Monthly State Let Maintenance Report For El Paso District As Of Jul 13, 2021 Page 1 Of 2

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6215-03-001
Proj IDRMC - 621503001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
600.000315260.00267748.0584.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-10
Work Began11-01-10
Work Completed
Time Computed11-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6215-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09104013
Totals315260.000.00267748.0584.9

CountyEL PASO
HighwayIH0010
FromNEW MEXICO STATE LINE
ToEL PASO DISTRICT LINE
CSJ6336-60-001
Proj IDRMC - 633660001
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
100.000692027.501182752.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-19
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6336-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04194206
Totals692027.5085434.001182752.6099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6336-67-001
Proj IDRMC - 633667001
Work TypeMETAL BEAM GUARDRAIL FENCE REPAIR
 
200.000641335.701385865.96100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-19
Work Completed05-31-20
Time Computed00-00-00
Contract Working Days365
Addl Days Granted152
Working Days Charged486
Percent Time Used94
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6336-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184005
Totals641335.7060510.001385865.96100.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6336-70-001
Proj IDRMC - 633670001
Work TypeBARRICADES, SIGNS, TRAFFIC CONTROL
 
200.000177021.00213147.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-11-19
Work Completed03-10-20
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6336-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184205
Totals177021.000.00213147.50100.0

CountyEL PASO
HighwayUS0054
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6339-57-001
Proj IDBPM - 633957001
Work TypeBPM
 
1.000485854.80449482.3992.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-14-20
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged64
Percent Time Used53
Contractor(s)
MARTINEZ BROS. CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6339-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204214
Totals485854.8031867.34449482.3992.5

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6339-73-001
Proj IDRMC - 633973001
Work TypeILLUMINATION MAINTENANCE REPAIR
 
100.000408709.80917689.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-19
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged701
Percent Time Used96
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6339-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194012
Totals408709.804533.75917689.0499.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6341-33-001
Proj IDRMC - 634133001
Work TypeMOWING HIGHWAY RIGHT-OF-WAY
 
100.000297963.00290951.4497.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-23-19
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged38
Percent Time Used26
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6341-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03194016
Totals297963.0027428.91290951.4497.6

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6343-30-001
Proj IDRMC - 634330001
Work TypeCRACK SEAL
 
400.000344856.10324124.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-17-20
Work Completed02-24-20
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged6
Percent Time Used7
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6343-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194209
Totals344856.1064506.00324124.00100.0

CountyJEFF DAVIS
HighwaySH0118
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6351-25-001
Proj IDBPM - 635125001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010583501.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6351-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214209
Totals583501.700.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6353-33-001
Proj IDRMC - 635333001
Work TypeBARRICADES, SIGNS AND TRAFFIC CONTROL
 
2.000373710.00489914.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-31-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged457
Percent Time Used62
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6353-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204020
Totals373710.0046187.00489914.5099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6353-34-001
Proj IDRMC - 635334001
Work TypeROADWAY SPALL AND FULL DEPTH REPAIR
 
160.000678000.00746235.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6353-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204021
Totals678000.000.00746235.0599.9

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6356-80-001
Proj IDRMC - 635680001
Work TypeMOWING HIGHWAY RIGHT-OF-WAY
 
200.000330501.00319017.0096.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted110
Working Days Charged37
Percent Time Used18
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6356-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204022
Totals330501.000.00319017.0096.5

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6356-84-001
Proj IDRMC - 635684001
Work TypeROADWAY SPALL & FULL DEPTH REPAIR
 
80.000692800.00599410.9986.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6356-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204208
Totals692800.000.00599410.9986.5

CountyEL PASO
HighwaySL0375
FromSL 0375
ToVARIOUS LOCATIONS
CSJ6359-28-001
Proj IDRMC - 635928001
Work TypeREHABILITATION OF ROADWAY
 
5.0002225974.74464357.5720.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-03-20
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged301
Percent Time Used752
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6359-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204213
Totals2225974.74260122.07464357.5720.8

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6361-88-001
Proj IDRMC - 636188001
Work TypeCLEANING & SWEEPING
 
150.000605650.00693662.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6361-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204013
Totals605650.0047820.00693662.4899.9

CountyCULBERSON
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6361-89-001
Proj IDRMC - 636189001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
100.000431376.0022597.385.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6361-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204012
Totals431376.000.0022597.385.2

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6363-57-001
Proj IDRMC - 636357001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
50.000486280.00467371.1996.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-08-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged205
Percent Time Used56
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6363-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204012
Totals486280.00197027.91467371.1996.1

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6363-58-001
Proj IDRMC - 636358001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
100.000363194.00109649.1030.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-16-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged227
Percent Time Used62
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6363-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204017
Totals363194.0021644.26109649.1030.1

CountyEL PASO
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6363-59-001
Proj IDRMC - 636359001
Work TypePAVEMENT MARKINGS
 
222400.00130879.5458.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-12-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged80
Percent Time Used21
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6363-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214011
Totals222400.0017326.87130879.5458.8

CountyBREWSTER
HighwayRM2627
FromBREWSTER RM2627
ToBREWSTER RM2627
CSJ6365-90-001
Proj IDMMC - 636590001
Work TypeAGGREGATE (MATERIAL ONLY)
 
10.000566631.00564582.3399.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged45
Percent Time Used37
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6365-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204013
Totals566631.0049204.35564582.3399.6

page 1 | page 2