|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BRAZOS |
Highway | US0190 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6346-24-001 |
Proj ID | RMC - 634624001 |
Work Type | INSTALLATION OF DRIVEWAY PIPE |
|
| 0.001 | 715533.00 | | 2396480.71 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-04-19 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 731 |
Working Days Charged | 1,215 |
Percent Time Used | 83 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6346-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07194205 |
| Totals | 715533.00 | 159159.22 | 2396480.71 | 99.9 |
|
County | WALKER |
Highway | SH0075 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6348-24-001 |
Proj ID | RMC - 634824001 |
Work Type | FLAGGING AND TRAFFIC CONTROL |
|
| 0.001 | 2322131.10 | | 3706624.20 | 99.9 |
Work Order | 06-23-20 |
Work Began | 07-01-20 |
Work Completed | |
Time Computed | 07-01-20 |
Contract Working Days | 731 |
Addl Days Granted | 731 |
Working Days Charged | 914 |
Percent Time Used | 62 |
Contractor(s) |
AREA WIDE PROTECTIVE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6348-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03204002 |
| Totals | 2322131.10 | 135972.82 | 3706624.20 | 99.9 |
|
County | FREESTONE |
Highway | US0084 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6364-18-001 |
Proj ID | RMC - 636418001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.001 | 730335.00 | | 301064.83 | 100.0 |
Work Order | 12-08-20 |
Work Began | 12-08-20 |
Work Completed | 12-08-22 |
Time Computed | 12-08-20 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 723 |
Percent Time Used | 99 |
Contractor(s) |
VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6364-18-001 JUNIOR CONSTRUCTION COMPANY, INC. (0.00)
|
Contract # | 09204205 |
| Totals | 730335.00 | 2663.90 | 301064.83 | 100.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6367-62-001 |
Proj ID | RMC - 636762001 |
Work Type | REMOVE/INSTALL LARGE GUIDE SIGNS |
|
| 0.001 | 677125.00 | | 541436.40 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-05-21 |
Work Completed | 12-16-22 |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 469 |
Percent Time Used | 128 |
Contractor(s) |
BATTERSON, LLP |
SUBCONTRACTOR(S) FOR CCSJ: 6367-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09204204 |
| Totals | 677125.00 | 0.00 | 541436.40 | 100.0 |
|
County | GRIMES |
Highway | BS0006S |
From | VARIOUS |
To | VARIOUS |
CSJ | 6375-83-001 |
Proj ID | RMC - 637583001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 1743869.29 | | 1673451.40 | 95.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-30-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 23 |
Addl Days Granted | 0 |
Working Days Charged | 22 |
Percent Time Used | 95 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6375-83-001 CEN TEX HYDROSEED, INC. (0.00) STRIPE LINES, INC. (0.00)
|
Contract # | 06224413 |
| Totals | 1743869.29 | 576117.27 | 1673451.40 | 95.9 |
|
County | WASHINGTON |
Highway | US0290 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6376-13-001 |
Proj ID | RMC - 637613001 |
Work Type | SPOT BASE REPAIR |
|
| 0.010 | 638323.50 | | 1169707.20 | 99.9 |
Work Order | 08-24-21 |
Work Began | 08-24-21 |
Work Completed | |
Time Computed | 09-01-21 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 487 |
Percent Time Used | 66 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6376-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07214006 |
| Totals | 638323.50 | 151714.10 | 1169707.20 | 99.9 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6376-14-001 |
Proj ID | RMC - 637614001 |
Work Type | SPOT BASE REPAIR |
|
| 0.010 | 828385.00 | | 976970.22 | 99.9 |
Work Order | 08-12-21 |
Work Began | 08-12-21 |
Work Completed | |
Time Computed | 09-01-21 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 487 |
Percent Time Used | 66 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6376-14-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04214004 |
| Totals | 828385.00 | 68200.40 | 976970.22 | 99.9 |
|
County | WALKER |
Highway | SH0030 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6376-15-001 |
Proj ID | RMC - 637615001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 489000.00 | | 261612.16 | 53.4 |
Work Order | 04-14-21 |
Work Began | 04-14-21 |
Work Completed | |
Time Computed | 04-14-21 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 627 |
Percent Time Used | 85 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6376-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02214010 |
| Totals | 489000.00 | 17235.00 | 261612.16 | 53.4 |
|
County | BRAZOS |
Highway | SH0006 |
From | .05 MI N OF THE SPEEDWAY OVERPASS |
To | .65 MI S OF FM 159 |
CSJ | 6376-19-001 |
Proj ID | RMC - 637619001 |
Work Type | MILL AND INLAY |
|
| 3.564 | 2511623.23 | | 2750324.16 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-01-22 |
Work Completed | 12-13-22 |
Time Computed | 00-00-00 |
Contract Working Days | 34 |
Addl Days Granted | 7 |
Working Days Charged | 38 |
Percent Time Used | 92 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6376-19-001 FLASHER EQUIPMENT COMPANY (0.00) LONESTAR TRAFFIC SAFETY, LLC (0.00) FORTSON CONTRACTING, INC. (0.00) SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
|
Contract # | 01224004 |
| Totals | 2511623.23 | 1859.74 | 2750324.16 | 100.0 |
|
County | WASHINGTON |
Highway | US0290 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6383-13-001 |
Proj ID | RMC - 638313001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1685260.00 | | 834313.00 | 49.5 |
Work Order | 08-26-21 |
Work Began | 08-26-21 |
Work Completed | |
Time Computed | 08-26-21 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 481 |
Percent Time Used | 65 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6383-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07214005 |
| Totals | 1685260.00 | 51679.00 | 834313.00 | 49.5 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6383-14-001 |
Proj ID | RMC - 638314001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1602255.00 | | 1202205.00 | 75.0 |
Work Order | 08-30-21 |
Work Began | 08-30-21 |
Work Completed | |
Time Computed | 09-07-21 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 481 |
Percent Time Used | 65 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6383-14-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07214003 |
| Totals | 1602255.00 | 56309.75 | 1202205.00 | 75.0 |
|
County | BRAZOS |
Highway | FM2818 |
From | END OF CONCRETE PAVEMENT NEAR FM 2154 |
To | SH 6 EFR |
CSJ | 6394-29-001 |
Proj ID | RMC - 639429001 |
Work Type | ACP OVERLAY |
|
| 0.010 | 1660054.10 | | 1731855.71 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-12-22 |
Work Completed | 10-14-22 |
Time Computed | 00-00-00 |
Contract Working Days | 30 |
Addl Days Granted | 0 |
Working Days Charged | 51 |
Percent Time Used | 170 |
Contractor(s) |
BRAZOS PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6394-29-001 HIGHWAY 1 LLC (0.00) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.00)
|
Contract # | 02224208 |
| Totals | 1660054.10 | 83716.57 | 1731855.71 | 100.0 |
|
County | BRAZOS |
Highway | FM1179 |
From | SH 47 WFR |
To | FM 2154 |
CSJ | 6394-30-001 |
Proj ID | RMC - 639430001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 1299946.94 | | 2202207.34 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-01-22 |
Work Completed | 12-02-22 |
Time Computed | 00-00-00 |
Contract Working Days | 30 |
Addl Days Granted | 8 |
Working Days Charged | 36 |
Percent Time Used | 94 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6394-30-001 STRIPE LINES, INC. (0.00)
|
Contract # | 02224207 |
| Totals | 1299946.94 | 18751.06 | 2202207.34 | 100.0 |
|
County | WALKER |
Highway | IH0045 |
From | MONTGOMERY/WALKER COUNTY LINE |
To | FREESTONE/NAVARRO COUNTY LINE |
CSJ | 6395-34-001 |
Proj ID | RMC - 639534001 |
Work Type | PERFORMANCE BASED CONTRACT |
|
| 0.010 | 13514343.00 | | 1891795.61 | 13.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 1,095 |
Addl Days Granted | 0 |
Working Days Charged | 184 |
Percent Time Used | 16 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6395-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224006 |
| Totals | 13514343.00 | 322356.22 | 1891795.61 | 13.9 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6395-61-001 |
Proj ID | RMC - 639561001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 425505.40 | | 95576.20 | 22.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-25-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 251 |
Percent Time Used | 68 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6395-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02224206 |
| Totals | 425505.40 | 0.00 | 95576.20 | 22.4 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6396-16-001 |
Proj ID | RMC - 639616001 |
Work Type | THERMOPLASTIC PAVEMENT MARKINGS |
|
| 0.010 | 1994507.00 | | 1141527.20 | 57.2 |
Work Order | 05-23-22 |
Work Began | 05-17-22 |
Work Completed | |
Time Computed | 05-31-22 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 229 |
Percent Time Used | 62 |
Contractor(s) |
STRIPE-A-ZONE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6396-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224005 |
| Totals | 1994507.00 | 96710.57 | 1141527.20 | 57.2 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6399-77-001 |
Proj ID | RMC - 639977001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1276985.00 | | 699833.59 | 54.8 |
Work Order | 07-12-22 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 09-01-22 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 122 |
Percent Time Used | 33 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6399-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06224001 |
| Totals | 1276985.00 | 566403.80 | 699833.59 | 54.8 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6400-51-001 |
Proj ID | RMC - 640051001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1656940.00 | | 1037077.63 | 62.5 |
Work Order | 06-16-22 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 09-01-22 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 122 |
Percent Time Used | 33 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6400-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05224002 |
| Totals | 1656940.00 | 180142.06 | 1037077.63 | 62.5 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6400-70-001 |
Proj ID | RMC - 640070001 |
Work Type | SPOT BASE REPAIR |
|
| 0.010 | 898531.50 | | 471087.10 | 52.4 |
Work Order | 06-16-22 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 09-01-22 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 122 |
Percent Time Used | 33 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6400-70-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05224003 |
| Totals | 898531.50 | 55979.51 | 471087.10 | 52.4 |
|
County | BRAZOS |
Highway | FM1179 |
From | SH 6 WFR |
To | FM 2154 |
CSJ | 6402-13-001 |
Proj ID | RMC - 640213001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1289907.65 | | 1457565.28 | 100.0 |
Work Order | 08-04-22 |
Work Began | 09-01-22 |
Work Completed | 12-06-22 |
Time Computed | 09-01-22 |
Contract Working Days | 20 |
Addl Days Granted | 3 |
Working Days Charged | 24 |
Percent Time Used | 104 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6402-13-001 STRIPE LINES, INC. (0.00) CEN-TEX SEEDING, INC. (0.00)
|
Contract # | 06224412 |
| Totals | 1289907.65 | 49492.23 | 1457565.28 | 100.0 |
|