Monthly State Let Construction Report For Dallas District As Of Nov 10, 2024 Page 6 Of 7

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDENTON
HighwayVA
FromVARIOUS LOCATIONS
ToIN DENTON COUNTY
CSJ0918-46-345
Proj IDC 918-46-345
Work TypeREHABILITATION OF EXISTING ROAD
 
1824550.78113769.416.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
TRAFFIC HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-345
STRIPE-A-ZONE, LLC (30.52)
Contract #04243022
Totals1824550.78113769.41113769.416.2

CountyDALLAS
HighwayCS
FromELSIE FAYE HEGGINS ST AT MALCOLM X BLVD
ToIN THE CITY OF DALLAS
CSJ0918-47-248
Proj IDSTP 2022(431)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1824000.00901149.2150.2
Work Order05-10-22
Work Began02-26-24
Work Completed
Time Computed04-17-23
Contract Working Days270
Addl Days Granted0
Working Days Charged289
Percent Time Used107
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-248
JR WEST TEXAS CONCRETE LLC (23.09)
ROAD MASTER STRIPING, LLC (2.97)
SALCOMM, LLC (6.20)
Contract #04223016
Totals1824000.0011935.00901149.2150.2

CountyDALLAS
HighwayCS
FromMCMILLAN AVE AT MOCKINGBIRD LN
ToIN THE CITY OF DALLAS
CSJ0918-47-249
Proj IDSTP 2022(338)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5921724000.00605125.5735.1
Work Order05-10-22
Work Began03-14-24
Work Completed
Time Computed04-17-24
Contract Working Days360
Addl Days Granted0
Working Days Charged310
Percent Time Used86
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-249
JR WEST TEXAS CONCRETE LLC (13.16)
ROAD MASTER STRIPING, LLC (4.95)
SALCOMM, LLC (9.49)
Contract #02223216
Totals1724000.0061761.06605125.5735.1

CountyDALLAS
Highway0000000
FromBARNES BRIDGE ROAD AT DUCK CREEK
To.
CSJ0918-47-288
Proj IDBR 2021(911)
Work TypeBRIDGE REPLACEMENT
 
2289177.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-288
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243023
Totals2289177.400.000.000.0

CountyDALLAS
HighwayCS ETC
FromVARIOUS INTERSECTIONS
ToIN THE CITY OF DALLAS
CSJ0918-47-342
Proj IDSTP 2023(705)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8002762362.5014573.000.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-30-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged135
Percent Time Used37
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-342
M. JONES CONSTRUCTION (0.27)
Contract #05233223
Totals2762362.500.0014573.000.5

CountyDALLAS
HighwayCS
FromAT OVERTON RD
ToIN THE CITY OF DALLAS.
CSJ0918-47-347
Proj IDSTP 2023(440)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8001765418.201587581.6289.9
Work Order03-16-23
Work Began10-16-23
Work Completed
Time Computed09-05-23
Contract Working Days340
Addl Days Granted0
Working Days Charged237
Percent Time Used69
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-347
WG ENGINEERING & CONSTRUCTION, LLC (60.74)
GOMEZ PROPERTY SOLUTIONS LLC (0.00)
STRIPE-A-ZONE, LLC (4.93)
Contract #02233229
Totals1765418.2075901.691587581.6289.9

CountyDALLAS
HighwayCR
FromON EAGLE FORD AND SHADY RIDGE CAMP LOOPS
ToWITHIN CEDAR HILL STATE PARK
CSJ0918-47-360
Proj IDC 918-47-360
Work TypeREHABILITATION OF EXISTING ROAD
 
3669509.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days253
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-360
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243225
Totals3669509.030.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0918-47-457
Proj IDSTP 2B24(223)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.393773400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-457
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243230
Totals773400.000.000.000.0

CountyCOLLIN
HighwayFM 543
FromAT TAYLOR BRANCH
To.
CSJ1012-01-017
Proj IDBR 2023(918)
Work TypeBRIDGE REPLACEMENT
 
0.2572920104.632887498.4198.8
Work Order07-19-23
Work Began11-03-23
Work Completed
Time Computed10-17-23
Contract Working Days214
Addl Days Granted0
Working Days Charged208
Percent Time Used97
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1012-01-017
WYLIE DRILLING & DRAINAGE, INC. (2.00)
WEST TEXAS ROCK RESOURCES, LLC (0.17)
TEXOP CONSTRUCTION (0.96)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.94)
SYNERGY SIGNS & SERVICES LLC (1.29)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.91)
HERMANOS STEEL, LLC (0.53)
FC TRAFFIC CONTROL, INC. (0.37)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.97)
HILBASH INVESTMENT LLC (3.42)
SOUTHEAST GRINDING AND GROOVING LLC (0.14)
HDZ CONSTRUCTION (0.00)
Contract #06233231
Totals2920104.63100008.232887498.4198.8

CountyDALLAS
HighwayFM 1382
FromCAMP WISDOM INTERSECTION
ToMANSFIELD RD
CSJ1047-03-079
Proj IDSTP 2024(350)TP
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
1.1684250000.003444085.6481.0
Work Order12-13-23
Work Began03-04-24
Work Completed
Time Computed01-12-24
Contract Working Days203
Addl Days Granted0
Working Days Charged150
Percent Time Used73
Contractor(s)
TEXAS-REYES GROUP LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-079
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (7.91)
SUPERIOR TRAFFIC CONTROL, LLC (0.20)
C T & S METAL FABRICATORS INC. (7.09)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.75)
QUALITY DUMP HAULERS, LLC (14.11)
FARR FOUNDATION, INC. (0.84)
Q. ROBERTS TRUCKING INCORPORATED (0.23)
Contract #11233211
Totals4250000.0047217.143444085.6481.0

CountyELLIS
HighwayFM 813
FromSIOUX DRIVE
ToSAPPHIRE LANE
CSJ1139-01-048
Proj IDF 2B23(108)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.2051051513.50813510.9077.7
Work Order09-07-23
Work Began11-27-23
Work Completed
Time Computed10-09-23
Contract Working Days100
Addl Days Granted0
Working Days Charged105
Percent Time Used105
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1139-01-048
ROAD SOLUTIONS L.L.C. (29.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.71)
Contract #08233060
Totals1051513.50143981.50813510.9077.7

CountyDENTON
HighwayFM 1385
FromNORTH OF FM 428
ToFM 455
CSJ1315-01-028
Proj IDF 2023(171)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.0087569742.932024816.3726.7
Work Order12-07-22
Work Began01-11-23
Work Completed
Time Computed01-09-23
Contract Working Days304
Addl Days Granted0
Working Days Charged183
Percent Time Used60
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-028
BARRICADES UNLIMITED (0.15)
DUSTROL, INC. (0.58)
TEXOP CONSTRUCTION (1.43)
PEACHTREE CONSTRUCTION, LTD. (5.17)
TRP CONSTRUCTION GROUP, LLC (1.01)
Contract #11223213
Totals7569742.9381431.282024816.3726.7

CountyCOLLIN
HighwayFM 1378
FromFM 3286
ToSOUTH OF FM 3286
CSJ1392-01-044
Proj IDCM 2023(702)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1.14811745456.814679866.0839.8
CountyCOLLIN
HighwayFM 1378
FromFM 3286
ToSOUTH OF FM 3286
CSJ1392-01-049
Proj IDROW 1392-01-049
Work TypeRIGHT OF WAY
 
0.6211893884.43722588.2438.1
Work Order06-14-23
Work Began10-16-23
Work Completed
Time Computed10-16-23
Contract Working Days659
Addl Days Granted0
Working Days Charged301
Percent Time Used45
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-044
ACT SAW CUTTING & REMOVAL (0.13)
BREDA COMPANY, INC. (0.38)
BRENDA PRICE TRUCKING (1.69)
TEX-BRASKA, LLC (0.00)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.98)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.57)
AWP SAFETY (0.63)
DURABLE SPECIALTIES, INC. (3.82)
SYNERGY SIGNS & SERVICES LLC (0.33)
T-BAR FENCE, INC. (0.24)
TEXOP CONSTRUCTION (1.98)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.92)
VENUS CONSTRUCTION COMPANY (13.03)
PEACHTREE CONSTRUCTION, LTD. (13.98)
Contract #05233209
Totals13639341.24372151.395402454.3239.6

CountyKAUFMAN
HighwayFM 1391
FromAT CEDAR CREEK RELIEF NO. 2
To.
CSJ1396-01-013
Proj IDBR 2024(767)
Work TypeBRIDGE REPLACEMENT
 
3454424.452198098.8563.6
CountyKAUFMAN
HighwayFM 1391
FromAT CEDAR CREEK
To.
CSJ1396-01-015
Proj IDBR 2024(743)
Work TypeBRIDGE REPLACEMENT
 
0.0171988899.05302174.0015.1
Work Order03-14-24
Work Began07-08-24
Work Completed
Time Computed04-13-24
Contract Working Days123
Addl Days Granted0
Working Days Charged78
Percent Time Used63
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1396-01-013
DIAMOND ELITE BARRICADES, LLC (0.12)
PROFESSIONAL TRAFFIC CONTROL LLC (0.15)
STRIPING TECHNOLOGY, L.P. (0.26)
SYNERGY SIGNS & SERVICES LLC (1.74)
TEXOP CONSTRUCTION (0.22)
PEACHTREE CONSTRUCTION, LTD. (2.82)
PRIMATE CONSTRUCTION, LP (0.15)
A. E. MOORE CONSTRUCTION, INC. (0.86)
Contract #02243217
Totals5443323.50791482.002500272.8545.9

CountyNAVARRO
HighwayFM 55
FromSH 22
ToELLIS COUNTY LINE
CSJ1451-03-017
Proj IDC 1451-3-17
Work TypeRESTORATION
 
4.3474964579.985285404.9499.9
Work Order03-16-22
Work Began04-08-22
Work Completed
Time Computed04-08-22
Contract Working Days210
Addl Days Granted0
Working Days Charged285
Percent Time Used135
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-03-017
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.89)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
STRIPE-A-ZONE, LLC (0.78)
MASSEY CONTRACTORS, LLC (1.17)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.40)
FORTSON CONTRACTING, INC. (2.39)
COLD CREEK CONSTRUCTION, LTD (0.82)
BEAR CREEK CONSTRUCTION, LLC (8.07)
AREA WIDE PROTECTIVE, INC. (0.02)
HOUSTON CONST TODAY INC (1.13)
J & M CONTRACTING, COMPANY (0.00)
Contract #02223003
Totals4964579.9899914.685285404.9499.9

CountyDENTON
HighwayFM 407
FromWISE COUNTY LINE
ToFM 156
CSJ1568-02-014
Proj IDF 2023(563)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.3966653767.016799336.1099.9
CountyDENTON
HighwayFM 407
FromAVERY RANCH WAY
To1M WEST OF FM 156
CSJ1568-02-015
Proj IDSTP 2023(564)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.9572316999.902507746.2799.9
Work Order06-28-23
Work Began08-07-23
Work Completed
Time Computed08-07-23
Contract Working Days203
Addl Days Granted2
Working Days Charged205
Percent Time Used100
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 1568-02-014
DALLAS LITE AND BARRICADE, INC. (0.31)
FORTSON CONTRACTING, INC. (0.32)
JR WEST TEXAS CONCRETE LLC (19.20)
MARCOMS CONSTRUCTION LLC (0.69)
TEXOP CONSTRUCTION (1.20)
TRP CONSTRUCTION GROUP, LLC (1.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (19.40)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
Contract #03233007
Totals8970766.9134932.969307082.3799.9

CountyELLIS
HighwayFM 2258
FromJOHNSON COUNTY LINE
ToFM 157
CSJ1599-05-011
Proj IDC 1599-5-11
Work TypeRESTORATION
 
2.5965747468.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days167
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1599-05-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243212
Totals5747468.580.000.000.0

CountyNAVARRO
HighwayFM 2930
FromFM 55 EAST
ToFM 1126 NORTH IN CRYER CREEK
CSJ1724-03-009
Proj IDC 1724-3-9
Work TypeREHABILITATION OF EXISTING ROAD
 
6.25211334814.784404541.0538.8
Work Order09-06-23
Work Began11-27-23
Work Completed
Time Computed10-09-23
Contract Working Days315
Addl Days Granted17
Working Days Charged168
Percent Time Used50
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1724-03-009
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.35)
MURRAY CONSTRUCTION (0.54)
STRIPE-A-ZONE, LLC (1.54)
TEXAS TRAFFIC AND BARRICADE, LLC (0.15)
COLD CREEK CONSTRUCTION, LTD (0.70)
FORTSON CONTRACTING, INC. (2.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.52)
BEAR CREEK CONSTRUCTION, LLC (25.33)
Contract #08233007
Totals11334814.78895117.454404541.0538.8

CountyKAUFMAN
HighwayFM 1895
FromFM 1836
ToBUS US 175 IN KEMP
CSJ1975-02-013
Proj IDC 1975-2-13
Work TypeREHABILITATION OF EXISTING ROAD
 
7.55011181793.396523149.4158.3
Work Order11-16-22
Work Began02-27-23
Work Completed
Time Computed02-20-23
Contract Working Days324
Addl Days Granted10
Working Days Charged336
Percent Time Used100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1975-02-013
BARRICADES UNLIMITED (0.10)
COLD CREEK CONSTRUCTION, LTD (0.57)
DUSTIN ALLEN, INC. (0.42)
MARCOM"S MOWING SERVICE, LLC (1.03)
TRP CONSTRUCTION GROUP, LLC (1.21)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.29)
J & M CONTRACTING, COMPANY (15.23)
J. H. ODEN CONTRACTING COMPANY (0.32)
Contract #10223007
Totals11181793.39702397.046523149.4158.3

CountyCOLLIN
HighwayFM 2551
FromFM 2514
ToFM 2170
CSJ2056-01-042
Proj IDC 2056-1-42
Work TypeWIDEN NON-FREEWAY
 
3.40245570230.016944669.5015.2
CountyCOLLIN
HighwayFM 2551
FromFM 2514
ToFM 2170
CSJ2056-01-043
Proj IDROW 2056-1-43
Work TypeRIGHT OF WAY
 
3.402763711.50316929.0041.4
Work Order07-26-23
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days648
Addl Days Granted0
Working Days Charged183
Percent Time Used28
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-042
MARCOMS CONSTRUCTION LLC (0.11)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.41)
BARRICADES UNLIMITED (0.33)
ACT SAW CUTTING & REMOVAL (0.30)
MICA CORPORATION (2.56)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (10.99)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.56)
BREDA COMPANY, INC. (0.91)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.09)
TEXAS AUGER BORING LLC (0.19)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (1.67)
TEXOP CONSTRUCTION (0.31)
Contract #04233202
Totals46333941.511501570.577261598.5015.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7