Monthly Local Let Maintenance Report For Beaumont District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayFM0770
FromVARIOUS
ToVARIOUS
CSJ6186-01-001
Proj IDEMC - 618601001
Work TypeDEBRIS REMOVAL - LIBERTY CO EAST
 
1.000265644.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-20-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082009
Totals265644.180.000.000.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6186-02-001
Proj IDEMC - 618602001
Work Typeemergency debris removal
 
1.000152111.829764.496.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-18-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged13
Percent Time Used61
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082010
Totals152111.820.009764.496.4

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6192-82-001
Proj IDRMC - 619282001
Work TypeMOWING OF RIGHT OF WAY- BEAUMONT MAINT
 
161.000170270.30166250.9097.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-09
Work Began06-08-09
Work Completed
Time Computed06-12-09
Contract Working Days200
Addl Days Granted0
Working Days Charged81
Percent Time Used40
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092005
Totals170270.300.00166250.9097.6

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6207-02-001
Proj IDSUP - 620702001
Work TypeGROUNDS MAINTENANCE - JASPER
 
1.0005127.962144.1241.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102011
Totals5127.960.002144.1241.8

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-13-001
Proj IDSUP - 620713001
Work TypeJANITORIAL MAINTENANCE - WOODVILLE
 
1.0004032.004032.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102008
Totals4032.000.004032.0099.9

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 190
CSJ6207-14-001
Proj IDSUP - 620714001
Work TypePICNIC MAINTENANCE - WOODVILLE
 
1.00013440.619773.4372.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days364
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102009
Totals13440.610.009773.4372.7

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-15-001
Proj IDSUP - 620715001
Work TypeGROUNDS MAINTENANCE - WOODVILLE
 
1.0002911.401674.3657.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102010
Totals2911.400.001674.3657.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-45-001
Proj IDSUP - 620945001
Work TypeJANITORIAL MAINTENANCE - ANAHUAC
 
1.0004071.304013.2898.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged254
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6209-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102018
Totals4071.300.004013.2898.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-46-001
Proj IDSUP - 620946001
Work TypeGROUNDS MAINTENANCE - ANAHUAC
 
1.0008123.006965.7985.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102015
Totals8123.000.006965.7985.7

CountyLIBERTY
HighwayUS0090
FromVARIOUS LOCATIONS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6232-67-001
Proj IDRMC - 623267001
Work TypeCLEAN AND RESHAPE DITCHES
 
1.000163024.0054792.5550.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-02-12
Work Began07-02-12
Work Completed
Time Computed04-02-12
Contract Working Days51
Addl Days Granted0
Working Days Charged352
Percent Time Used690
Contractor(s)
PARTNER MARIA SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6232-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122002
Totals163024.000.0054792.5550.4

CountyJEFFERSON
HighwayUS0069
FromUS 69 N
ToUS 69 N
CSJ6237-81-001
Proj IDSUP - 623781001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.0006779.286136.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-12
Work Began02-01-12
Work Completed02-10-13
Time Computed02-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY
SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12112007
Totals6779.280.006136.20100.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6246-49-001
Proj IDSUP - 624649001
Work TypeLIBERTY ~ LITTER
 
1.000239756.04236236.2098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08122006
Totals239756.040.00236236.2098.5

CountyJASPER
HighwayUS0190
FromJASPER MAINTENANCE YARD
ToJASPER MAINTENANCE YARD
CSJ6375-35-001
Proj IDMMC - 637535001
Work TypeAGGREGATE
 
0.0104999.007885.42100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-19-21
Work Completed12-11-21
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged44
Percent Time Used36
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6375-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212003
Totals4999.000.007885.42100.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICT WAREHOUSE
ToDISTRICT WAREHOUSE
CSJ6376-08-001
Proj IDMMC - 637608001
Work TypeDE-ICING SALT
 
0.0109900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON A CRUZ
SUBCONTRACTOR(S) FOR CCSJ: 6376-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02212011
Totals9900.000.000.000.0

CountyTYLER
HighwayUS0287
FromWOODVILLE MAINTENANCE YARD
ToWOODVILLE MAINTENANCE YARD
CSJ6377-42-001
Proj IDMMC - 637742001
Work TypeHOT-MIX COLD-LAID
 
0.01066241.0066265.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-19-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged172
Percent Time Used71
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04222001
Totals66241.000.0066265.6099.9

CountyJEFFERSON
HighwaySH0347
FromSH 347 @ FM 366 NEDERLAND, TX
ToSH 321 IN DAYTON, TX
CSJ6378-93-001
Proj IDRMC - 637893001
Work TypePUMP STATION MAINTENANCE AND REPAIRS
 
0.010107105.0039150.0036.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
AIMS COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 6378-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11212002
Totals107105.000.0039150.0036.5

CountyJASPER
HighwayUS0096
FromJASPER AREA
ToVARIOUS
CSJ6379-51-001
Proj IDRMC - 637951001
Work TypeCULVERT REPAIR
 
0.010390515.00389922.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-18-22
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted10
Working Days Charged74
Percent Time Used134
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08212004
Totals390515.000.00389922.6699.9

CountyCHAMBERS
HighwaySH0124
FromWINNIE STOCKPILE
ToWINNIE STOCKPILE
CSJ6388-55-001
Proj IDMMC - 638855001
Work TypeROCK/RIPRAP
 
0.01050000.00207082.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-14-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged291
Percent Time Used80
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02222004
Totals50000.000.00207082.3899.9

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6391-42-001
Proj IDBPM - 639142001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010265009.00202967.9576.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-02-22
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6391-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02222003
Totals265009.000.00202967.9576.5

CountyLIBERTY
HighwayFM2025
From0.05 MI N OF US 59
To0.05 MI S OF US 59
CSJ6391-52-001
Proj IDRMC - 639152001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.010220345.09258139.45100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-12-22
Work Completed09-13-22
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged33
Percent Time Used100
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6391-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12212001
Totals220345.09306600.00258139.45100.0

page 1 | page 2 | page 3 | page 4