Monthly State Let Maintenance Report For Bryan District As Of Jan 10, 2023 Page 1 Of 3

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6346-24-001
Proj IDRMC - 634624001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.001715533.002396480.7199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-04-19
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,215
Percent Time Used83
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6346-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194205
Totals715533.00159159.222396480.7199.9

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6348-24-001
Proj IDRMC - 634824001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0012322131.103706624.2099.9
Work Order06-23-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days731
Addl Days Granted731
Working Days Charged914
Percent Time Used62
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6348-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204002
Totals2322131.10135972.823706624.2099.9

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6364-18-001
Proj IDRMC - 636418001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001730335.00301064.83100.0
Work Order12-08-20
Work Began12-08-20
Work Completed12-08-22
Time Computed12-08-20
Contract Working Days730
Addl Days Granted0
Working Days Charged723
Percent Time Used99
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6364-18-001
JUNIOR CONSTRUCTION COMPANY, INC. (0.00)
Contract #09204205
Totals730335.002663.90301064.83100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6367-62-001
Proj IDRMC - 636762001
Work TypeREMOVE/INSTALL LARGE GUIDE SIGNS
 
0.001677125.00541436.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-05-21
Work Completed12-16-22
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged469
Percent Time Used128
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6367-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204204
Totals677125.000.00541436.40100.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6375-83-001
Proj IDRMC - 637583001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101743869.291673451.4095.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-30-22
Work Completed
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged22
Percent Time Used95
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6375-83-001
CEN TEX HYDROSEED, INC. (0.00)
STRIPE LINES, INC. (0.00)
Contract #06224413
Totals1743869.29576117.271673451.4095.9

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6376-13-001
Proj IDRMC - 637613001
Work TypeSPOT BASE REPAIR
 
0.010638323.501169707.2099.9
Work Order08-24-21
Work Began08-24-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted365
Working Days Charged487
Percent Time Used66
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6376-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214006
Totals638323.50151714.101169707.2099.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6376-14-001
Proj IDRMC - 637614001
Work TypeSPOT BASE REPAIR
 
0.010828385.00976970.2299.9
Work Order08-12-21
Work Began08-12-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted365
Working Days Charged487
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6376-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04214004
Totals828385.0068200.40976970.2299.9

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6376-15-001
Proj IDRMC - 637615001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010489000.00261612.1653.4
Work Order04-14-21
Work Began04-14-21
Work Completed
Time Computed04-14-21
Contract Working Days730
Addl Days Granted0
Working Days Charged627
Percent Time Used85
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214010
Totals489000.0017235.00261612.1653.4

CountyBRAZOS
HighwaySH0006
From.05 MI N OF THE SPEEDWAY OVERPASS
To.65 MI S OF FM 159
CSJ6376-19-001
Proj IDRMC - 637619001
Work TypeMILL AND INLAY
 
3.5642511623.232750324.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-22
Work Completed12-13-22
Time Computed00-00-00
Contract Working Days34
Addl Days Granted7
Working Days Charged38
Percent Time Used92
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6376-19-001
FLASHER EQUIPMENT COMPANY (0.00)
LONESTAR TRAFFIC SAFETY, LLC (0.00)
FORTSON CONTRACTING, INC. (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
Contract #01224004
Totals2511623.231859.742750324.16100.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6383-13-001
Proj IDRMC - 638313001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101685260.00834313.0049.5
Work Order08-26-21
Work Began08-26-21
Work Completed
Time Computed08-26-21
Contract Working Days730
Addl Days Granted0
Working Days Charged481
Percent Time Used65
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214005
Totals1685260.0051679.00834313.0049.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6383-14-001
Proj IDRMC - 638314001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101602255.001202205.0075.0
Work Order08-30-21
Work Began08-30-21
Work Completed
Time Computed09-07-21
Contract Working Days730
Addl Days Granted0
Working Days Charged481
Percent Time Used65
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214003
Totals1602255.0056309.751202205.0075.0

CountyBRAZOS
HighwayFM2818
FromEND OF CONCRETE PAVEMENT NEAR FM 2154
ToSH 6 EFR
CSJ6394-29-001
Proj IDRMC - 639429001
Work TypeACP OVERLAY
 
0.0101660054.101731855.71100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-12-22
Work Completed10-14-22
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged51
Percent Time Used170
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6394-29-001
HIGHWAY 1 LLC (0.00)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.00)
Contract #02224208
Totals1660054.1083716.571731855.71100.0

CountyBRAZOS
HighwayFM1179
FromSH 47 WFR
ToFM 2154
CSJ6394-30-001
Proj IDRMC - 639430001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101299946.942202207.34100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-22
Work Completed12-02-22
Time Computed00-00-00
Contract Working Days30
Addl Days Granted8
Working Days Charged36
Percent Time Used94
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6394-30-001
STRIPE LINES, INC. (0.00)
Contract #02224207
Totals1299946.9418751.062202207.34100.0

CountyWALKER
HighwayIH0045
FromMONTGOMERY/WALKER COUNTY LINE
ToFREESTONE/NAVARRO COUNTY LINE
CSJ6395-34-001
Proj IDRMC - 639534001
Work TypePERFORMANCE BASED CONTRACT
 
0.01013514343.001891795.6113.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-22
Work Completed
Time Computed00-00-00
Contract Working Days1,095
Addl Days Granted0
Working Days Charged184
Percent Time Used16
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224006
Totals13514343.00322356.221891795.6113.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6395-61-001
Proj IDRMC - 639561001
Work TypePAVEMENT MARKINGS
 
0.010425505.4095576.2022.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-25-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged251
Percent Time Used68
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6395-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224206
Totals425505.400.0095576.2022.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6396-16-001
Proj IDRMC - 639616001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.0101994507.001141527.2057.2
Work Order05-23-22
Work Began05-17-22
Work Completed
Time Computed05-31-22
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224005
Totals1994507.0096710.571141527.2057.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6399-77-001
Proj IDRMC - 639977001
Work TypeMILL AND INLAY
 
0.0101276985.00699833.5954.8
Work Order07-12-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6399-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224001
Totals1276985.00566403.80699833.5954.8

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6400-51-001
Proj IDRMC - 640051001
Work TypeMILL AND INLAY
 
0.0101656940.001037077.6362.5
Work Order06-16-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6400-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224002
Totals1656940.00180142.061037077.6362.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6400-70-001
Proj IDRMC - 640070001
Work TypeSPOT BASE REPAIR
 
0.010898531.50471087.1052.4
Work Order06-16-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6400-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224003
Totals898531.5055979.51471087.1052.4

CountyBRAZOS
HighwayFM1179
FromSH 6 WFR
ToFM 2154
CSJ6402-13-001
Proj IDRMC - 640213001
Work TypeMILL AND INLAY
 
0.0101289907.651457565.28100.0
Work Order08-04-22
Work Began09-01-22
Work Completed12-06-22
Time Computed09-01-22
Contract Working Days20
Addl Days Granted3
Working Days Charged24
Percent Time Used104
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6402-13-001
STRIPE LINES, INC. (0.00)
CEN-TEX SEEDING, INC. (0.00)
Contract #06224412
Totals1289907.6549492.231457565.28100.0

page 1 | page 2 | page 3