Monthly State Let Maintenance Report For El Paso District As Of Nov 10, 2024 Page 3 Of 3
Last Update: Sunday, November 10, 2024
|
| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | CULBERSON |
| Highway | IH0010 |
| From | VARIOUS LOCATIONS |
| To | VARIOUS LOCATIONS |
| CSJ | 6466-22-001 |
| Proj ID | RMC - 646622001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 578225.00 | | 145848.00 | 25.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 09-04-24 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 144 |
| Addl Days Granted | 0 |
| Working Days Charged | 25 |
| Percent Time Used | 17 |
| Contractor(s) |
| ABESCAPE GROUP LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6466-22-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 06244023 |
| Totals | 578225.00 | 12076.00 | 145848.00 | 25.2 |
|