Monthly State Let Maintenance Report For El Paso District As Of Nov 10, 2024 Page 1 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6215-03-001
Proj IDRMC - 621503001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
600.000315260.00267748.0584.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-10
Work Began11-01-10
Work Completed
Time Computed11-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6215-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09104013
Totals315260.000.00267748.0584.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6336-67-001
Proj IDRMC - 633667001
Work TypeMETAL BEAM GUARDRAIL FENCE REPAIR
 
200.000641335.701385865.96100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-19
Work Completed05-31-20
Time Computed00-00-00
Contract Working Days365
Addl Days Granted152
Working Days Charged486
Percent Time Used94
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6336-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184005
Totals641335.7060510.001385865.96100.0

CountyEL PASO
HighwayFM0076
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6388-37-001
Proj IDRMC - 638837001
Work TypeMILL AND INLAY
 
0.0101061725.502492932.8899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-02-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6388-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234025
Totals1061725.500.002492932.8899.9

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6388-69-001
Proj IDRMC - 638869001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010769420.751602651.33100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-22
Work Completed03-01-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted425
Working Days Charged790
Percent Time Used100
Contractor(s)
B & MS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214212
Totals769420.750.001602651.33100.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6404-02-001
Proj IDBPM - 640402001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010637877.50925174.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-23
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted16
Working Days Charged72
Percent Time Used98
Contractor(s)
B & MS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6404-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234005
Totals637877.500.00925174.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6405-10-001
Proj IDRMC - 640510001
Work TypeCULVERT CLEANING
 
0.010435554.10721402.99100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-15-22
Work Completed08-13-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6405-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224605
Totals435554.100.00721402.99100.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6405-12-001
Proj IDRMC - 640512001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010921772.001753289.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-15-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
APACHE BARRICADE & SIGN
SUBCONTRACTOR(S) FOR CCSJ: 6405-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224604
Totals921772.000.001753289.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6409-71-001
Proj IDRMC - 640971001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101387135.002853120.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
APACHE BARRICADE & SIGN
SUBCONTRACTOR(S) FOR CCSJ: 6409-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224226
Totals1387135.000.002853120.6499.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6428-18-001
Proj IDRMC - 642818001
Work TypeCOMMUNICATION CABLE
 
1985311.56912470.2545.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged550
Percent Time Used75
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6428-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234217
Totals1985311.5611727.00912470.2545.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6429-06-001
Proj IDMMC - 642906001
Work TypeHOT MIX
 
0.010439500.0037990.168.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted330
Working Days Charged397
Percent Time Used88
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6429-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234020
Totals439500.0037990.1637990.168.6

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6429-14-001
Proj IDRMC - 642914001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101096192.781998197.7199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged565
Percent Time Used77
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234032
Totals1096192.7862136.911998197.7199.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6431-58-001
Proj IDBPM - 643158001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101643286.641209114.0373.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-22-24
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged100
Percent Time Used100
Contractor(s)
SPARTAN CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6431-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234011
Totals1643286.640.001209114.0373.5

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6435-00-001
Proj IDRMC - 643500001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010999905.401542134.6199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged483
Percent Time Used66
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6435-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234210
Totals999905.4086564.031542134.6199.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6435-88-001
Proj IDBPM - 643588001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101220296.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6435-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244201
Totals1220296.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6437-83-001
Proj IDRMC - 643783001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010400550.00591971.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-15-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged444
Percent Time Used60
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234026
Totals400550.0041432.50591971.4699.9

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6443-60-001
Proj IDMMC - 644360001
Work TypeDE-ICING SALT
 
0.010299056.0251692.8417.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-03-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged360
Percent Time Used100
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234021
Totals299056.020.0051692.8417.2

CountyBREWSTER
HighwayFM0170
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-12-001
Proj IDMMC - 644612001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010799135.00263772.8433.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-25-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged357
Percent Time Used66
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234209
Totals799135.000.00263772.8433.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-29-001
Proj IDRMC - 645129001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.0101201850.00470875.9039.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-04-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged302
Percent Time Used41
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234012
Totals1201850.009554.60470875.9039.1

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-31-001
Proj IDRMC - 645131001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010729500.00669661.2591.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-08-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged298
Percent Time Used40
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234013
Totals729500.0067735.00669661.2591.7

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-77-001
Proj IDRMC - 645177001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101194460.00838852.6070.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-18-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged228
Percent Time Used31
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244018
Totals1194460.00131564.50838852.6070.2

page 1 | page 2 | page 3