Monthly State Let Maintenance Report For Beaumont District As Of Nov 10, 2024 Page 1 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayIH0010
FromORANGE COUNTY LINE
ToHARRIS COUNTY LINE
CSJ6164-51-001
Proj IDRMC - 616451001
Work TypeSWEEPING MAIN ROUTE HIGHWAYS
 
0.1001801022.091859518.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-27-08
Work Began06-03-08
Work Completed
Time Computed06-03-08
Contract Working Days480
Addl Days Granted60
Working Days Charged535
Percent Time Used99
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6164-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03084014
Totals1801022.090.001859518.6499.9

CountyJEFFERSON
HighwayIH0010
FromBRAKES BAYOU
ToBRIDGE
CSJ6221-53-001
Proj IDABT - 622153001
Work TypeHAZ-MAT
 
0.06669000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05124021
Totals69000.000.000.000.0

CountyJEFFERSON
HighwayIH0010
FromVARIOUS HIGHWAYS IN DISTRICT 20
ToVARIOUS HIGHWAYS IN DISTRICT 20
CSJ6253-63-001
Proj IDRMC - 625363001
Work TypeCALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.0011600000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134017
Totals1600000.000.000.000.0

CountyCHAMBERS
HighwayFM2936
FromFM 2936, FM 2939, FM 1738, FM 1007,
ToFM 1408, FM 2800, FM 686
CSJ6274-34-001
Proj IDRMC - 627434001
Work TypeDISTRICTWIDE SEAL COAT
 
31.317951388.94995575.03100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-18-15
Work Completed07-28-15
Time Computed05-18-15
Contract Working Days29
Addl Days Granted0
Working Days Charged29
Percent Time Used100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-34-001
INTERSTATE BARRICADES & MARKINGS, INC. (12.61)
Contract #01154015
Totals951388.940.00995575.03100.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6349-17-001
Proj IDRMC - 634917001
Work TypeSIGN INSTALLATION AND MAINTENANCE
 
0.100375050.00522100.6799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-13-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted203
Working Days Charged568
Percent Time Used100
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6349-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204206
Totals375050.003000.00522100.6799.9

CountyORANGE
HighwaySH0073
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6392-15-001
Proj IDRMC - 639215001
Work TypeEROSION REPAIR
 
0.010492945.00435107.0488.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-03-23
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged42
Percent Time Used85
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234009
Totals492945.00184242.50435107.0488.2

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS AND LIBERTY COUNTIES
ToCHAMBERS AND LIBERTY COUNTIES
CSJ6395-00-001
Proj IDRMC - 639500001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010439056.00269642.5061.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-18-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234214
Totals439056.000.00269642.5061.4

CountyJASPER
HighwayUS0096
FromVARIOUS
ToVARIOUS
CSJ6396-81-001
Proj IDRMC - 639681001
Work TypeBRIDGE REPAIR
 
0.0101727474.001368975.0079.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days118
Addl Days Granted0
Working Days Charged121
Percent Time Used102
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234004
Totals1727474.00253469.001368975.0079.3

CountyLIBERTY
HighwayFM0563
FromFM 770
To2.2 MI SOUTH
CSJ6397-27-001
Proj IDRMC - 639727001
Work TypeBASE REPAIR WITH SEAL COAT AND/OR OVERL
 
0.010933873.91701447.3975.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-30-24
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged22
Percent Time Used73
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6397-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244005
Totals933873.91701447.39701447.3975.1

CountyLIBERTY
HighwaySH0099
FromLIBERTY CL TO CHAMBERS CL
ToSH99
CSJ6399-15-001
Proj IDRMC - 639915001
Work TypeBUNDLED BID
 
0.0104274495.768073196.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-07-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged725
Percent Time Used99
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224017
Totals4274495.761268656.018073196.3199.9

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6402-17-001
Proj IDRMC - 640217001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101126764.00828342.48100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-27-22
Work Completed10-17-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6402-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224410
Totals1126764.000.00828342.48100.0

CountyORANGE
HighwayFM1135
FromSFR IH 10
ToFM 105
CSJ6403-74-001
Proj IDRMC - 640374001
Work TypeACP OVERLAY
 
0.0101387550.101429335.7299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-07-22
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged140
Percent Time Used77
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6403-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224214
Totals1387550.100.001429335.7299.9

CountyJASPER
HighwayUS0096
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6404-80-001
Proj IDRMC - 640480001
Work TypeDITCH CLEANING AND RESHAPING
 
0.0101886796.15812951.28100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-30-22
Work Completed10-01-24
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6404-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224216
Totals1886796.150.00812951.28100.0

CountyJEFFERSON
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6410-35-001
Proj IDRMC - 641035001
Work TypeCULVERT CLEANING
 
0.010392190.00240800.0061.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-12-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6410-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224233
Totals392190.0045500.00240800.0061.3

CountyCHAMBERS
HighwayFM3246
FromIH 10
ToFM 565
CSJ6413-57-001
Proj IDRMC - 641357001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
0.0101218368.601410873.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-02-23
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted12
Working Days Charged35
Percent Time Used61
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-57-001
H J HENKE, LLC (1.25)
BADGER DAYLIGHTING CORP. (0.32)
Contract #06234406
Totals1218368.600.001410873.0499.9

CountyLIBERTY
HighwayBS105T
FromVARIOUS
ToVARIOUS
CSJ6414-53-001
Proj IDRMC - 641453001
Work TypeMILL AND INLAY
 
0.0103176353.602881325.4291.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged64
Percent Time Used145
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6414-53-001
HOUSTON VACUUM TRUCK, LLC (0.15)
STRIPE LINES, INC. (3.44)
CEN TEX HYDROSEED, INC. (0.42)
WILLOW CITY SIGN & RAIL, INC. (0.00)
PROFESSIONAL TRAFFIC CONTROL LLC (0.22)
KINGZ INDUSTRIAL LLC (0.77)
Contract #06234602
Totals3176353.600.002881325.4291.3

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6417-85-001
Proj IDRMC - 641785001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101848245.00965094.3752.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-23
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged54
Percent Time Used75
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6417-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234204
Totals1848245.000.00965094.3752.2

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6418-57-001
Proj IDRMC - 641857001
Work TypePAVEMENT MARKINGS
 
0.010989383.003426787.80100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-15-22
Work Completed10-17-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6418-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10224002
Totals989383.000.003426787.80100.0

CountyCHAMBERS
HighwayFM1724
FromIH 10 N. JUG HANDLE
ToFM 1663
CSJ6420-79-001
Proj IDRMC - 642079001
Work TypeASPHALT PAVEMENT WIDENING
 
0.0101219731.951285581.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-02-23
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted1
Working Days Charged27
Percent Time Used44
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6420-79-001
AMERICAN REMEDIATION OPTIONS, INC. (6.25)
PROFESSIONAL TRAFFIC CONTROL LLC (0.49)
Contract #06234603
Totals1219731.950.001285581.1199.9

CountyCHAMBERS
HighwayFM1942
FromHARRIS COUNTY LINE
ToHATCHERVILLE RD, EAST
CSJ6421-53-001
Proj IDRMC - 642153001
Work TypeBASE REPAIR WITH SEAL COAT AND/OR OVERL
 
0.0101523652.251452455.1595.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged54
Percent Time Used120
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6421-53-001
J & M CONTRACTING, COMPANY (7.87)
HIGHWAY 1 LLC (0.42)
ODUM SERVICES, LLC (2.98)
PROFESSIONAL TRAFFIC CONTROL LLC (0.46)
BATTERSON, LLP (3.12)
CEN TEX HYDROSEED, INC. (0.41)
Contract #06234201
Totals1523652.250.001452455.1595.8