Monthly State Let Construction Report For El Paso District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwaySH 20 ETC
FromAT PA 2401/DONIPHAN DR/N MESA ST
To.
CSJ0001-01-062
Proj IDSTP 2021(621)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.0865350903.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days340
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-01-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213011
Totals5350903.140.000.000.0

CountyEL PASO
HighwaySH 20
From0.598 MI N OF SH 178
To0.553 MI N OF PA 2401
CSJ0001-01-063
Proj IDSTP 2021(688)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
221390.440.000.0
CountyEL PASO
HighwaySH 20
From0.598 MI N OF SH 178
To0.753 MI N OF PA 2401
CSJ0001-01-066
Proj IDF 2021(689)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.5842212270.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days193
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAWK CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0001-01-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213018
Totals2433661.190.000.000.0

CountyEL PASO
HighwaySH 20
FromSUNLAND PARK DRIVE
ToBALTIMORE DRIVE
CSJ0001-02-055
Proj IDNH 2019(781)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.02911138603.306711171.2660.2
CountyEL PASO
HighwaySH 20
FromSUNLAND PARK DRIVE
ToBALTIMORE DRIVE
CSJ0001-02-065
Proj IDROW 1-2-65
Work TypeRIGHT OF WAY
 
4.029318645.00580.000.1
Work Order12-30-19
Work Began04-13-20
Work Completed
Time Computed01-29-20
Contract Working Days240
Addl Days Granted45
Working Days Charged268
Percent Time Used94
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-055
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.19)
MAJOR MOTION LOGISTICS, LLC (8.05)
DUSTROL, INC. (2.64)
TRI STATE ELECTRIC, LTD. (0.83)
E. G. L. CONSTRUCTION, INC. (0.06)
PMI PAVEMENT MARKING, LLC (0.08)
Contract #11193207
Totals11457248.30389459.006711751.2658.5

CountyEL PASO
HighwaySH 20
From0.1 MI W OF BALTIMORE DR
ToCINCINNATI AVE
CSJ0001-02-069
Proj IDC 1-2-69
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.189359987.12114776.5931.8
CountyEL PASO
HighwaySH 20
FromCINCINNATI AVE
ToRIVER AVE
CSJ0001-03-061
Proj IDC 1-3-61
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.811382439.7324000.006.2
CountyEL PASO
HighwaySL 478
FromHARRISON AVE
ToFLORY AVE
CSJ0167-02-073
Proj IDC 167-2-73
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.338922711.98458336.2149.6
Work Order09-18-20
Work Began11-30-20
Work Completed
Time Computed10-18-20
Contract Working Days240
Addl Days Granted0
Working Days Charged120
Percent Time Used50
Contractor(s)
MARTINEZ BROS. CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-069
EL PASO A.R.C. ELECTRIC, INC. (55.93)
PMI PAVEMENT MARKING, LLC (2.73)
TRAFFIC BARRICADE SERVICE, INC. (5.48)
HARDY HOLE DRILLING (0.15)
Contract #08203240
Totals1665138.8384085.01597112.8035.8

CountyEL PASO
HighwaySH 20 ETC
FromAT MISSOURI AVE
To.
CSJ0001-03-058
Proj IDSTP 2019(963)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2643024946.562266290.1974.9
Work Order06-13-19
Work Began03-30-20
Work Completed
Time Computed07-13-19
Contract Working Days280
Addl Days Granted0
Working Days Charged203
Percent Time Used72
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-03-058
BORDER DRILLING LLC (0.33)
APOLLO CONSTRUCTORS, INC. (0.19)
DEL MAR CONTRACTING, INC. (7.27)
PMI PAVEMENT MARKING, LLC (6.25)
Contract #05193017
Totals3024946.565588.002266290.1974.9

CountyEL PASO
HighwaySH 20
From0.085 MI S OF FM 76
To0.17 MI W OF COLINA
CSJ0002-01-099
Proj IDSTP 2021(624)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.612767350.350.000.0
CountyEL PASO
HighwayFM 1281
FromFM 76
To1.194 MI N OF IH 10
CSJ3451-01-035
Proj IDSTP 2021(624)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.915803145.590.000.0
CountyEL PASO
HighwayFM 1281
From1.194 MI N OF IH 10
To5.474 MI E OF IH 10
CSJ3451-01-036
Proj IDSTP 2021(624)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2791252255.050.000.0
CountyEL PASO
HighwayFM 1281
From1.194 MI N OF IH 10
To5.474 MI E OF IH 10
CSJ3451-01-041
Proj IDF 2021(625)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2762348603.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days252
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213207
Totals5171354.490.000.000.0

CountyEL PASO
HighwaySH 20
From0.25 MI S OF SL 375
To2.256 MI S OF SL 375
CSJ0002-02-055
Proj IDF 2021(540)
Work TypeOVERLAY
 
2.0131795080.800.000.0
CountyEL PASO
HighwaySH 20
From0.15 MI E OF SL 375
To1.27 MI E OF SL 375
CSJ0002-02-056
Proj IDSTP 2021(553)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.120420179.500.000.0
CountyEL PASO
HighwaySH 20
From0.331 MI S OF SL 375
To2.256 MI S OF SL 375
CSJ0002-02-057
Proj IDSTP 2021(553)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.925391337.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213210
Totals2606597.500.000.000.0

CountyHUDSPETH
HighwayIH 10
From3.109 MI E OF SH 20
To0.12 MI E OF FM 34
CSJ0002-05-048
Proj IDSTP 2021(541)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
44.2764097877.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days411
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-05-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213207
Totals4097877.000.000.000.0

CountyHUDSPETH
HighwayIH 10
From3.114 MI N OF SH 20
To1.833 MI N OF SH 20
CSJ0002-05-050
Proj IDC 2-5-50
Work TypeREHABILITATION OF EXISTING ROAD
 
11.5581883865.281521408.7580.7
Work Order07-07-20
Work Began08-06-20
Work Completed
Time Computed08-06-20
Contract Working Days238
Addl Days Granted0
Working Days Charged213
Percent Time Used89
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-05-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05203225
Totals1883865.28149697.741521408.7580.7

CountyHUDSPETH
HighwayIH 10
From2.09 MI E OF FM 34
To11.172 MI E OF FM 34
CSJ0002-06-058
Proj IDF 2021(411)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.8051994619.340.000.0
Work Order05-27-21
Work Began00-00-00
Work Completed
Time Computed06-26-21
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIAMOND SURFACE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213033
Totals1994619.340.000.000.0

CountyHUDSPETH ETC
HighwayIH 10 ETC
From7.51 MI E OF FM 34
To8.505 MI E OF FM 34
CSJ0002-06-059
Proj IDSTP 2021(354)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.4903140241.000.000.0
Work Order03-12-21
Work Began00-00-00
Work Completed
Time Computed04-12-21
Contract Working Days220
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02213212
Totals3140241.000.000.000.0

CountyHUDSPETH
HighwayIH 10
FromLASCA RD
To3 MI W OF RM 1111
CSJ0002-07-054
Proj IDC 2-7-54
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.7262841820.202766764.5597.3
Work Order08-14-20
Work Began10-30-20
Work Completed
Time Computed09-13-20
Contract Working Days240
Addl Days Granted0
Working Days Charged150
Percent Time Used62
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-054
APOLLO CONSTRUCTORS, INC. (42.86)
Contract #07203025
Totals2841820.20197890.452766764.5597.3

CountyHUDSPETH ETC
HighwayIH 10
From19.02 MI E OF RM 1111
To4.73 MI W OF US 90
CSJ0002-10-038
Proj IDSTP 2021(554)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
59.4505286278.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days466
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-10-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213011
Totals5286278.000.000.000.0

CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-055
Proj IDSTP 2019(990)TAPS
Work TypeSAFETY REST AREA
 
3.91229044962.1122127382.8776.1
CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-056
Proj IDNH 1902(067)
Work TypeRIGHT OF WAY
 
3.912283266.80234843.0082.9
Work Order09-18-19
Work Began02-03-20
Work Completed
Time Computed11-17-19
Contract Working Days440
Addl Days Granted0
Working Days Charged342
Percent Time Used77
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0003-01-055
L & J CONSTRUCTION, INC. (0.16)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.57)
BOWMAN ENGINEERING & CONSULTING, INC. (0.67)
PAVEMENT MARKINGS INC. (0.17)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20)
ACCENT LANDSCAPE CONTRACTORS, INC. (2.18)
A BROTHERS MILLING, LLC (0.04)
HENRY TRUJILLO, INC. (1.25)
MEDLOCK COMMERCIAL CONTRACTORS, LLC (35.62)
ALLEN CONCRETE, LLC (6.36)
APCO BUILDING SPECIALTIES INC. (0.86)
LVR COMMERCIAL FLOORING, INC. (0.38)
YEAR ONE ELECTRICAL CONTRACTOR, LLC (3.24)
AQUATECH SEPTIC & UNDERGROUND, LLC (3.23)
ALLIED PAVING CO. (1.22)
LM ENDEAVOR LLC (0.35)
BARRAGAN"S GROUP LLC (1.91)
D & D PIMENTEL PLUMBING CONTRACTOR (0.56)
BELT CON CONSTRUCTION, INC. (3.73)
TDW (US), INC. (0.21)
CASEWORK SOLUTIONS, LLC (0.28)
HDW CONSTRUCTION & DRILLING, LLC. (0.47)
CURTIS-ABEL WATER SYSTEMS, INC. (0.77)
TEXAS DRYWALL & PAINT LLC (1.12)
KIMMINS KOATINGS (0.03)
MINER, LTD (0.02)
TRI STATE ELECTRIC, LTD. (2.62)
TORO BRAVO CONSTRUCTION, LLC (0.67)
BORDER DEMOLITION AND ENVIRONMENTAL, INC. (0.11)
PERFORMANCE GLASS & ALUMINUM, INC. (1.23)
PROTECH ROOFING SYSTEMS, LLC (3.66)
RIVER BEND CRANE & RIGGING, INC. (1.00)
OVER THE TOP TERRAZZO&TILE INC. (1.10)
APOLLO CONSTRUCTORS, INC. (1.36)
Contract #08193203
Totals29328228.91513901.1122362225.8776.2

CountyPRESIDIO
HighwayUS 67
From1.061 MI W OF BREWSTER CL
To2.486 MI W OF BREWSTER CL
CSJ0020-08-046
Proj IDSTP 2021(555)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.425653492.690.000.0
CountyPRESIDIO
HighwayUS 67
FromPRESIDIO/BREWSTER CL
ToPRESIDIO/BREWSTER CL
CSJ0020-10-018
Proj IDSTP 2021(555)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.49697696.220.000.0
CountyCULBERSON
HighwayUS 62
FromJCT OF US 62/SH 54
To8.685 MI N OF JCT OF US 62/SH 54
CSJ0233-02-031
Proj IDSTP 2021(555)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.685454895.780.000.0
CountyJEFF DAVIS
HighwaySH 118
FromSH 17
ToBREWSTER CL
CSJ0358-01-028
Proj IDSTP 2021(555)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
15.1161804216.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days352
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0020-08-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213021
Totals3010301.330.000.000.0

CountyJEFF DAVIS ETC
HighwaySH 17 ETC
FromREEVES COUNTY LINE
To7.77 MI E OF SH 118
CSJ0104-02-030
Proj IDSTP 2021(161)
Work TypeSEAL COAT
 
84.8526598503.115121198.6877.6
Work Order01-14-21
Work Began05-12-21
Work Completed
Time Computed05-10-21
Contract Working Days40
Addl Days Granted0
Working Days Charged38
Percent Time Used95
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0104-02-030
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (22.20)
FC TRAFFIC CONTROL, INC. (1.56)
CENTERLINE TECHNOLOGIES, LLC (4.58)
RED SIXTEEN CONSTRUCTION, INC (0.57)
LINEAR TRAFFIC MARKINGS LLC (0.16)
Contract #12203009
Totals6598503.113001620.455121198.6877.6

CountyPRESIDIO
HighwaySH 17
FromNORTH CITY LIMIT OF MARFA
ToJCT OF US 67/90
CSJ0104-05-025
Proj IDSTP 2021(356)
Work TypeREHABILITATION OF EXISTING ROAD
 
1293210.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-23-21
Work Began00-00-00
Work Completed
Time Computed07-12-21
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0104-05-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02213027
Totals1293210.530.000.000.0

CountyPRESIDIO
HighwayUS 67
From9.061 MI S OF RM 169
To25.02 MI N OF FM 170
CSJ0104-07-025
Proj IDSTP 2021(412)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
16.6722085521.30371700.0017.8
CountyPRESIDIO
HighwayUS 67
From25.02 MI N OF FM 170
To22.929 MI N OF FM 170
CSJ0104-08-025
Proj IDSTP 2021(412)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.089677493.300.000.0
Work Order04-08-21
Work Began00-00-00
Work Completed
Time Computed05-08-21
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0104-07-025
X GOMEZ LOGISTICS LLC (2.59)
4-WAY HAULERS, LLC (7.28)
DOUBLE A CONTRACTING, L.P. (7.71)
Contract #03213015
Totals2763014.60371700.00371700.0013.4

CountyPRESIDIO
HighwayUS 67
FromPUERTO RICO ST
ToINTERNATIONAL DEMARCATION LINE
CSJ0104-10-006
Proj IDNH 1702(686)
Work TypeNEW TWO-LANE TWIN BRIDGE STRUCTURE
 
0.6596854362.507269746.4399.9
Work Order09-25-17
Work Began05-21-18
Work Completed
Time Computed10-25-17
Contract Working Days260
Addl Days Granted245
Working Days Charged429
Percent Time Used84
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0104-10-006
PRIMATE CONSTRUCTION, INC. (0.19)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.73)
CONTRACTORS SERVICE COMPANY (0.85)
MICA CORPORATION (6.41)
LANCO TURF & SEEDING, INC. (0.20)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.88)
BOWMAN ENGINEERING & CONSULTING, INC. (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.47)
HAWK CONSTRUCTION (0.93)
Contract #08173207
Totals6854362.500.007269746.4399.9

CountyEL PASO
HighwayUS 54
FromLP 375 (CESAR CHAVEZ BORDER HWY)
ToYANDELL DR
CSJ0167-01-113
Proj IDNH 2019(166)
Work TypeINTERCHANGE IMPROVEMENTS
 
1.18189861277.4085028391.5694.6
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-118
Proj IDNH 2019(167)
Work TypeINSTALLATION OF SIGNS
 
0.900357297.000.000.0
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-119
Proj IDROW 167-1-119
Work TypeACQUISITION
 
0.900948024.00672890.6370.9
Work Order01-15-19
Work Began02-19-19
Work Completed
Time Computed02-02-19
Contract Working Days722
Addl Days Granted52
Working Days Charged694
Percent Time Used89
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-113
TRI STATE ELECTRIC, LTD. (17.11)
APACHE BARRICADE & SIGN (1.12)
NATIONWIDE REBAR, INC. (0.87)
HARDY HOLE DRILLING (8.97)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.74)
F A L C ENTERPRISES, LLC. (1.67)
THE GROUND LEVEL COMPANY (1.60)
BORDER DRILLING LLC (0.08)
DUSTROL, INC. (0.01)
ALLIED PAVING CO. (2.02)
ADVANCED CONCRETE SAWING & SEALING, LLC (0.09)
SCOTT DERR PAINTING CO, LLC (0.25)
HYDRATECH FIELD SERVICES, LLC (0.06)
HERNANDEZ CONCRETE PUMPING, INC. (0.57)
CRANE SERVICES, INC. (0.61)
SOUTHEAST GRINDING & GROOVING, LLC (0.07)
CHOCTAW ERECTORS, INC. (0.89)
OSCAR ORDUNO, INC. (0.95)
DH UNDERGROUND, INC. (0.12)
MAJOR MOTION LOGISTICS, LLC (1.50)
RMI WORLDWIDE LLC (0.13)
MARTINEZ BROS. CONTRACTORS, LLC (1.00)
NEW MEXICO TAP MASTER, INC. (0.00)
JORDAN FOSTER CONSTRUCTION, LLC (0.03)
BLACK STALLION CONTRACTORS INC. (0.01)
BORDER DEMOLITION AND ENVIRONMENTAL, INC. (0.00)
APOLLO CONSTRUCTORS, INC. (0.01)
Contract #11183001
Totals91166598.403582051.2285701282.1994.0

page 1 | page 2 | page 3