Monthly State Let Maintenance Report For El Paso District As Of Nov 10, 2024 Page 3 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6466-22-001
Proj IDRMC - 646622001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010578225.00145848.0025.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-04-24
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged25
Percent Time Used17
Contractor(s)
ABESCAPE GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6466-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244023
Totals578225.0012076.00145848.0025.2