Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | WASHINGTON |
Highway | US0290 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6443-08-001 |
Proj ID | RMC - 644308001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 2044500.00 | | 1093294.10 | 53.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-26-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 433 |
Percent Time Used | 59 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6443-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234017 |
| Totals | 2044500.00 | 114178.10 | 1093294.10 | 53.4 |
|
County | GRIMES |
Highway | SH0030 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6443-26-001 |
Proj ID | MMC - 644326001 |
Work Type | WINTER WEATHER MATERIAL |
|
| 0.010 | 551200.00 | | 34559.51 | 6.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-11-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 180 |
Working Days Charged | 387 |
Percent Time Used | 71 |
Contractor(s) |
SOUTHWEST ENVIROTX PARTNERS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6443-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234212 |
| Totals | 551200.00 | 0.00 | 34559.51 | 6.2 |
|
County | BRAZOS |
Highway | US0190 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6444-52-001 |
Proj ID | RMC - 644452001 |
Work Type | INSTALLATION OF DRIVEWAY PIPE |
|
| 0.010 | 949656.00 | | 79401.00 | 8.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-08-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 420 |
Percent Time Used | 57 |
Contractor(s) |
DIGG COMMERCIAL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6444-52-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234407 |
| Totals | 949656.00 | 0.00 | 79401.00 | 8.3 |
|
County | WASHINGTON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6445-31-001 |
Proj ID | MMC - 644531001 |
Work Type | HYDRAULIC CEMENT |
|
| 0.010 | 393592.80 | | 69292.60 | 17.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-26-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 360 |
Working Days Charged | 433 |
Percent Time Used | 80 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6445-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234408 |
| Totals | 393592.80 | 33063.81 | 69292.60 | 17.6 |
|
County | BRAZOS |
Highway | US0190 |
From | DEMOCRAT ROAD |
To | MADISON COUNTY LINE |
CSJ | 6451-57-001 |
Proj ID | RMC - 645157001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 4330955.34 | | 2541058.00 | 58.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-02-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 44 |
Addl Days Granted | 0 |
Working Days Charged | 26 |
Percent Time Used | 59 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6451-57-001 CEN-TEX SEEDING, INC. (0.00) PROFESSIONAL TRAFFIC CONTROL LLC (0.00) STRIPE LINES, INC. (0.00)
|
Contract # | 05244008 |
| Totals | 4330955.34 | 1671144.14 | 2541058.00 | 58.6 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-43-001 |
Proj ID | RMC - 645643001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 440007.00 | | 125075.50 | 28.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-06-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 269 |
Percent Time Used | 36 |
Contractor(s) |
T&L CLEANING SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-43-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234006 |
| Totals | 440007.00 | 18907.50 | 125075.50 | 28.4 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6457-61-001 |
Proj ID | MMC - 645761001 |
Work Type | HOT MIX |
|
| 0.010 | 519900.00 | | 924955.78 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 360 |
Working Days Charged | 268 |
Percent Time Used | 49 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234012 |
| Totals | 519900.00 | 131742.58 | 924955.78 | 99.9 |
|
County | GRIMES |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6458-83-001 |
Proj ID | RMC - 645883001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 296255.00 | | 419584.00 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-16-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 169 |
Percent Time Used | 46 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-83-001 TEAL ARROW LLC (0.00)
|
Contract # | 03244005 |
| Totals | 296255.00 | 120483.00 | 419584.00 | 99.9 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-15-001 |
Proj ID | RMC - 645915001 |
Work Type | THERMOPLASTIC PAVEMENT MARKINGS |
|
| 0.010 | 3575281.00 | | 744871.66 | 20.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 268 |
Percent Time Used | 36 |
Contractor(s) |
STRIPE LINES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234014 |
| Totals | 3575281.00 | 221307.95 | 744871.66 | 20.8 |
|
County | MILAM |
Highway | FM0486 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-21-001 |
Proj ID | RMC - 645921001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 226589.04 | | 42447.78 | 18.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 268 |
Percent Time Used | 73 |
Contractor(s) |
ABESCAPE LANDSCAPING, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234204 |
| Totals | 226589.04 | 0.00 | 42447.78 | 18.7 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-55-001 |
Proj ID | MMC - 645955001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 292965.00 | | 225854.75 | 77.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 360 |
Working Days Charged | 260 |
Percent Time Used | 48 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-55-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234205 |
| Totals | 292965.00 | 94262.72 | 225854.75 | 77.0 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-57-001 |
Proj ID | MMC - 645957001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 418245.00 | | 144285.74 | 34.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 360 |
Working Days Charged | 268 |
Percent Time Used | 49 |
Contractor(s) |
MARTIN MARIETTA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234015 |
| Totals | 418245.00 | 17901.55 | 144285.74 | 34.4 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-54-001 |
Proj ID | BPM - 646054001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 455768.00 | | 334023.68 | 73.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-02-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 50 |
Addl Days Granted | 0 |
Working Days Charged | 39 |
Percent Time Used | 78 |
Contractor(s) |
SCR CIVIL CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244009 |
| Totals | 455768.00 | 209605.68 | 334023.68 | 73.2 |
|
County | GRIMES |
Highway | SH0105 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-57-001 |
Proj ID | BPM - 646057001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 270970.00 | | 226786.00 | 85.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-03-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 31 |
Addl Days Granted | 0 |
Working Days Charged | 39 |
Percent Time Used | 125 |
Contractor(s) |
RHINO EQUITY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-57-001 GV LANDSCAPE AND CONSTRUCTION LLC (0.00)
|
Contract # | 06244010 |
| Totals | 270970.00 | 143950.80 | 226786.00 | 85.5 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-67-001 |
Proj ID | MMC - 646067001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 281900.00 | | 202393.50 | 71.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 360 |
Working Days Charged | 268 |
Percent Time Used | 49 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-67-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234016 |
| Totals | 281900.00 | 0.00 | 202393.50 | 71.7 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-95-001 |
Proj ID | MMC - 646095001 |
Work Type | HYDRAULIC CEMENT |
|
| 0.010 | 400399.20 | | 46915.05 | 11.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-09-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 237 |
Percent Time Used | 65 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244007 |
| Totals | 400399.20 | 11382.75 | 46915.05 | 11.7 |
|
County | BURLESON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6462-10-001 |
Proj ID | RMC - 646210001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 285360.00 | | 43898.00 | 15.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-05-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 210 |
Percent Time Used | 57 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-10-001 TEAL ARROW LLC (0.00)
|
Contract # | 02244227 |
| Totals | 285360.00 | 12892.00 | 43898.00 | 15.3 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6462-12-001 |
Proj ID | RMC - 646212001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 491400.00 | | 78466.60 | 15.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-27-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 188 |
Percent Time Used | 51 |
Contractor(s) |
REPUBLIC TRAFFIC SAFETY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6462-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244030 |
| Totals | 491400.00 | 41751.50 | 78466.60 | 15.9 |
|
County | WASHINGTON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6466-07-001 |
Proj ID | MMC - 646607001 |
Work Type | HOT MIX |
|
| 0.010 | 724325.00 | | 569208.78 | 78.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-16-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 77 |
Percent Time Used | 21 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 6466-07-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244011 |
| Totals | 724325.00 | 277139.74 | 569208.78 | 78.5 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6466-08-001 |
Proj ID | MMC - 646608001 |
Work Type | HYDRAULIC CEMENT |
|
| 0.010 | 529715.20 | | 20428.80 | 3.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-16-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 77 |
Percent Time Used | 42 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6466-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244012 |
| Totals | 529715.20 | 0.00 | 20428.80 | 3.8 |
|