Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOWIE
HighwayUS0067
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6452-09-001
Proj IDBPM - 645209001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010549785.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-06-24
Work Completed
Time Computed02-06-24
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6452-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234201
Totals549785.000.000.000.0

CountyHARRISON
HighwayUS0080
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-81-001
Proj IDRMC - 645381001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010311644.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days87
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DCC CONSTRUCTION AND SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6453-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244203
Totals311644.860.000.000.0

CountyBOWIE
HighwayIH0030
FromIH0030/US0059
ToIH0030/US0059
CSJ6457-45-001
Proj IDRMC - 645745001
Work TypeLANDSCAPE MAINTENANCE
 
0.010410162.4037200.009.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days717
Addl Days Granted0
Working Days Charged3
Percent Time Used0
Contractor(s)
SOUTHERN EDGE CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234202
Totals410162.4037200.0037200.009.0

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS IN THE ATL DISTRICT
To.
CSJ6457-57-001
Proj IDMMC - 645757001
Work TypeAGGREGATE
 
0.010314430.00125570.5639.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged31
Percent Time Used25
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234002
Totals314430.00125570.56125570.5639.9

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-18-001
Proj IDRMC - 646218001
Work TypeCABLE BARRIER REPAIR
 
0.010667815.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days612
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244228
Totals667815.000.000.000.0

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-19-001
Proj IDRMC - 646219001
Work TypeCABLE BARRIER REPAIR
 
0.010478435.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days612
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244229
Totals478435.000.000.000.0