|
| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | JEFFERSON |
| Highway | IH0010 |
| From | VARIOUS |
| To | VARIOUS |
| CSJ | 6443-40-001 |
| Proj ID | RMC - 644340001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 1250570.24 | | 503531.20 | 40.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 11-01-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 726 |
| Addl Days Granted | 0 |
| Working Days Charged | 366 |
| Percent Time Used | 50 |
| Contractor(s) |
| WAYNE YANCEY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6443-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08234012 |
| Totals | 1250570.24 | 22093.28 | 503531.20 | 40.2 |
|
| County | JEFFERSON |
| Highway | IH0010 |
| From | VARIOUS LOCATIONS IN |
| To | JEFFERSON AND HARDIN COUNTIES |
| CSJ | 6445-82-001 |
| Proj ID | BPM - 644582001 |
| Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
| |
| 0.010 | 759064.50 | | 2833472.88 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 01-08-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 65 |
| Addl Days Granted | 90 |
| Working Days Charged | 110 |
| Percent Time Used | 70 |
| Contractor(s) |
| AAD CONTRACTING INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6445-82-001 SJ&J CONSTRUCTION, LLC (38.78) THE TRUESDELL CORPORATION (20.44) L & M MOWING CONTRACTORS, LLC (2.89) 1 PRIORITY ENVIRONMENTAL SERVICES, LLC (2.89) HIGHWAY 1 LLC (2.13) ORION CONSTRUCTION, LLC (159.10)
|
| Contract # | 10234205 |
| Totals | 759064.50 | 72850.77 | 2833472.88 | 99.9 |
|
| County | TYLER |
| Highway | FM0256 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6448-69-001 |
| Proj ID | MMC - 644869001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 511077.00 | | 1079602.01 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 09-19-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 365 |
| Percent Time Used | 100 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6448-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08234013 |
| Totals | 511077.00 | 185809.84 | 1079602.01 | 99.9 |
|
| County | CHAMBERS |
| Highway | IH0010 |
| From | VARIOUS |
| To | VARIOUS |
| CSJ | 6449-59-001 |
| Proj ID | BPM - 644959001 |
| Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
| |
| 0.010 | 381541.00 | | 550102.55 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 12-16-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 38 |
| Addl Days Granted | 0 |
| Working Days Charged | 33 |
| Percent Time Used | 86 |
| Contractor(s) |
| STRUCTURAL INTEGRITY GROUP LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6449-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 11234206 |
| Totals | 381541.00 | 221477.75 | 550102.55 | 99.9 |
|
| County | JEFFERSON |
| Highway | US0069 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6450-75-001 |
| Proj ID | MMC - 645075001 |
| Work Type | HOT MIX |
| |
| 0.010 | 3421275.00 | | 3000113.47 | 87.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 11-01-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 60 |
| Working Days Charged | 366 |
| Percent Time Used | 86 |
| Contractor(s) |
| TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-75-001 RAILPROS FIELD SERVICES, INC. (0.09)
|
| Contract # | 09234007 |
| Totals | 3421275.00 | 1394580.79 | 3000113.47 | 87.6 |
|
| County | ORANGE |
| Highway | FM0105 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6450-81-001 |
| Proj ID | MMC - 645081001 |
| Work Type | HOT MIX |
| |
| 0.010 | 3211500.00 | | 1144240.90 | 35.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 11-01-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 60 |
| Working Days Charged | 366 |
| Percent Time Used | 86 |
| Contractor(s) |
| TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-81-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09234008 |
| Totals | 3211500.00 | 3199.30 | 1144240.90 | 35.6 |
|
| County | CHAMBERS |
| Highway | FM0565 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6451-49-001 |
| Proj ID | MMC - 645149001 |
| Work Type | HOT MIX |
| |
| 0.010 | 747500.00 | | 646049.48 | 86.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-30-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 308 |
| Percent Time Used | 84 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6451-49-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09234006 |
| Totals | 747500.00 | 298577.66 | 646049.48 | 86.4 |
|
| County | CHAMBERS |
| Highway | IH0010 |
| From | VARIOUS |
| To | VARIOUS |
| CSJ | 6452-75-001 |
| Proj ID | RMC - 645275001 |
| Work Type | METAL BEAM GUARD FENCE REPAIR |
| |
| 0.010 | 554027.00 | | 337919.00 | 60.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 03-20-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 185 |
| Percent Time Used | 50 |
| Contractor(s) |
| HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6452-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 02244011 |
| Totals | 554027.00 | 74070.00 | 337919.00 | 60.9 |
|
| County | NEWTON |
| Highway | FM1415 |
| From | BEAUMONT AREA DISTRICT |
| To | BEAUMONT AREA DISTRICT |
| CSJ | 6453-13-001 |
| Proj ID | MMC - 645313001 |
| Work Type | EMULSION |
| |
| 0.010 | 696110.00 | | 1280144.73 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-30-23 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 365 |
| Working Days Charged | 368 |
| Percent Time Used | 50 |
| Contractor(s) |
| CLEVELAND ASPHALT PRODUCTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09234204 |
| Totals | 696110.00 | 338120.16 | 1280144.73 | 99.9 |
|
| County | ORANGE |
| Highway | SH0012 |
| From | STA. 392+67 - 664' WEST OF FM 1136 |
| To | STA. 483+61 - 170' WEST OF SH 62 |
| CSJ | 6454-21-001 |
| Proj ID | RMC - 645421001 |
| Work Type | ASPHALT |
| |
| 0.010 | 2156544.92 | | 827840.98 | 38.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-01-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 44 |
| Addl Days Granted | 0 |
| Working Days Charged | 32 |
| Percent Time Used | 72 |
| Contractor(s) |
| TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6454-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 04244006 |
| Totals | 2156544.92 | 562009.81 | 827840.98 | 38.3 |
|
| County | JEFFERSON |
| Highway | US0069 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6455-60-001 |
| Proj ID | RMC - 645560001 |
| Work Type | PAVEMENT MARKINGS |
| |
| 0.010 | 557638.75 | | 1733932.85 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 02-23-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 252 |
| Percent Time Used | 69 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6455-60-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234006 |
| Totals | 557638.75 | 327650.60 | 1733932.85 | 99.9 |
|
| County | JEFFERSON |
| Highway | US0069 |
| From | JEFFERSON/ORANGE/HARDIN COUNTIES |
| To | JEFFERSON/ORANGE/HARDIN COUNTIES |
| CSJ | 6456-75-001 |
| Proj ID | RMC - 645675001 |
| Work Type | TREE TRIMMING AND BRUSH REMOVAL |
| |
| 0.010 | 485825.00 | | 274056.42 | 56.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 01-23-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 283 |
| Percent Time Used | 77 |
| Contractor(s) |
| ACE CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234007 |
| Totals | 485825.00 | 50006.42 | 274056.42 | 56.4 |
|
| County | LIBERTY |
| Highway | US0090 |
| From | LIBERTY COUNTY |
| To | CHAMBERS COUNTY |
| CSJ | 6456-77-001 |
| Proj ID | RMC - 645677001 |
| Work Type | TREE TRIMMING AND BRUSH REMOVAL |
| |
| 0.010 | 293800.00 | | 86730.00 | 29.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 01-29-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 277 |
| Percent Time Used | 75 |
| Contractor(s) |
| MARLANE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234008 |
| Totals | 293800.00 | 0.00 | 86730.00 | 29.5 |
|
| County | JASPER |
| Highway | US0096 |
| From | JASPER/NEWTON/ORANGE COUNTIES |
| To | JASPER/NEWTON/ORANGE COUNTIES |
| CSJ | 6456-79-001 |
| Proj ID | RMC - 645679001 |
| Work Type | TREE TRIMMING AND BRUSH REMOVAL |
| |
| 0.010 | 349702.00 | | 4760.00 | 1.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 01-24-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 274 |
| Percent Time Used | 75 |
| Contractor(s) |
| ACE CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-79-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234009 |
| Totals | 349702.00 | 4760.00 | 4760.00 | 1.3 |
|
| County | JEFFERSON |
| Highway | US0069 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6458-36-001 |
| Proj ID | RMC - 645836001 |
| Work Type | ILLUMINATION MAINTENANCE |
| |
| 0.010 | 760697.90 | | 404333.64 | 53.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 01-30-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 276 |
| Percent Time Used | 75 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6458-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12234010 |
| Totals | 760697.90 | 93.00 | 404333.64 | 53.1 |
|
| County | JEFFERSON |
| Highway | US0069 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6458-93-001 |
| Proj ID | RMC - 645893001 |
| Work Type | LARGE SIGN REPLACEMENT |
| |
| 0.010 | 675755.00 | | 677990.46 | 99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 06-01-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 153 |
| Percent Time Used | 41 |
| Contractor(s) |
| 3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 01244005 |
| Totals | 675755.00 | 153112.15 | 677990.46 | 99.9 |
|
| County | JEFFERSON |
| Highway | SH0347 |
| From | SH 347 AT FM 366 |
| To | SH 321, DAYTON |
| CSJ | 6460-85-001 |
| Proj ID | RMC - 646085001 |
| Work Type | PUMP STATION & DRAINAGE SYSTEM CLEANING |
| |
| 0.010 | 129046.00 | | 9200.00 | 7.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 04-08-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 207 |
| Percent Time Used | 56 |
| Contractor(s) |
| AIMS COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 6460-85-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 02244025 |
| Totals | 129046.00 | 3850.00 | 9200.00 | 7.1 |
|
| County | JASPER |
| Highway | US0096 |
| From | US 96 |
| To | VARIOUS LOCATIONS |
| CSJ | 6461-76-001 |
| Proj ID | RMC - 646176001 |
| Work Type | METAL BEAM GUARD FENCE REPAIR |
| |
| 0.010 | 858387.03 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 08-29-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6461-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 07244005 |
| Totals | 858387.03 | 0.00 | 0.00 | 0.0 |
|
| County | JASPER |
| Highway | US0096 |
| From | DISTRICTWIDE |
| To | DISTRICTWIDE |
| CSJ | 6462-09-001 |
| Proj ID | RMC - 646209001 |
| Work Type | DITCH CLEANING AND RESHAPING |
| |
| 0.010 | 2350250.45 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| TEXAS DRAINAGE INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6462-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09244001 |
| Totals | 2350250.45 | 0.00 | 0.00 | 0.0 |
|
| County | JEFFERSON |
| Highway | IH0010 |
| From | VARIOUS |
| To | VARIOUS |
| CSJ | 6463-09-001 |
| Proj ID | RMC - 646309001 |
| Work Type | CULVERT CLEANING |
| |
| 0.010 | 397690.00 | | 235710.00 | 59.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 10-01-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 31 |
| Percent Time Used | 8 |
| Contractor(s) |
| HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 07244006 |
| Totals | 397690.00 | 235710.00 | 235710.00 | 59.2 |
|