Monthly State Let Maintenance Report For Beaumont District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayIH0010
FromORANGE COUNTY LINE
ToHARRIS COUNTY LINE
CSJ6164-51-001
Proj IDRMC - 616451001
Work TypeSWEEPING MAIN ROUTE HIGHWAYS
 
0.1001801022.091859518.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-27-08
Work Began06-03-08
Work Completed
Time Computed06-03-08
Contract Working Days480
Addl Days Granted60
Working Days Charged535
Percent Time Used99
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6164-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03084014
Totals1801022.090.001859518.6499.9

CountyJEFFERSON
HighwayIH0010
FromBRAKES BAYOU
ToBRIDGE
CSJ6221-53-001
Proj IDABT - 622153001
Work TypeHAZ-MAT
 
0.06669000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05124021
Totals69000.000.000.000.0

CountyJEFFERSON
HighwayIH0010
FromVARIOUS HIGHWAYS IN DISTRICT 20
ToVARIOUS HIGHWAYS IN DISTRICT 20
CSJ6253-63-001
Proj IDRMC - 625363001
Work TypeCALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.0011600000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134017
Totals1600000.000.000.000.0

CountyCHAMBERS
HighwayFM2936
FromFM 2936, FM 2939, FM 1738, FM 1007,
ToFM 1408, FM 2800, FM 686
CSJ6274-34-001
Proj IDRMC - 627434001
Work TypeDISTRICTWIDE SEAL COAT
 
31.317951388.94995575.03100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-18-15
Work Completed07-28-15
Time Computed05-18-15
Contract Working Days29
Addl Days Granted0
Working Days Charged29
Percent Time Used100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-34-001
INTERSTATE BARRICADES & MARKINGS, INC. (12.61)
Contract #01154015
Totals951388.940.00995575.03100.0

CountyJEFFERSON
HighwayIH0010
FromVARIOUS HIGHWAYS IN DISTRICT 20
ToVARIOUS HIGHWAYS IN DISTRICT 20
CSJ6316-25-001
Proj IDRMC - 631625001
Work TypeCALLOUT DEBRIS REMOVAL AND DISPOSAL
 
0.0011358501.003522330.9899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-17
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted173
Working Days Charged209
Percent Time Used96
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174015
Totals1358501.000.003522330.9899.9

CountyLIBERTY
HighwayFM0787
FromAT TRINITY RIVER BRIDGE
To0.5 MILE EAST OF TRINITY RIVER BRIDGE
CSJ6344-05-001
Proj IDRMC - 634405001
Work TypeSTABILIZE BANK OF TRINITY RIVER
 
0.39015552095.9419201053.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-10-20
Work Completed
Time Computed00-00-00
Contract Working Days138
Addl Days Granted123
Working Days Charged255
Percent Time Used97
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6344-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204212
Totals15552095.940.0019201053.4599.9

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6347-56-001
Proj IDRMC - 634756001
Work TypeCHEVRON SIGN INSTALLATION
 
0.010822241.00744707.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-18-20
Work Completed06-03-20
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged50
Percent Time Used60
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6347-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11194202
Totals822241.00343775.80744707.75100.0

CountyNEWTON
HighwayFM2460
FromSH 87
ToFM 1416
CSJ6348-60-001
Proj IDRMC - 634860001
Work TypeOVERLAY
 
2.500878620.85828125.1794.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged28
Percent Time Used93
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6348-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204215
Totals878620.850.00828125.1794.2

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6349-17-001
Proj IDRMC - 634917001
Work TypeSIGN INSTALLATION AND MAINTENANCE
 
0.100375050.00522100.6799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-13-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted203
Working Days Charged568
Percent Time Used100
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6349-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204206
Totals375050.003000.00522100.6799.9

CountyORANGE
HighwayFM1130
FromFM1136
ToEAST OF ZAVALLA RD
CSJ6360-24-001
Proj IDRMC - 636024001
Work TypeOVERLAY ROADWAY
 
4.233681341.651062014.3899.9
Work Order00-00-00
Work Began09-14-20
Work Completed
Time Computed09-14-20
Contract Working Days28
Addl Days Granted13
Working Days Charged34
Percent Time Used82
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6360-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204203
Totals681341.6510672.501062014.3899.9

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6368-53-001
Proj IDRMC - 636853001
Work TypeSIGNAL/ILLUMINATION INSTALL/MAINTENANCE
 
0.0011369287.002516724.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted280
Working Days Charged636
Percent Time Used98
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6368-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204212
Totals1369287.0058994.592516724.1899.9

CountyCHAMBERS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6371-75-001
Proj IDRMC - 637175001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
796813.05883629.6599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-14-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged237
Percent Time Used32
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214005
Totals796813.050.00883629.6599.9

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6371-76-001
Proj IDRMC - 637176001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
318686.36252610.3279.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6371-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214003
Totals318686.360.00252610.3279.2

CountyJASPER
HighwayUS0096
FromVARIOUS
ToVARIOUS
CSJ6371-77-001
Proj IDRMC - 637177001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
674971.12649183.9296.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged518
Percent Time Used70
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6371-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214004
Totals674971.120.00649183.9296.1

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6371-78-001
Proj IDRMC - 637178001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
613231.50634539.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-17-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged149
Percent Time Used20
Contractor(s)
ANGEL LADY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6371-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214006
Totals613231.500.00634539.5899.9

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6371-79-001
Proj IDRMC - 637179001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
330820.84319421.8896.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged579
Percent Time Used79
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6371-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214007
Totals330820.840.00319421.8896.5

CountyORANGE
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6371-80-001
Proj IDRMC - 637180001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
512174.80508760.4099.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-03-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged579
Percent Time Used79
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6371-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214205
Totals512174.800.00508760.4099.3

CountyJEFFERSON
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6371-81-001
Proj IDRMC - 637181001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
469216.00388075.0082.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
CLASSIC IRRIGATION & LANDSCAPE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6371-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214206
Totals469216.000.00388075.0082.7

CountyHARDIN
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6371-82-001
Proj IDRMC - 637182001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
503714.28503614.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6371-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214207
Totals503714.280.00503614.2899.9

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6371-83-001
Proj IDRMC - 637183001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
366712.00366612.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged404
Percent Time Used55
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6371-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214208
Totals366712.000.00366612.0099.9

page 1 | page 2 | page 3 | page 4