|
| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | WILLIAMSON |
| Highway | US0079 |
| From | VARIOUS LOCATIONS IN |
| To | WILLIAMSON COUNTY |
| CSJ | 6405-32-001 |
| Proj ID | RMC - 640532001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 413256.45 | | 361263.92 | 87.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-17-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 110 |
| Addl Days Granted | 0 |
| Working Days Charged | 38 |
| Percent Time Used | 34 |
| Contractor(s) |
| P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12224205 |
| Totals | 413256.45 | 57222.95 | 361263.92 | 87.4 |
|
| County | TRAVIS |
| Highway | IH0035 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6405-34-001 |
| Proj ID | RMC - 640534001 |
| Work Type | INSTALLATION OF TRAFFIC SIGNALS |
| |
| 0.010 | 898125.00 | | 1299525.04 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 04-03-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 450 |
| Percent Time Used | 61 |
| Contractor(s) |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 02234204 |
| Totals | 898125.00 | 20146.11 | 1299525.04 | 99.9 |
|
| County | BURNET |
| Highway | US0281 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6405-36-001 |
| Proj ID | RMC - 640536001 |
| Work Type | METAL BEAM GUARD FENCE REPAIR |
| |
| 0.010 | 1515205.00 | | 1179276.86 | 77.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 04-10-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 571 |
| Percent Time Used | 78 |
| Contractor(s) |
| BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12224206 |
| Totals | 1515205.00 | 72522.30 | 1179276.86 | 77.8 |
|
| County | TRAVIS |
| Highway | IH0035 |
| From | VARIOUS LOCATIONS IN |
| To | TRAVIS AND WILLIAMSON COUNTY |
| CSJ | 6405-42-001 |
| Proj ID | RMC - 640542001 |
| Work Type | METAL BEAM GUARD FENCE REPAIR |
| |
| 0.010 | 3044832.00 | | 1926656.10 | 63.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 05-01-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 550 |
| Percent Time Used | 75 |
| Contractor(s) |
| BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-42-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 02234006 |
| Totals | 3044832.00 | 161381.10 | 1926656.10 | 63.2 |
|
| County | TRAVIS |
| Highway | IH0035 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6405-44-001 |
| Proj ID | RMC - 640544001 |
| Work Type | DEBRIS REMOVAL |
| |
| 0.010 | 937598.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 11-01-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 366 |
| Percent Time Used | 50 |
| Contractor(s) |
| T.F.R. ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08234207 |
| Totals | 937598.00 | 0.00 | 0.00 | 0.0 |
|
| County | TRAVIS |
| Highway | US0183 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6405-46-001 |
| Proj ID | RMC - 640546001 |
| Work Type | MAINTENANCE OF LARGE SIGNS |
| |
| 0.010 | 352302.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 31 |
| Percent Time Used | 4 |
| Contractor(s) |
| DIGG COMMERCIAL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 06244004 |
| Totals | 352302.00 | 0.00 | 0.00 | 0.0 |
|
| County | TRAVIS |
| Highway | FM0685 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6405-48-001 |
| Proj ID | RMC - 640548001 |
| Work Type | TRAFFIC SIGNAL MAINTENANCE |
| |
| 0.010 | 894172.00 | | 447934.20 | 50.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 07-06-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 478 |
| Percent Time Used | 65 |
| Contractor(s) |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 03234008 |
| Totals | 894172.00 | 16700.00 | 447934.20 | 50.0 |
|
| County | GILLESPIE |
| Highway | US0087 |
| From | VARIOUS LOCATIONS IN GILLESPIE, |
| To | BLANCO AND LLANO COUNTIES |
| CSJ | 6405-50-001 |
| Proj ID | RMC - 640550001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 428480.80 | | 341519.70 | 79.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-06-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 88 |
| Addl Days Granted | 0 |
| Working Days Charged | 35 |
| Percent Time Used | 39 |
| Contractor(s) |
| P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 03234009 |
| Totals | 428480.80 | 0.00 | 341519.70 | 79.7 |
|
| County | MASON |
| Highway | US0087 |
| From | VARIOUS LOCATIONS IN MASON, |
| To | LLANO AND GILLESPIE COUNTIES |
| CSJ | 6405-52-001 |
| Proj ID | RMC - 640552001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 499977.28 | | 374892.96 | 74.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-21-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 104 |
| Addl Days Granted | 0 |
| Working Days Charged | 35 |
| Percent Time Used | 33 |
| Contractor(s) |
| P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-52-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 03234209 |
| Totals | 499977.28 | 0.00 | 374892.96 | 74.9 |
|
| County | LLANO |
| Highway | SH0071 |
| From | VARIOUS LOCATIONS IN LLANO, BURNET |
| To | AND BLANCO COUNTIES |
| CSJ | 6405-54-001 |
| Proj ID | RMC - 640554001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 432033.68 | | 444127.26 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 07-03-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 128 |
| Addl Days Granted | 0 |
| Working Days Charged | 38 |
| Percent Time Used | 29 |
| Contractor(s) |
| R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 04234204 |
| Totals | 432033.68 | 0.00 | 444127.26 | 99.9 |
|
| County | LEE |
| Highway | US0290 |
| From | VARIOUS LOCATIONS IN |
| To | LEE COUNTY |
| CSJ | 6405-56-001 |
| Proj ID | RMC - 640556001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 696198.00 | | 554437.00 | 79.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-10-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 164 |
| Addl Days Granted | 0 |
| Working Days Charged | 33 |
| Percent Time Used | 20 |
| Contractor(s) |
| R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-56-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 03234208 |
| Totals | 696198.00 | 48769.00 | 554437.00 | 79.6 |
|
| County | CALDWELL |
| Highway | US0183 |
| From | VARIOUS LOCATIONS IN |
| To | CALDWELL COUNTY |
| CSJ | 6405-66-001 |
| Proj ID | RMC - 640566001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 544613.28 | | 370899.83 | 68.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 07-07-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 194 |
| Addl Days Granted | 0 |
| Working Days Charged | 84 |
| Percent Time Used | 43 |
| Contractor(s) |
| USA DT SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-66-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 04234205 |
| Totals | 544613.28 | 0.00 | 370899.83 | 68.1 |
|
| County | BASTROP |
| Highway | SH0071 |
| From | VARIOUS LOCATIONS IN |
| To | BASTROP COUNTY |
| CSJ | 6405-68-001 |
| Proj ID | RMC - 640568001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 439334.00 | | 130191.00 | 29.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 05-01-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 192 |
| Addl Days Granted | 0 |
| Working Days Charged | 62 |
| Percent Time Used | 32 |
| Contractor(s) |
| ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-68-001 TEAL ARROW LLC (0.00)
|
| Contract # | 02244002 |
| Totals | 439334.00 | 32598.00 | 130191.00 | 29.6 |
|
| County | BLANCO |
| Highway | US0281 |
| From | VARIOUS LOCATIONS IN BLANCO, BURNET, |
| To | GILLESPIE, HAYS, AND KENDALL COUNTIES |
| CSJ | 6405-92-001 |
| Proj ID | RMC - 640592001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 273559.28 | | 136632.78 | 49.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 11-16-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 100 |
| Addl Days Granted | 0 |
| Working Days Charged | 18 |
| Percent Time Used | 18 |
| Contractor(s) |
| P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08234008 |
| Totals | 273559.28 | 0.00 | 136632.78 | 49.9 |
|
| County | BURNET |
| Highway | US0281 |
| From | VARIOUS LOCATIONS IN BURNET |
| To | AND LLANO COUNTY |
| CSJ | 6405-94-001 |
| Proj ID | RMC - 640594001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 317464.00 | | 20638.00 | 6.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 08-01-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 92 |
| Addl Days Granted | 0 |
| Working Days Charged | 20 |
| Percent Time Used | 21 |
| Contractor(s) |
| ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-94-001 TEAL ARROW LLC (0.00)
|
| Contract # | 10234002 |
| Totals | 317464.00 | 0.00 | 20638.00 | 6.5 |
|
| County | TRAVIS |
| Highway | IH0035 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6406-00-001 |
| Proj ID | RMC - 640600001 |
| Work Type | ILLUMINATION MAINTENANCE |
| |
| 0.010 | 508337.00 | | 81776.40 | 16.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 03-06-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 234 |
| Percent Time Used | 32 |
| Contractor(s) |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6406-00-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234202 |
| Totals | 508337.00 | 9870.00 | 81776.40 | 16.0 |
|
| County | BURNET |
| Highway | US0281 |
| From | VARIOUS LOCATIONS IN BLANCO, BURNET |
| To | GILLESPIE, LLANO, AND MASON COUNTIES |
| CSJ | 6406-04-001 |
| Proj ID | RMC - 640604001 |
| Work Type | TREE TRIMMING AND BRUSH REMOVAL |
| |
| 0.010 | 446071.00 | | 288917.20 | 64.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 09-16-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 171 |
| Addl Days Granted | 0 |
| Working Days Charged | 34 |
| Percent Time Used | 19 |
| Contractor(s) |
| JCW CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-04-001 BEAVER BOYS SERVICES LLC (0.00)
|
| Contract # | 06244207 |
| Totals | 446071.00 | 172724.40 | 288917.20 | 64.7 |
|
| County | WILLIAMSON |
| Highway | US0079 |
| From | VARIOUS LOCATIONS IN WILLIAMSON |
| To | TRAVIS AND LEE COUNTIES |
| CSJ | 6406-10-001 |
| Proj ID | RMC - 640610001 |
| Work Type | TREE TRIMMING AND BRUSH REMOVAL |
| |
| 0.010 | 427320.00 | | 30000.00 | 7.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-15-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 92 |
| Addl Days Granted | 0 |
| Working Days Charged | 13 |
| Percent Time Used | 14 |
| Contractor(s) |
| ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-10-001 TEAL ARROW LLC (65.08)
|
| Contract # | 06244208 |
| Totals | 427320.00 | 30000.00 | 30000.00 | 7.0 |
|
| County | TRAVIS |
| Highway | IH0035 |
| From | VARIOUS LOCATIONS IN |
| To | THE AUSTIN DISTRICT |
| CSJ | 6408-71-001 |
| Proj ID | RMC - 640871001 |
| Work Type | PAVEMENT MARKINGS |
| |
| 0.010 | 2791397.50 | | 380379.50 | 13.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 03-25-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 220 |
| Percent Time Used | 30 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6408-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234005 |
| Totals | 2791397.50 | 103860.95 | 380379.50 | 13.6 |
|
| County | HAYS |
| Highway | FM2001 |
| From | VARIOUS LOCATIONS IN HAYS |
| To | TRAVIS, AND CALDWELL COUNTIES |
| CSJ | 6408-77-001 |
| Proj ID | RMC - 640877001 |
| Work Type | METAL BEAM GUARD FENCE REPAIR |
| |
| 0.010 | 2162563.00 | | 1822336.60 | 84.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-30-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 368 |
| Percent Time Used | 50 |
| Contractor(s) |
| BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6408-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08234209 |
| Totals | 2162563.00 | 259398.60 | 1822336.60 | 84.2 |
|