Monthly State Let Maintenance Report For Austin District As Of Nov 10, 2024 Page 1 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayUS0183
FromUS 183 FLYOVER
ToLOOP 1
CSJ6221-30-001
Proj IDRMC - 622130001
Work TypeREPAIR DAMAGE TO BRIDGE FROM FIRE
 
1.000319429.00259709.7981.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-11
Work Began08-01-11
Work Completed
Time Computed08-01-11
Contract Working Days20
Addl Days Granted2
Working Days Charged22
Percent Time Used100
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04114012
Totals319429.000.00259709.7981.3

CountyWILLIAMSON
HighwayFM1331
FromCR 418
ToMILAM CO. LINE
CSJ6246-44-001
Proj IDRMC - 624644001
Work TypePAVEMENT REPAIR, LEVEL-UP & SEAL COAT
 
0.001627289.00731428.05100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-13
Work Began09-23-13
Work Completed08-19-14
Time Computed09-23-13
Contract Working Days30
Addl Days Granted20
Working Days Charged50
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6246-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02134007
Totals627289.000.00731428.05100.0

CountyWILLIAMSON
HighwayFM1460
FromSS 26
ToHIGH TECH DRIVE
CSJ6246-53-001
Proj IDRMC - 624653001
Work TypeMILL, SEAL AND OVERLAY
 
0.603336667.00373547.9899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-13
Work Began08-03-13
Work Completed
Time Computed07-26-13
Contract Working Days32
Addl Days Granted0
Working Days Charged30
Percent Time Used93
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6246-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134008
Totals336667.000.00373547.9899.9

CountyGILLESPIE
HighwayUS0087
FromVARIOUS ROADS IN GILLESPIE AND
ToBURNET COUNTIES
CSJ6246-77-001
Proj IDRMC - 624677001
Work TypeMILL, SEAL AND OVERLAY
 
3.2061253789.621405849.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-13
Work Began09-16-13
Work Completed09-30-15
Time Computed09-16-13
Contract Working Days28
Addl Days Granted0
Working Days Charged54
Percent Time Used192
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6246-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134028
Totals1253789.620.001405849.16100.0

CountyTRAVIS
HighwayLP0001
FromVAR LOCATIONS ON LP1,IH35,US183,
ToUS290/71,FM 734
CSJ6246-86-001
Proj IDRMC - 624686001
Work TypeVARIOUS ROADSIDE MAINTENANCE
 
62.4104133013.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6246-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03134020
Totals4133013.120.000.000.0

CountyGILLESPIE
HighwayUS0290
FromDISTRICT 14: TRAVIS, WILLIAMSON,
ToMASON, LLANO, BURNET, GILLESPIE, BLANCO
CSJ6273-72-001
Proj IDRMC - 627372001
Work TypeREPAIR AND UPGRADE MBGF
 
0.1001417549.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10144006
Totals1417549.900.000.000.0

CountyLLANO
HighwaySH0071
FromVARIOUS LOCATIONS IN LLANO, BURNET,
ToMASON AND BLANCO COUNTIES
CSJ6318-61-001
Proj IDRMC - 631861001
Work TypeTREE AND BRUSH REMOVAL
 
159.616216352.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
UNITY CONTRACTOR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174007
Totals216352.800.000.000.0

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS ON IH 35, LP 1,
ToUS 183, US 290, ETC.
CSJ6325-60-001
Proj IDRMC - 632560001
Work TypeVARIOUS ROADSIDE MAINTENANCE
 
0.10039712405.0064809245.4999.9
Work Order00-00-00
Work Began03-01-19
Work Completed
Time Computed03-01-19
Contract Working Days1,827
Addl Days Granted1,826
Working Days Charged2,072
Percent Time Used56
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-60-001
CEN-TEX IRRIGATION SYSTEMS, INC. (0.00)
MPR SERVICES (0.00)
BK FIELD OPERATIONS LLC (0.00)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00)
RESTEK, INC. (0.00)
THE CLEANING GUYS, LLC (0.00)
Contract #11184005
Totals39712405.001093357.8864809245.4999.9

CountyTRAVIS
HighwaySH0130
FromVARIOUS LOCATIONS ON SH 130,
ToLP 1, AND SH 45
CSJ6336-08-001
Proj IDRMC - 633608001
Work TypePERFORMANCE BASED CONTRACT
 
70.40022626610.0026917176.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-20
Work Completed
Time Computed00-00-00
Contract Working Days1,826
Addl Days Granted0
Working Days Charged1,492
Percent Time Used81
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6336-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204211
Totals22626610.00438491.9426917176.3999.9

CountyTRAVIS
HighwaySH0130
FromUS 79
ToUS 290
CSJ6340-46-001
Proj IDRMC - 634046001
Work TypeACP OVERLAY
 
0.01034906067.3538614504.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted163
Working Days Charged298
Percent Time Used92
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6340-46-001
MAIN LANE INDUSTRIES LTD. (7.38)
MPB, INC. (0.51)
PENHALL COMPANY (5.17)
RPV CONSTRUCTION, LLC (3.61)
RUCOBA & MAYA CONSTRUCTION, LLC (2.01)
SAN ANTONIO SWEEPING SERVICES, INC. (0.25)
STRIPE IT UP, LLC (0.02)
TRP CONSTRUCTION GROUP, LLC (2.10)
TEXAS TRAFFIC AND BARRICADE, LLC (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.91)
HOLES INCORPORATED (0.00)
STRIPES & STOPS COMPANY, INC. (0.00)
MC2 CIVIL, LLC (7.38)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.05)
Contract #04234203
Totals34906067.353836010.0238614504.6699.9

CountyTRAVIS
HighwaySH0130
FromUS 290
ToSH 71
CSJ6340-47-001
Proj IDRMC - 634047001
Work TypeACP OVERLAY
 
0.01040923831.4219407023.4647.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-25-24
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged169
Percent Time Used46
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6340-47-001
TRP CONSTRUCTION GROUP, LLC (2.52)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.16)
MC2 CIVIL, LLC (27.61)
PENHALL COMPANY (3.89)
SAN ANTONIO SWEEPING SERVICES, INC. (0.21)
SCR CIVIL CONSTRUCTION, LLC (0.42)
STRIPE IT UP, LLC (0.02)
HOLES INCORPORATED (0.00)
TEXAS CURB CUT (0.24)
TEXAS TRAFFIC AND BARRICADE, LLC (0.02)
Contract #12234004
Totals40923831.421564818.4019407023.4647.4

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToTHE AUSTIN DISTRICT
CSJ6367-81-001
Proj IDRMC - 636781001
Work TypePAVEMENT MARKINGS
 
0.0103724890.754473802.2199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted275
Working Days Charged956
Percent Time Used95
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6367-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214006
Totals3724890.75328228.414473802.2199.9

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6368-89-001
Proj IDRMC - 636889001
Work TypeMAINTENANCE OF LARGE SIGNS
 
0.010388451.41746031.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-27-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted365
Working Days Charged1,094
Percent Time Used99
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6368-89-001
TRP CONSTRUCTION GROUP, LLC (0.00)
Contract #04214002
Totals388451.410.00746031.1099.9

CountyBASTROP
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToTHE AUSTIN DISTRICT
CSJ6386-68-001
Proj IDRMC - 638668001
Work TypeSKID RESTORATION (NON-REHAB)
 
0.0108286398.332997875.4136.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-27-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged524
Percent Time Used71
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6386-68-001
SKIDABRADER GROUP LLC (0.00)
Contract #03224203
Totals8286398.330.002997875.4136.1

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToTRAVIS COUNTY
CSJ6387-69-001
Proj IDRMC - 638769001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010591420.00240762.0040.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted17
Working Days Charged25
Percent Time Used24
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6387-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234201
Totals591420.00173634.00240762.0040.7

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToTHE AUSTIN DISTRICT
CSJ6391-93-001
Proj IDBPM - 639193001
Work TypeBRIDGE REPAIR
 
0.0101429650.001389528.5997.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-27-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged226
Percent Time Used30
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-93-001
ENVIRONMENTAL SAFETY SERVICES, INC. (74.24)
PRIMETEX MATERIALS LLC (17.49)
Contract #03224003
Totals1429650.00188697.941389528.5997.1

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS
ToIN THE AUSTIN DISTRICT
CSJ6399-60-001
Proj IDRMC - 639960001
Work TypeCONCRETE SPALL REPAIR
 
0.0101723645.002883934.44100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed08-31-24
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-60-001
AARON CONCRETE CONTRACTORS, L.P. (0.00)
AARON CONCRETE CONTRACTORS, LLC (22.63)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.56)
TRP CONSTRUCTION GROUP, LLC (1.74)
SAWMAN LLC (0.08)
Contract #06224204
Totals1723645.000.002883934.44100.0

CountyBASTROP
HighwayUS0290
FromVARIOUS LOCATIONS IN BASTROP,
ToCALDWELL, AND LEE COUNTIES
CSJ6405-24-001
Proj IDRMC - 640524001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0102144000.002679522.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged701
Percent Time Used96
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6405-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224208
Totals2144000.00132109.502679522.5099.9

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToTHE AUSTIN DISTRICT
CSJ6405-28-001
Proj IDRMC - 640528001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101241630.00620936.0050.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged631
Percent Time Used86
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6405-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224006
Totals1241630.00100800.00620936.0050.0

CountyWILLIAMSON
HighwaySH0195
FromVARIOUS LOCATIONS IN
ToWILLIAMSON COUNTY
CSJ6405-30-001
Proj IDRMC - 640530001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010510828.00367452.0071.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-23
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged35
Percent Time Used28
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6405-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234203
Totals510828.000.00367452.0071.9