Monthly State Let Maintenance Report For Bryan District As Of Nov 10, 2024 Page 1 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwayIH0045
FromMONTGOMERY/WALKER COUNTY LINE
ToFREESTONE/NAVARRO COUNTY LINE
CSJ6395-34-001
Proj IDRMC - 639534001
Work TypePERFORMANCE BASED CONTRACT
 
0.01013514343.009407734.7369.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-22
Work Completed
Time Computed00-00-00
Contract Working Days1,095
Addl Days Granted0
Working Days Charged854
Percent Time Used77
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224006
Totals13514343.00344911.439407734.7369.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6411-55-001
Proj IDRMC - 641155001
Work TypeSPOT PAVEMENT MARKINGS
 
0.010458225.001242171.18100.0
Work Order10-20-22
Work Began10-20-22
Work Completed10-22-24
Time Computed10-20-22
Contract Working Days365
Addl Days Granted365
Working Days Charged712
Percent Time Used97
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224023
Totals458225.00130289.491242171.18100.0

CountyWASHINGTON
HighwayPR0012
FromINTERSECTION AT FM 1155
ToINTERSECTION AT FM 1155
CSJ6414-36-001
Proj IDRMC - 641436001
Work TypeLANDSCAPE MAINTENANCE
 
0.010899167.10983182.8699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-14-23
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged90
Percent Time Used97
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6414-36-001
CEN TEX HYDROSEED, INC. (0.00)
BROCK CONSTRUCTION, LLC (0.00)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.00)
JASON STORM LLC (0.00)
DAVID & DEIKE INTERESTS, L.L.C. (0.00)
Contract #02234208
Totals899167.100.00983182.8699.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6424-00-001
Proj IDRMC - 642400001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010528699.001121516.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged655
Percent Time Used89
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6424-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224206
Totals528699.000.001121516.0099.9

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6430-26-001
Proj IDRMC - 643026001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010548925.00589359.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-08-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted371
Working Days Charged573
Percent Time Used77
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6430-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234037
Totals548925.0059632.50589359.1899.9

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6432-72-001
Proj IDMMC - 643272001
Work TypeHOT MIX
 
0.010486600.001261845.5399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged274
Percent Time Used50
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6432-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234203
Totals486600.0032482.881261845.5399.9

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6436-39-001
Proj IDMMC - 643639001
Work TypeWINTER WEATHER MATERIAL
 
0.010450000.0046689.4010.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-04-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged516
Percent Time Used70
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6436-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234003
Totals450000.000.0046689.4010.3

CountyBRAZOS
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6438-49-001
Proj IDBPM - 643849001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010538850.00568429.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-08-23
Work Completed10-10-24
Time Computed00-00-00
Contract Working Days40
Addl Days Granted15
Working Days Charged67
Percent Time Used121
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-49-001
DIAMOND ELITE BARRICADES, LLC (0.00)
Contract #10234006
Totals538850.006180.00568429.50100.0

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6438-55-001
Proj IDBPM - 643855001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010442895.00330733.0074.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-13-24
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged42
Percent Time Used70
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234005
Totals442895.0060000.00330733.0074.6

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6439-18-001
Proj IDRMC - 643918001
Work TypeMILL AND INLAY
 
0.0101297678.006661536.9899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234004
Totals1297678.00831253.576661536.9899.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6439-20-001
Proj IDRMC - 643920001
Work TypeMILL AND INLAY
 
0.0101293480.001188714.8391.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234006
Totals1293480.000.001188714.8391.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6439-22-001
Proj IDRMC - 643922001
Work TypeMILL AND INLAY
 
0.0101747300.002657684.1299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234205
Totals1747300.00645724.812657684.1299.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6439-30-001
Proj IDRMC - 643930001
Work TypeSPOT BASE REPAIR
 
0.0101067637.501044416.9497.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234007
Totals1067637.50278302.691044416.9497.8

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6439-32-001
Proj IDRMC - 643932001
Work TypeSPOT BASE REPAIR
 
0.0101557750.001132289.9272.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234206
Totals1557750.000.001132289.9272.6

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6439-34-001
Proj IDRMC - 643934001
Work TypeSPOT BASE REPAIR
 
0.0103254250.003374986.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234005
Totals3254250.00353747.733374986.4099.9

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6441-94-001
Proj IDMMC - 644194001
Work TypeHOT MIX
 
0.010377600.001188473.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-16-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged439
Percent Time Used81
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6441-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234008
Totals377600.00184010.941188473.2599.9

CountyMADISON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6441-95-001
Proj IDMMC - 644195001
Work TypeHOT MIX
 
0.010389800.00667088.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-20-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged439
Percent Time Used81
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6441-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234009
Totals389800.004788.44667088.5599.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6442-24-001
Proj IDMMC - 644224001
Work TypeHOT MIX
 
0.010623600.001689757.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged268
Percent Time Used74
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6442-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234011
Totals623600.0094749.001689757.2099.9

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6442-38-001
Proj IDMMC - 644238001
Work TypeWINTER WEATHER MATERIAL
 
0.010341200.0031885.499.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted180
Working Days Charged387
Percent Time Used71
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234015
Totals341200.000.0031885.499.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6442-50-001
Proj IDRMC - 644250001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0102053200.001541216.2575.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged433
Percent Time Used59
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234016
Totals2053200.00125915.001541216.2575.0

page 1 | page 2 | page 3