Monthly State Let Construction Report For El Paso District As Of Nov 10, 2024 Page 4 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwaySL 375
FromZARAGOZA RD
ToALAMEDA AVE
CSJ2552-03-070
Proj IDF 2022(824)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
678787.00538691.4079.3
Work Order09-21-22
Work Began11-15-22
Work Completed
Time Computed10-21-22
Contract Working Days60
Addl Days Granted40
Working Days Charged64
Percent Time Used64
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-03-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223243
Totals678787.0057623.15538691.4079.3

CountyEL PASO
HighwaySH 178
FromNM/TX STATELINE
ToIH 10
CSJ3592-01-009
Proj IDF 2B24(273)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
3.023237442317.921155840.000.4
CountyEL PASO
HighwaySH 178
FromNM/TX STATELINE
ToIH 10
CSJ3592-01-012
Proj IDROW 3592-1-12
Work TypeRIGHT OF WAY
 
3.0236305453.500.000.0
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed01-04-25
Contract Working Days1,273
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3592-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243002
Totals243747771.421155840.001155840.000.4

CountyPRESIDIO
HighwayCR
FromTEXAS / MEXICO BORDER ON RAIL LINE
ToINTERSECTION OF CR 31 / RAIL LINE
CSJ7124-01-006
Proj IDF 2B23(122)
Work TypeBORDER CROSSING FACILITY
 
27750000.001515125.005.4
Work Order04-18-24
Work Began08-19-24
Work Completed
Time Computed05-18-24
Contract Working Days342
Addl Days Granted0
Working Days Charged49
Percent Time Used14
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 7124-01-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243039
Totals27750000.00235125.001515125.005.4

page 1 | page 2 | page 3 | page 4