Monthly Local Let Maintenance Report For Beaumont District As Of Nov 10, 2024 Page 4 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayUS0059
FromSAN JACINTO COUNTY
ToMONTGOMERY COUNTY LINE
CSJ6468-84-001
Proj IDSUP - 646884001
Work TypeDEBRIS REMOVAL
 
0.01095638.4015633.2016.3
Work Order06-11-24
Work Began06-17-24
Work Completed
Time Computed06-11-24
Contract Working Days730
Addl Days Granted0
Working Days Charged137
Percent Time Used18
Contractor(s)
WORKQUEST
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6468-84-001
SDR & ASSOC. INC. (100.00)
Contract #05242033
Totals95638.404598.0015633.2016.3

CountyNEWTON
HighwaySH0012
FromSH12
ToSH12
CSJ6470-50-001
Proj IDSUP - 647050001
Work TypeLANDSCAPE MAINTENANCE
 
0.01020300.885332.3626.2
Work Order07-24-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-50-001
RUCON, INC. (100.00)
Contract #07242032
Totals20300.881718.805332.3626.2

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6471-50-001
Proj IDMMC - 647150001
Work TypeHYDRAULIC CEMENT
 
0.01084000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6471-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08242050
Totals84000.000.000.000.0

CountyHARDIN
HighwayUS0069
FromUS69
ToUS69
CSJ6471-61-001
Proj IDSUP - 647161001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01016508.004952.4030.0
Work Order07-24-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-61-001
RUCON, INC. (100.00)
Contract #07242033
Totals16508.001650.804952.4030.0

CountyORANGE
HighwaySH0012
FromSH12
ToSH12
CSJ6471-62-001
Proj IDSUP - 647162001
Work TypeLITTER REMOVAL
 
0.01010543.522635.8825.0
Work Order07-24-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-62-001
RUCON, INC. (100.00)
Contract #07242034
Totals10543.521013.802635.8825.0

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6471-63-001
Proj IDSUP - 647163001
Work TypeJANITORIAL MAINTENANCE
 
0.01092936.7320409.0621.9
Work Order07-25-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-63-001
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC. (99.99)
Contract #07242035
Totals92936.736803.0220409.0621.9

CountyNEWTON
HighwayUS0190
FromUS190
ToUS190
CSJ6471-64-001
Proj IDSUP - 647164001
Work TypeLITTER REMOVAL
 
0.01097638.0939693.4540.6
Work Order07-25-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-64-001
RUCON, INC. (99.99)
Contract #07242038
Totals97638.0925029.7139693.4540.6

CountyLIBERTY
HighwayUS0090
FromUS90
ToUS90
CSJ6471-65-001
Proj IDSUP - 647165001
Work TypeJANITORIAL MAINTENANCE
 
0.01027171.486792.8725.0
Work Order07-24-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-65-001
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC. (100.00)
Contract #07242037
Totals27171.482264.296792.8725.0

CountyORANGE
HighwaySH0062
FromSH62
ToSH62
CSJ6471-66-001
Proj IDSUP - 647166001
Work TypeLITTER REMOVAL
 
0.010171462.2740940.3323.8
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6471-66-001
SAUMYA, INC (100.00)
Contract #07242036
Totals171462.2715047.2140940.3323.8

CountyLIBERTY
HighwayFM0787
FromAT STRUCTURE
ToTRINITY RIVER BRIDGE
CSJ6472-02-001
Proj IDEMC - 647202001
Work TypeEMERGENCY BRIDGE REPAIR
 
0.01011985429.906930888.7057.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-16-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged46
Percent Time Used25
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6472-02-001
HUNTER DEMOLITION & WRECKING CORPORATION (2.01)
K4 ENVIRONMENTAL LLC (0.00)
HEMPHILL WBE PILE DRIVING CO. (0.00)
STRIPES & STOPS COMPANY, INC. (0.00)
DUSTROL, INC. (0.00)
MAXON DRILLING LLC (4.83)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.00)
Contract #08242040
Totals11985429.90245150.006930888.7057.8

CountyORANGE
HighwaySH0062
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6472-34-001
Proj IDMMC - 647234001
Work TypeFLOWABLE FILL
 
0.01049720.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-26-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged36
Percent Time Used9
Contractor(s)
SOUTHERN SOURCING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08242051
Totals49720.000.000.000.0

CountyJEFFERSON
HighwaySH0073
FromSH 73
ToSH 73
CSJ6473-37-001
Proj IDSUP - 647337001
Work TypeGROUNDS MAINTENANCE
 
0.01029565.125141.7617.3
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-37-001
RUCON, INC. (100.00)
Contract #08242031
Totals29565.122570.885141.7617.3

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6473-38-001
Proj IDSUP - 647338001
Work TypeLITTER REMOVAL
 
0.01080937.720.000.0
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-38-001
RUCON, INC. (99.99)
Contract #08242032
Totals80937.720.000.000.0

CountyTYLER
HighwayUS0069
FromUS69
ToUS69
CSJ6473-44-001
Proj IDSUP - 647344001
Work TypeLITTER REMOVAL
 
0.01094918.940.000.0
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-44-001
RUCON, INC. (100.00)
Contract #08242035
Totals94918.940.000.000.0

CountyHARDIN
HighwayUS0069
FromUS69
ToUS69
CSJ6473-45-001
Proj IDSUP - 647345001
Work TypeLITTER REMOVAL
 
0.010100941.4820779.4520.5
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-45-001
RUCON, INC. (100.00)
Contract #08242037
Totals100941.4810993.0320779.4520.5

CountyLIBERTY
HighwayUS0090
FromUS90
ToUS90
CSJ6473-46-001
Proj IDSUP - 647346001
Work TypeLITTER REMOVAL
 
0.010219151.1391247.8941.6
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-46-001
RUCON, INC. (93.99)
Contract #08242034
Totals219151.1324336.3791247.8941.6

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6473-47-001
Proj IDSUP - 647347001
Work TypeLITTER REMOVAL
 
0.010149194.5360734.1640.7
Work Order08-28-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-47-001
RUCON, INC. (100.00)
Contract #08242036
Totals149194.5337850.0660734.1640.7

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6473-48-001
Proj IDSUP - 647348001
Work TypeLITTER REMOVAL
 
0.010189252.5940388.4821.3
Work Order08-27-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-48-001
RUCON, INC. (100.00)
Contract #08242033
Totals189252.5924914.2740388.4821.3

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6473-59-001
Proj IDMMC - 647359001
Work TypeFLEXIBLE BASE
 
0.010704930.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-15-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged17
Percent Time Used4
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09242050
Totals704930.000.000.000.0

CountyJEFFERSON
HighwaySH0347
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6473-91-001
Proj IDMMC - 647391001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010595171.0067349.3411.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-22-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged16
Percent Time Used4
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09242051
Totals595171.0067349.3467349.3411.3

page 1 | page 2 | page 3 | page 4 | page 5