Monthly State Let Construction Report For Dallas District As Of Nov 10, 2024 Page 2 Of 7

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDENTON ETC
HighwayIH 35W ETC
FromAT FM 2449
ToIN THE CITY OF DENTON
CSJ0081-13-069
Proj IDSTP 2023(612)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.151726000.04373108.1851.4
Work Order05-25-23
Work Began06-21-24
Work Completed
Time Computed06-21-24
Contract Working Days60
Addl Days Granted0
Working Days Charged61
Percent Time Used101
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-13-069
SNOWHILL CONTRACTING LLC (21.36)
Contract #04233037
Totals726000.040.00373108.1851.4

CountyCOLLIN ETC
HighwaySH 289 ETC
FromAT CR 99 / CR 100
ToIN THE CITY OF CELINA
CSJ0091-03-031
Proj IDF 2023(708)
Work TypeTRAFFIC CONTROL DEVICES
 
0.3152504717.441156185.0246.1
Work Order06-19-23
Work Began06-13-24
Work Completed
Time Computed03-04-24
Contract Working Days220
Addl Days Granted0
Working Days Charged142
Percent Time Used64
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-031
MEDELLIN HDD LLC (1.51)
JR WEST TEXAS CONCRETE LLC (11.63)
LINEAR TRAFFIC MARKINGS LLC (3.22)
DOUBLE S CONSTRUCTION (1.17)
Contract #05233030
Totals2504717.44210226.141156185.0246.1

CountyCOLLIN
HighwaySH 289
FromPANTHER CREEK RELIEF
ToPANTHER CREEK
CSJ0091-04-069
Proj IDF 2024(319)
Work TypeRESTORATION
 
0.3083848916.551878687.1048.8
Work Order01-11-24
Work Began03-05-24
Work Completed
Time Computed03-04-24
Contract Working Days198
Addl Days Granted0
Working Days Charged139
Percent Time Used70
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-069
OSCAR ORDUNO, INC. (16.20)
SCOTT DERR PAINTING CO, LLC (0.19)
STOIC CIVIL CONSTRUCTION, INC. (20.58)
TEXAS SWPPP SERVICES (2.49)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.13)
AWP SAFETY (0.77)
BREDA COMPANY, INC. (0.09)
BRENDA PRICE TRUCKING, INC. (0.08)
CIVIL TREE SOLUTIONS, LLC (0.24)
Contract #10233027
Totals3848916.5531500.001878687.1048.8

CountyCOLLIN
HighwayBS 289C
FromBEECH STREET
ToSH 289S
CSJ0091-09-017
Proj IDC 91-9-17
Work TypeREHABILITATION OF EXISTING ROAD
 
1.4752843504.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0091-09-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243240
Totals2843504.700.000.000.0

CountyDALLAS
HighwayUS 175 ETC
FromSOUTH OF BUDD ST
ToIH 45
CSJ0092-01-052
Proj IDNH 2013(596)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.54478665971.4966351253.8185.9
Work Order01-15-20
Work Began07-06-20
Work Completed
Time Computed07-06-20
Contract Working Days813
Addl Days Granted40
Working Days Charged1,239
Percent Time Used145
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0092-01-052
TEXAS UTILITY SERVICE (3.21)
AREA WIDE PROTECTIVE, INC. (0.13)
LINDAMOOD DEMOLITION, INC. (1.30)
INTEGRATED ROADWAY SERVICES, INC. (5.72)
STRIPING TECHNOLOGY, L.P. (0.55)
ACT SAW CUTTING & REMOVAL (0.10)
HERITAGE MATERIALS, LLC (1.52)
OSCAR ORDUNO, INC. (1.15)
ANCORTEX, INC. (0.00)
PENHALL COMPANY (0.03)
STRAIGHT LINE SAWING & SEALING, INC. (0.01)
TORO BRAVO CONSTRUCTION, LLC (0.60)
JB PINNACLE GROUP, LLC (3.91)
MASSEY CONTRACTORS, LLC (0.16)
Q. ROBERTS TRUCKING INCORPORATED (1.01)
D. T. READ STEEL CO., INC. (0.21)
TORO BRAVO CONSTRUCTION, LLC (0.07)
J.H. PAINTING COMPANY (0.20)
LINDAMOOD, INC. (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.20)
CORONADO R. CONSTRUCTION, LLC (0.04)
ELITE EMERALD CONSTRUCTION, LLC (0.09)
RANGELINE UTILITY SERVICES LLC (0.24)
MONARREZ TRUCKING LLC. (0.25)
OSCAR RENDA CONTRACTING, INC. (3.17)
REY-MAR CONSTRUCTION (1.67)
Contract #12193001
Totals78665971.49541984.4866351253.8185.9

CountyDALLAS
HighwayIH 45
FromSOUTH OF MALLOY BRIDGE RD
ToIH 20
CSJ0092-02-135
Proj IDF 2B23(093)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.9077294650.853938823.8653.9
Work Order02-08-24
Work Began06-12-24
Work Completed
Time Computed06-10-24
Contract Working Days189
Addl Days Granted0
Working Days Charged94
Percent Time Used49
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-135
IBCTX, LLC (37.62)
DUSTROL, INC. (0.30)
KING GEORGE TRAFFIC SOLUTIONS LLC (5.35)
S & S BRIDGE PAINTING, INC. (2.11)
PEACHTREE CONSTRUCTION, LTD. (7.31)
TEXAS TRAFFIC AND BARRICADE, LLC (0.71)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
ACT SAW CUTTING & REMOVAL (0.25)
MACIAS SPECIALTY CONTRACTING LLC (4.86)
O. TREVINO CONSTRUCTION, LLC (3.83)
BRENDA PRICE TRUCKING, INC. (0.05)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.22)
ODUM SERVICES, LLC (3.30)
Contract #01243011
Totals7294650.85562778.403938823.8653.9

CountyDALLAS
HighwayIH 45
FromELLIS COUNTY LINE
ToSOUTH OF IH 20
CSJ0092-02-137
Proj IDCM 2023(611)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
9.5904499999.993171423.5070.4
Work Order06-28-23
Work Began02-13-24
Work Completed
Time Computed02-12-24
Contract Working Days320
Addl Days Granted0
Working Days Charged148
Percent Time Used46
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-137
NORTH TEXAS INTELLIGENT TRANSPORTATION SYSTEMS LLC (2.46)
SUPERIOR TRAFFIC CONTROL, LLC (0.37)
Contract #04233020
Totals4499999.99175119.903171423.5070.4

CountyDALLAS
HighwaySH 310
FromAT SIMPSON STUART RD
ToIN CITY OF DALLAS
CSJ0092-02-138
Proj IDSTP 2B24(163)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2002894528.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days169
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-138
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.37)
Contract #06243025
Totals2894528.770.000.000.0

CountyDALLAS ETC
HighwayIH 45 ETC
FromAT MALLOY BRIDGE ROAD (SOUTH BOUND)
To.
CSJ0092-02-141
Proj IDBR 2023(441)
Work TypeBRIDGE MAINTENANCE
 
4336407.904684991.3399.9
Work Order03-23-23
Work Began05-22-23
Work Completed
Time Computed04-24-23
Contract Working Days186
Addl Days Granted1
Working Days Charged237
Percent Time Used126
Contractor(s)
STRUCTURAL INTEGRITY GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-141
ODUM SERVICES, LLC (11.43)
DALLAS LITE AND BARRICADE, INC. (6.57)
STRIPING TECHNOLOGY, L.P. (0.00)
S&S BRIDGE PAINTING (0.71)
DELTA STRUCTURAL TECHNOLOGY, LLC (0.00)
AVILES CONSTRUCTION SERVICE, INC (5.56)
FC TRAFFIC CONTROL, INC. (0.00)
HOUSTON SAWING & DRILLING (0.00)
Contract #02233018
Totals4336407.901275311.014684991.3399.9

CountyELLIS
HighwayIH 45
FromNB MAINLANE AT SL 561 CROSSOVER
To.
CSJ0092-03-065
Proj IDF 2B24(067)
Work TypeRESTORATION
 
0.2182474265.000.000.0
CountyNAVARRO
HighwayIH 45
FromIH 45 EAST OF 287
ToIH 45 EAST
CSJ0093-01-106
Proj IDF 2B24(067)
Work TypeRESTORATION
 
0.1705304066.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0092-03-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243011
Totals7778331.000.000.000.0

CountyDALLAS
HighwaySH 356
FromSH 183
ToELM FORK TRINITY RIVER
CSJ0092-07-062
Proj IDC 92-7-62
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0407572475.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days188
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0092-07-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243209
Totals7572475.600.000.000.0

CountyNAVARRO
HighwayBI 45-F
FromHARTY ROAD
ToIH 45 SOUTH
CSJ0092-13-033
Proj IDC 92-13-33
Work TypeREHABILITATION OF EXISTING ROAD
 
4119672.99211419.755.1
Work Order04-18-24
Work Began08-08-24
Work Completed
Time Computed06-18-24
Contract Working Days106
Addl Days Granted0
Working Days Charged14
Percent Time Used13
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-13-033
CEN-TREE SOLUTIONS LLC (0.00)
FORTSON CONTRACTING, INC. (0.00)
JR WEST TEXAS CONCRETE LLC (0.00)
SUPERIOR TRAFFIC CONTROL, LLC (0.00)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.00)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.00)
Contract #03243016
Totals4119672.99158230.00211419.755.1

CountyDALLAS
HighwayIH 345
FromIH 30 INTERCHANGE
ToSPUR 366 INTERCHANGE
CSJ0092-14-086
Proj IDBR 2024(349)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1.40021883782.809409781.4742.9
Work Order03-14-24
Work Began05-13-24
Work Completed
Time Computed05-13-24
Contract Working Days378
Addl Days Granted0
Working Days Charged136
Percent Time Used35
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-086
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.63)
A BROTHERS MILLING, LLC (0.19)
ACT SAW CUTTING & REMOVAL (0.15)
JE CASEY, LLC (5.13)
DALLAS LITE AND BARRICADE, INC. (0.26)
TORO BRAVO CONSTRUCTION, LLC (0.09)
H TORRES TRUCKING, L.L.C. (0.00)
HYDRO TECHNOLOGIES, INC. (1.43)
TREENEWAL, LLC (0.01)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.01)
STEEL INSPECTORS OF TEXAS, INC. (0.37)
GLOBAL INDUSTRY GROUP INC (2.80)
J MUNOZ TRUCKING LLC (0.04)
PENHALL COMPANY (0.36)
DUSTROL, INC. (0.22)
ELITE STRIPING, LLC (0.55)
Contract #11233007
Totals21883782.80989616.489409781.4742.9

CountyDALLAS
HighwayIH 45
FromPENNSYLVANIA AVE
ToIH 30
CSJ0092-14-103
Proj IDF 2024(581)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.3467188411.941140019.9515.8
Work Order05-22-24
Work Began07-20-24
Work Completed
Time Computed06-22-24
Contract Working Days365
Addl Days Granted0
Working Days Charged128
Percent Time Used35
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-103
GLOBAL INDUSTRY GROUP INC (1.98)
HYDRO TECHNOLOGIES, INC. (10.92)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.76)
DALLAS LITE AND BARRICADE, INC. (0.18)
TEX OP CONSTRUCTION, LP (1.40)
H TORRES TRUCKING, L.L.C. (0.01)
ACT SAW CUTTING & REMOVAL (0.15)
Contract #12233019
Totals7188411.9487000.001140019.9515.8

CountyDALLAS
HighwayIH 45
FromOVERTON RD
ToIH 20
CSJ0092-14-104
Proj IDF 2B23(095)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.8533534464.303496374.9899.9
Work Order09-06-23
Work Began11-28-23
Work Completed
Time Computed10-06-23
Contract Working Days102
Addl Days Granted2
Working Days Charged160
Percent Time Used153
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-104
TEXAS SWPPP SERVICES (1.25)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.79)
WYLIE DRILLING & DRAINAGE, INC. (3.76)
BRENDA PRICE TRUCKING (1.08)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (2.63)
XROADS, L.P. (0.47)
Contract #08233229
Totals3534464.30296224.113496374.9899.9

CountyDALLAS
HighwayIH 45
FromAT NEWTON CREEK
ToAND FIVE MILE CREEK
CSJ0092-14-108
Proj IDC 92-14-108
Work TypeBRIDGE MAINTENANCE
 
0.2843175651.003196868.0899.9
Work Order02-05-24
Work Began05-13-24
Work Completed
Time Computed05-13-24
Contract Working Days262
Addl Days Granted0
Working Days Charged99
Percent Time Used37
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-108
G J SEEDING, LLC (3.47)
SUPERIOR TRAFFIC CONTROL, LLC (1.28)
Contract #01243223
Totals3175651.00764591.053196868.0899.9

CountyKAUFMAN
HighwayUS 80
FromLAWSON RD (DALLAS / KAUFMAN C/L)
ToFM 460
CSJ0095-03-080
Proj IDF 2022(793)
Work TypeWIDEN FREEWAY
 
1.984112819452.1663782648.0256.5
CountyKAUFMAN
HighwayUS 80
FromAT FM 460
To.
CSJ0095-03-085
Proj IDF 2022(793)
Work TypeBRIDGE REPLACEMENT
 
0.2106723348.945262486.7078.2
Work Order08-02-22
Work Began04-03-23
Work Completed
Time Computed04-03-23
Contract Working Days964
Addl Days Granted5
Working Days Charged455
Percent Time Used46
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-080
HB FARMER FOUNDATION, LLC (4.74)
J. H. ODEN CONTRACTING COMPANY (0.53)
TORO BRAVO CONSTRUCTION, LLC (5.88)
TEX OP CONSTRUCTION, LP (0.19)
TEXAS MATERIALS GROUP, INC. (9.97)
MICA CORPORATION (2.41)
HOUSTON SAWING & DRILLING (0.09)
DUSTIN ALLEN, INC. (0.16)
190 CONSTRUCTION LLC (1.71)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.24)
J & M CONTRACTING, COMPANY (1.50)
JE CASEY, LLC (0.31)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (1.80)
MONARREZ TRUCKING LLC. (0.16)
H SERVICES, LLC (0.04)
Q. ROBERTS TRUCKING INCORPORATED (2.37)
DURABLE SPECIALTIES, INC. (0.45)
INDUS ROAD & BRIDGE, INC. (1.06)
CND CONTRACTING (0.61)
MTAM CORPORATION (0.03)
Contract #06223401
Totals119542801.105879443.3869045134.7257.7

CountyKAUFMAN
HighwayUS 80
FromAT SH 205/FM 148
To.
CSJ0095-04-069
Proj IDCM 2022(384)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.49113807277.2710868978.6578.7
CountyKAUFMAN
HighwayUS 80
FromUS 80 EB
ToAT BACHELOR CREEK
CSJ0095-04-073
Proj IDBR 2022(385)
Work TypeBRIDGE REPLACEMENT
 
0.1732032084.902024876.9299.6
Work Order06-30-22
Work Began10-25-22
Work Completed
Time Computed10-28-22
Contract Working Days504
Addl Days Granted0
Working Days Charged494
Percent Time Used98
Contractor(s)
STERLING DELAWARE HOLDING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0095-04-069
A BROTHERS MILLING, LLC (0.93)
ACT SAW CUTTING & REMOVAL (0.36)
ANTIGO CONSTRUCTION, INC. (0.21)
DALLAS LITE AND BARRICADE, INC. (0.38)
BREDA COMPANY, INC. (0.27)
FARR FOUNDATION, INC. (0.56)
FORTSON CONTRACTING, INC. (0.18)
JB PINNACLE GROUP, LLC (0.43)
J. H. ODEN CONTRACTING COMPANY (0.97)
MELS ELECTRIC, L.P. (6.68)
RDI FOUNDATION DRILLING (0.51)
SCOTT DERR PAINTING CO, LLC (0.01)
SYNERGY SIGNS & SERVICES LLC (0.32)
TEXAS BOMANITE (1.45)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.03)
BRENDA PRICE TRUCKING (1.73)
PEACHTREE CONSTRUCTION, LTD. (20.42)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.26)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.29)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.87)
CURB PLANET INC. (0.19)
JMMO TRUCKING LLC (0.83)
XEGR, LLC (0.03)
Contract #03223203
Totals15839362.17372243.3712893855.5781.4

CountyKAUFMAN
HighwayUS 80
FromUS 80 AT FM 2728 (WEST)
To.
CSJ0095-05-063
Proj IDF 2022(826)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.245257050.95304031.3399.9
CountyDALLAS
HighwayIH 35E
FromRIVER BEND DR
ToNORTH MOCKINGBIRD INTERSECTION
CSJ0196-03-290
Proj IDF 2022(825)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5671534425.051609385.9599.9
CountyDALLAS
HighwayUS 175
FromRYLIE CREST
ToOLD MILL LN
CSJ0197-02-136
Proj IDF 2022(825)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.098363548.00341335.9393.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began02-27-23
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted5
Working Days Charged349
Percent Time Used131
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-05-063
JR WEST TEXAS CONCRETE LLC (18.33)
MICA CORPORATION (1.33)
ROAD MASTER STRIPING, LLC (2.70)
DALLAS LITE AND BARRICADE, INC. (0.07)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.74)
SALCOMM, LLC (4.57)
Contract #08223028
Totals2155024.00540.002254753.2199.9

CountyKAUFMAN ETC
HighwayIH 20 ETC
FromDALLAS COUNTY LINE
ToSP 557
CSJ0095-14-033
Proj IDC 95-14-33
Work TypeTRAFFIC CONTROL DEVICES
 
66.0402192309.352053099.7793.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged163
Percent Time Used40
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-14-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233235
Totals2192309.358932.282053099.7793.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7