
0.010279524.00777817.4599.9
Work Order00-00-00
Work Began04-03-23
Work Completed
Time Computed04-03-23
Contract Working Days150
Addl Days Granted105
Working Days Charged168
Percent Time Used65
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-95-001
EASTGATE SERVICES (94.11)
Contract #09224205
Totals279524.000.00777817.4599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6425-02-001
Proj IDRMC - 642502001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101081105.00921981.6085.2
Work Order00-00-00
Work Began02-17-23
Work Completed
Time Computed02-17-23
Contract Working Days254
Addl Days Granted254
Working Days Charged418
Percent Time Used82
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6425-02-001
CARTHAGE DRILLING, INC. (4.47)
Contract #12224218
Totals1081105.0010168.00921981.6085.2

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6425-14-001
Proj IDRMC - 642514001
Work TypePAVEMENT MARKINGS
 
0.010334545.00232695.0069.5
Work Order00-00-00
Work Began03-01-23
Work Completed
Time Computed03-01-23
Contract Working Days254
Addl Days Granted254
Working Days Charged410
Percent Time Used80
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6425-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224219
Totals334545.0016004.00232695.0069.5

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6425-16-001
Proj IDRMC - 642516001
Work TypePAVEMENT MARKINGS
 
0.0101051650.002327276.6099.9
Work Order00-00-00
Work Began05-16-23
Work Completed
Time Computed03-01-23
Contract Working Days254
Addl Days Granted254
Working Days Charged412
Percent Time Used81
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6425-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224220
Totals1051650.00434967.502327276.6099.9

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
To.
CSJ6441-07-001
Proj IDRMC - 644107001
Work TypeCONCRETE SPALL REPAIR
 
0.0106993700.001391370.6719.8
Work Order00-00-00
Work Began01-24-24
Work Completed
Time Computed01-24-24
Contract Working Days200
Addl Days Granted0
Working Days Charged182
Percent Time Used91
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6441-07-001
GHB EQUIPMENT COMPANY, L.L.C. (30.02)
Contract #08234006
Totals6993700.00583447.761391370.6719.8

CountyBOWIE
HighwayUS0067
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6452-09-001
Proj IDBPM - 645209001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010549785.001055932.70100.0
Work Order00-00-00
Work Began02-06-24
Work Completed09-12-24
Time Computed02-06-24
Contract Working Days100
Addl Days Granted79
Working Days Charged47
Percent Time Used26
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6452-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234201
Totals549785.0070594.001055932.70100.0

CountyHARRISON
HighwayUS0080
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-81-001
Proj IDRMC - 645381001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010311644.86248304.1579.6
Work Order00-00-00
Work Began05-28-24
Work Completed
Time Computed05-28-24
Contract Working Days87
Addl Days Granted0
Working Days Charged72
Percent Time Used82
Contractor(s)
DCC CONSTRUCTION AND SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6453-81-001
RISE UP CONSTRUCTION LLC (100.00)
Contract #01244203
Totals311644.8678700.05248304.1579.6

CountyBOWIE
HighwayIH0030
FromIH0030/US0059
ToIH0030/US0059
CSJ6457-45-001
Proj IDRMC - 645745001
Work TypeLANDSCAPE MAINTENANCE
 
0.010410162.40137837.4033.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days717
Addl Days Granted0
Working Days Charged274
Percent Time Used38
Contractor(s)
SOUTHERN EDGE CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234202
Totals410162.4019995.70137837.4033.6

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-15-001
Proj IDRMC - 646215001
Work TypeMILL AND INLAY
 
0.0106564750.001400509.1321.3
Work Order00-00-00
Work Began08-05-24
Work Completed
Time Computed08-05-24
Contract Working Days150
Addl Days Granted0
Working Days Charged11
Percent Time Used7
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-15-001
STRIPING TECHNOLOGY, L.P. (1.84)
TEXOP CONSTRUCTION (3.13)
Contract #03244002
Totals6564750.000.001400509.1321.3

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-16-001
Proj IDRMC - 646216001
Work TypeMILL AND INLAY
 
0.0106136950.001572626.4225.6
Work Order00-00-00
Work Began08-21-24
Work Completed
Time Computed08-20-24
Contract Working Days150
Addl Days Granted0
Working Days Charged9
Percent Time Used6
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-16-001
STRIPING TECHNOLOGY, L.P. (2.36)
Contract #03244201
Totals6136950.000.001572626.4225.6

page 1 | page 2