Monthly State Let Maintenance Report For Bryan District As Of Nov 10, 2024 Page 2 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6443-08-001
Proj IDRMC - 644308001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0102044500.001093294.1053.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged433
Percent Time Used59
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234017
Totals2044500.00114178.101093294.1053.4

CountyGRIMES
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6443-26-001
Proj IDMMC - 644326001
Work TypeWINTER WEATHER MATERIAL
 
0.010551200.0034559.516.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted180
Working Days Charged387
Percent Time Used71
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234212
Totals551200.000.0034559.516.2

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6444-52-001
Proj IDRMC - 644452001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.010949656.0079401.008.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-23
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234407
Totals949656.000.0079401.008.3

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6445-31-001
Proj IDMMC - 644531001
Work TypeHYDRAULIC CEMENT
 
0.010393592.8069292.6017.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged433
Percent Time Used80
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234408
Totals393592.8033063.8169292.6017.6

CountyBRAZOS
HighwayUS0190
FromDEMOCRAT ROAD
ToMADISON COUNTY LINE
CSJ6451-57-001
Proj IDRMC - 645157001
Work TypeMILL AND INLAY
 
0.0104330955.342541058.0058.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-02-24
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged26
Percent Time Used59
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6451-57-001
CEN-TEX SEEDING, INC. (0.00)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
STRIPE LINES, INC. (0.00)
Contract #05244008
Totals4330955.341671144.142541058.0058.6

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6456-43-001
Proj IDRMC - 645643001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010440007.00125075.5028.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-06-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged269
Percent Time Used36
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234006
Totals440007.0018907.50125075.5028.4

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6457-61-001
Proj IDMMC - 645761001
Work TypeHOT MIX
 
0.010519900.00924955.7899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged268
Percent Time Used49
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6457-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234012
Totals519900.00131742.58924955.7899.9

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6458-83-001
Proj IDRMC - 645883001
Work TypeTREE REMOVAL
 
0.010296255.00419584.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged169
Percent Time Used46
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6458-83-001
TEAL ARROW LLC (0.00)
Contract #03244005
Totals296255.00120483.00419584.0099.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6459-15-001
Proj IDRMC - 645915001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.0103575281.00744871.6620.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged268
Percent Time Used36
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234014
Totals3575281.00221307.95744871.6620.8

CountyMILAM
HighwayFM0486
FromVARIOUS
ToVARIOUS
CSJ6459-21-001
Proj IDRMC - 645921001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010226589.0442447.7818.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged268
Percent Time Used73
Contractor(s)
ABESCAPE LANDSCAPING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6459-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234204
Totals226589.040.0042447.7818.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6459-55-001
Proj IDMMC - 645955001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010292965.00225854.7577.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged260
Percent Time Used48
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6459-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234205
Totals292965.0094262.72225854.7577.0

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6459-57-001
Proj IDMMC - 645957001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010418245.00144285.7434.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged268
Percent Time Used49
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234015
Totals418245.0017901.55144285.7434.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6460-54-001
Proj IDBPM - 646054001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010455768.00334023.6873.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-02-24
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged39
Percent Time Used78
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244009
Totals455768.00209605.68334023.6873.2

CountyGRIMES
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6460-57-001
Proj IDBPM - 646057001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010270970.00226786.0085.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-03-24
Work Completed
Time Computed00-00-00
Contract Working Days31
Addl Days Granted0
Working Days Charged39
Percent Time Used125
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-57-001
GV LANDSCAPE AND CONSTRUCTION LLC (0.00)
Contract #06244010
Totals270970.00143950.80226786.0085.5

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6460-67-001
Proj IDMMC - 646067001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010281900.00202393.5071.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged268
Percent Time Used49
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234016
Totals281900.000.00202393.5071.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6460-95-001
Proj IDMMC - 646095001
Work TypeHYDRAULIC CEMENT
 
0.010400399.2046915.0511.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-09-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged237
Percent Time Used65
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244007
Totals400399.2011382.7546915.0511.7

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6462-10-001
Proj IDRMC - 646210001
Work TypeTREE REMOVAL
 
0.010285360.0043898.0015.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-05-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged210
Percent Time Used57
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-10-001
TEAL ARROW LLC (0.00)
Contract #02244227
Totals285360.0012892.0043898.0015.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6462-12-001
Proj IDRMC - 646212001
Work TypePAVEMENT MARKINGS
 
0.010491400.0078466.6015.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-27-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged188
Percent Time Used51
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244030
Totals491400.0041751.5078466.6015.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6466-07-001
Proj IDMMC - 646607001
Work TypeHOT MIX
 
0.010724325.00569208.7878.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-16-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged77
Percent Time Used21
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6466-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244011
Totals724325.00277139.74569208.7878.5

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6466-08-001
Proj IDMMC - 646608001
Work TypeHYDRAULIC CEMENT
 
0.010529715.2020428.803.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-16-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged77
Percent Time Used42
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6466-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244012
Totals529715.200.0020428.803.8

page 1 | page 2 | page 3