Monthly State Let Construction Report For Fort Worth District As Of Jan 10, 2023 Page 1 Of 6

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPALO PINTO
HighwayUS 180
FromWEST OF US 281
ToFM 1821
CSJ0008-01-046
Proj IDC 8-1-46
Work TypeOVERLAY
 
2.7715673196.482175801.6938.3
Work Order03-23-22
Work Began10-14-22
Work Completed
Time Computed04-23-22
Contract Working Days342
Addl Days Granted0
Working Days Charged29
Percent Time Used8
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-01-046
DURABLE SPECIALTIES, INC. (16.89)
JR WEST TEXAS CONCRETE LLC (5.35)
TRP CONSTRUCTION GROUP, LLC (1.90)
JAY MILLS CONTRACTING, INCORPORATED (1.42)
TEXAS TRAFFIC AND BARRICADE, LLC (1.08)
SOUTHERN CROSS CONTRACTORS, LLC (6.75)
Contract #02223004
Totals5673196.4812115.632175801.6938.3

CountyPARKER
HighwayUS 180
FromUS 180 WB OVER DRY CREEK
To.
CSJ0008-02-073
Proj IDF 2021(342)
Work TypeBRIDGE REPLACEMENT
 
0.0262139284.221507734.3572.4
Work Order08-12-21
Work Began10-15-21
Work Completed
Time Computed09-12-21
Contract Working Days216
Addl Days Granted2
Working Days Charged272
Percent Time Used124
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-073
LINDAMOOD DEMOLITION, INC. (1.76)
TOTAL HIGHWAY MAINTENANCE, LLC (1.81)
PEACHTREE CONSTRUCTION, LTD. (7.85)
FORTSON CONTRACTING, INC. (3.57)
TEXAS SHAFTS, INC. (4.85)
STOIC CIVIL CONSTRUCTION, INC. (13.10)
TEXOP CONSTRUCTION (0.51)
WOLFE CONSTRUCTION GROUP, INCORPORATED (2.46)
PROTEX EROSION CONTROL, LLC (0.55)
PINNACLE GRINDING AND GROOVING LLC (0.43)
SCOTT DERR PAINTING CO, LLC (0.13)
TORO BRAVO CONSTRUCTION, LLC (0.17)
FC TRAFFIC CONTROL, INC. (0.39)
PIERCE R & B LLC (7.24)
Contract #07213224
Totals2139284.2223594.141507734.3572.4

CountyPARKER
HighwayUS 180
From0.430 MILES E. OF FM 113 AT US 180
To0.430 MILES W. OF FM 113 AT US 180
CSJ0008-02-077
Proj IDSTP 2022(866)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
176530.711483.220.8
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed12-20-22
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223251
Totals176530.710.001483.220.8

CountyPARKER
HighwayIH 20
From450 FT WEST OF FM 5
To550 FT EAST OF FM 5
CSJ0008-03-089
Proj IDNH 1702(087)
Work TypeGRADING, PAVEMENT, STRIPING, & SIGN
 
0.1893921685.616698499.2199.9
Work Order09-21-17
Work Began01-07-19
Work Completed
Time Computed10-22-17
Contract Working Days192
Addl Days Granted415
Working Days Charged628
Percent Time Used103
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-089
BOWMAN ENGINEERING & CONSULTING, INC. (2.64)
RAMBO CONTRACTING, INC. (3.04)
MARCOM"S MOWING SERVICE, LLC (0.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.47)
FARR FOUNDATION, INC. (6.15)
DK CONTRACTING, LLC (0.65)
NORTHEASTERN PAVERS, INC. (7.16)
MICA CORPORATION (10.05)
TRP CONSTRUCTION GROUP, LLC (1.37)
DURABLE SPECIALTIES, INC. (5.60)
AAA DRILLING FOUNDATION CO., INC. (0.09)
NOLAND"S CONSTRUCTION, LLC (0.82)
Contract #08173237
Totals3921685.610.006698499.2199.9

CountyPARKER
HighwayUS 180
FromFM 730
ToCENTER POINT RD
CSJ0008-03-134
Proj IDF 2022(844)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
680358.258000.001.1
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed10-21-22
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223257
Totals680358.257200.008000.001.1

CountyTARRANT
HighwaySH 180
FromN. KENTUCKY AVE
ToBEACH ST.
CSJ0008-05-031
Proj IDSTP 2021(863)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1663320.501104031.9966.3
Work Order09-16-21
Work Began10-20-21
Work Completed
Time Computed10-17-21
Contract Working Days362
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-05-031
CLASSIC TEJAS CONSTRUCTION, INC. (5.95)
Contract #08213036
Totals1663320.5031976.501104031.9966.3

CountyTARRANT
HighwayIH 20
FromAT TRANSVISION TRAFFIC MANAGEMENT CENTER
ToON IH 20 AT MCCART
CSJ0008-12-095
Proj IDCM 2021(341)
Work TypeTRANSPORTATION NON-ROADWAY
 
1729558.351134450.2472.3
Work Order06-04-21
Work Began05-11-22
Work Completed
Time Computed09-03-21
Contract Working Days86
Addl Days Granted0
Working Days Charged236
Percent Time Used274
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-12-095
DATA PROJECTIONS, INC. (50.40)
VISTACOM CONTROL ROOM SOLUTIONS INC. (0.00)
D DUPUCH REAL ESTATE INC (1.73)
Contract #04213222
Totals1729558.35382063.101134450.2472.3

CountyTARRANT
HighwayIH 820 ETC
FromSH 121/SH 183 INTERCHANGE
ToRANDOL MILL ROAD
CSJ0008-13-221
Proj IDNH 2018(321)
Work TypeGR,DR,BS,STR,PAV,ITS,SGNL,ILLUM&SGN
 
8.944173724094.74165866799.4095.4
Work Order02-05-18
Work Began07-23-18
Work Completed
Time Computed06-06-18
Contract Working Days1,126
Addl Days Granted641
Working Days Charged1,318
Percent Time Used74
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-221
VENUS CONSTRUCTION COMPANY (3.23)
ATS DRILLING, L.P. (2.99)
DUSTROL, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
SOUTH TEXAS PAINTING CONTRACTORS (0.26)
STRUCTURAL TECHNOLOGIES, LLC (0.15)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
STORM WATER MANAGEMENT, INC. (0.14)
ADF EXCAVATION, LLC (0.13)
ANTIGO CONSTRUCTION, INC. (0.02)
PANIOLO CONSTRUCTION SERVICES, LLC (0.82)
MICA CORPORATION (5.11)
PREMIER PAVING, LTD. (9.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.26)
OSCAR ORDUNO, INC. (2.38)
(INACTIVE)AR DANIEL CONSTRUCTION SERVICES, INC. (0.69)
EPCS ENVIRONMENTAL, LLC (0.53)
JE CASEY, LLC (0.24)
ROYAL REBAR (0.81)
LINDAMOOD DEMOLITION, INC. (0.02)
BREDA COMPANY, INC. (0.01)
DURABLE SPECIALTIES, INC. (0.44)
LAWN PATROL SERVICE INC. (0.19)
PROTEX EROSION CONTROL, LLC (0.14)
SACE SERVICES, LLC (0.19)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.58)
BUYERS BARRICADES, INC. (0.40)
W.O.E. CONSTRUCTION, INC. (1.31)
PRIMATE CONSTRUCTION, LP (0.09)
HERMANOS STEEL, LLC (0.03)
HERMANOS STEEL, LLC (0.07)
ELITECURB & CONCRETE, LLC (0.66)
JB PINNACLE GROUP, LLC (0.66)
SCOTT DERR PAINTING CO, LLC (0.26)
ACT SAW CUTTING & REMOVAL (0.02)
EAST - TEX PIPE AND FAB LLC (0.05)
ROYAL REBAR (0.10)
TEXAS MATERIALS GROUP, INC. (0.24)
CHOCTAW ERECTORS, INC. (0.35)
Contract #12173001
Totals173724094.741980024.46165866799.4095.4

CountyTARRANT
HighwayIH 820
From0.124 MI SW OF FM 1220
To0.122 MI NE OF FM 1220
CSJ0008-14-118
Proj IDSTP 2022(287)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.246133150.0052400.0039.3
CountyTARRANT
HighwayIH 820
FromQUEBEC ST.
ToIH 35W
CSJ0008-14-119
Proj IDF 2022(230)
Work TypeOVERLAY
 
7.77310372494.764547909.0143.8
CountyTARRANT
HighwayIH 820
FromCAHOBA DR
ToIH 35
CSJ0008-14-120
Proj IDSTP 2022(287)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.89952458.400.000.0
Work Order02-16-22
Work Began05-09-22
Work Completed
Time Computed03-19-22
Contract Working Days278
Addl Days Granted0
Working Days Charged112
Percent Time Used40
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0008-14-118
DUSTROL, INC. (0.00)
SOUTHERN CROSS CONTRACTORS, LLC (0.00)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
STRIPING TECHNOLOGY, L.P. (0.00)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.00)
BARRICADES UNLIMITED (0.00)
Contract #01223004
Totals10558103.161069125.294600309.0143.5

CountyTARRANT
HighwayIH 820
From0.05 MILES N. OF CLIFFORD ST
To0.05 MILES S. OF CLIFFORD ST
CSJ0008-15-059
Proj IDF 2022(672)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
365571.75321530.3791.5
Work Order06-27-22
Work Began08-08-22
Work Completed
Time Computed07-28-22
Contract Working Days58
Addl Days Granted0
Working Days Charged80
Percent Time Used137
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05223239
Totals365571.7569957.72321530.3791.5

CountyTARRANT
HighwayIH 20
FromBRYANT IRVIN
ToWINSCOTT
CSJ0008-16-042
Proj IDNH 1902(222)
Work TypeWIDEN FREEWAY
 
2.20020961181.9417725201.8685.1
Work Order06-09-20
Work Began08-10-20
Work Completed
Time Computed07-10-20
Contract Working Days371
Addl Days Granted150
Working Days Charged568
Percent Time Used109
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-042
STRIPING TECHNOLOGY, L.P. (0.31)
ATS DRILLING, INC. (5.23)
EROSION PREVENTION PRODUCTS (4.89)
ACT SAW CUTTING & REMOVAL (0.07)
KELLER NORTH AMERICA, INC. (1.30)
PEACHTREE CONSTRUCTION, LTD. (3.98)
PROTEX EROSION CONTROL, LLC (0.11)
A BROTHERS MILLING, LLC (0.07)
COMEN ENTERPRISE LLC (0.03)
PINNACLE GRINDING AND GROOVING LLC (1.71)
COWBOY TRUCKING (0.45)
E.P. DRILLING, INC. (1.04)
THELIN RECYCLING COMPANY, L.P. (0.03)
PANIOLO CONSTRUCTION SERVICES, LLC (4.89)
BREDA COMPANY, INC. (0.63)
SELECT MAINTENANCE, L.L.C. (6.13)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.28)
ALLIANCE GEOTECHNICAL GROUP, INC. (0.45)
FUTURE INFRASTRUCTURE, LLC (0.07)
C.B. SERVICES, INC. (0.14)
SLATON BROTHERS, INC. (1.51)
TX DOWN UNDER CONSTRUCTION, LLC (0.08)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
PENHALL COMPANY (0.03)
LOLLAR CONSTRUCTION GROUP LLC (1.47)
TRAFFIC TECH SOLUTIONS, LLC (0.83)
J N K ADVANCE TREE SERVICE (0.59)
FC WELDING (0.05)
BROCK CONSTRUCTION, LLC (0.11)
REPUBLIC COMPOSITE STUD WELDING (0.01)
Contract #04203202
Totals20961181.94153911.1417725201.8685.1

CountyPALO PINTO
HighwayUS 180
FromSTEPHENS C/L
To0.978 MI EAST OF SH 16 SOUTH
CSJ0011-10-027
Proj IDSTP 2021(166)
Work TypeOVERLAY
 
13.3768439322.107357792.1187.1
Work Order12-04-20
Work Began07-06-21
Work Completed
Time Computed01-04-21
Contract Working Days448
Addl Days Granted0
Working Days Charged353
Percent Time Used78
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-10-027
JAY MILLS CONTRACTING, INCORPORATED (2.13)
JR WEST TEXAS CONCRETE LLC (8.35)
SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (3.20)
STATEWIDE SAFETY SYSTEMS (0.62)
TRP CONSTRUCTION GROUP, LLC (3.59)
CHEROKEE SERVICES (0.36)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
Contract #11203010
Totals8439322.1049790.257357792.1187.1

CountyWISE
HighwayUS 81
From0.5 MI. SOUTH OF CR 4228
ToTARRANT COUNTY LINE
CSJ0013-08-144
Proj IDSTP 2022(647)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
15.8251371550.1120400.001.4
Work Order07-06-22
Work Began00-00-00
Work Completed
Time Computed08-06-22
Contract Working Days235
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESSON CONSTRUCTION SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-144
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06223228
Totals1371550.110.0020400.001.4

CountyTARRANT
HighwayBU 287P
FromMINTON ROAD
ToSAGINAW CITY LIMITS
CSJ0013-10-089
Proj IDF 2022(845)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
406337.70164802.5040.5
Work Order09-21-22
Work Began11-07-22
Work Completed
Time Computed10-22-22
Contract Working Days85
Addl Days Granted0
Working Days Charged32
Percent Time Used37
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223062
Totals406337.7059644.00164802.5040.5

CountyTARRANT
HighwayBU 287P
FromAT SH 183
To.
CSJ0014-01-025
Proj IDSTP 2021(636)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200360530.00328645.0091.1
CountyTARRANT
HighwayBU 287P
FromAT SH 183
To.
CSJ0014-01-027
Proj IDF 2021(637)
Work TypeTRAFFIC CONTROL DEVICES
 
163470.00150827.4692.2
Work Order09-16-21
Work Began01-18-22
Work Completed
Time Computed12-16-21
Contract Working Days86
Addl Days Granted0
Working Days Charged85
Percent Time Used98
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-01-025
ROAD MASTER STRIPING, LLC (3.61)
BUYERS BARRICADES, INC. (4.14)
Contract #08213261
Totals524000.0039318.71479472.4691.5

CountyJOHNSON
HighwayIH 35W
FromCR 604/CR707
ToUS 67
CSJ0014-03-087
Proj IDBR 2022(867)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.14913369086.342004549.9514.9
Work Order09-21-22
Work Began11-30-22
Work Completed
Time Computed10-22-22
Contract Working Days231
Addl Days Granted0
Working Days Charged18
Percent Time Used7
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-087
ACT SAW CUTTING & REMOVAL (0.21)
BREDA COMPANY, INC. (0.68)
BRENDA PRICE TRUCKING (2.86)
XROADS, L.P. (0.31)
DUSTROL, INC. (1.10)
FORTSON CONTRACTING, INC. (0.96)
NORTHEASTERN PAVERS, LLC (9.67)
STRIPING TECHNOLOGY, L.P. (0.85)
SYNERGY SIGNS & SERVICES LLC (1.38)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.37)
TEXAS SWPPP SERVICES (0.29)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
ANTIGO CONSTRUCTION, INC. (0.26)
Contract #08223007
Totals13369086.341323754.102004549.9514.9

CountyTARRANT
HighwayUS 81
FromBNSF RAIL ROAD-US 287
To.
CSJ0014-15-080
Proj IDC 14-15-80
Work TypeRESTORATION
 
739218.400.000.0
Work Order08-31-22
Work Began00-00-00
Work Completed
Time Computed10-01-22
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-15-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03223018
Totals739218.400.000.000.0

CountyTARRANT
HighwayIH 35W
FromALTAMESA BLVD
ToLUELLA ST
CSJ0014-16-283
Proj IDC 14-16-283
Work TypeREHABILITATION OF EXISTING ROAD
 
10273783.293364040.5832.7
Work Order09-21-22
Work Began10-17-22
Work Completed
Time Computed10-17-22
Contract Working Days214
Addl Days Granted0
Working Days Charged42
Percent Time Used19
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-283
AREA WIDE PROTECTIVE, INC. (0.18)
SKIDABRADER GROUP LLC (43.97)
TRP CONSTRUCTION GROUP, LLC (10.49)
BRENDA PRICE TRUCKING (0.33)
PINNACLE GRINDING AND GROOVING LLC (0.19)
Contract #08223016
Totals10273783.29980377.003364040.5832.7

CountyJOHNSON
HighwaySH 171
FromHILL COUNTY LINE
ToSH 174
CSJ0019-02-034
Proj IDF 2021(340)
Work TypeOVERLAY
 
6387249.334033438.3363.1
Work Order03-25-21
Work Began06-09-21
Work Completed
Time Computed04-25-21
Contract Working Days320
Addl Days Granted0
Working Days Charged291
Percent Time Used90
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0019-02-034
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
MARCOM"S MOWING SERVICE, LLC (0.38)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53)
FORTSON CONTRACTING, INC. (1.81)
J & M CONTRACTING, COMPANY (1.65)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
NIXON ENGINEERING (0.08)
PINNACLE GRINDING AND GROOVING LLC (0.26)
CHEROKEE SERVICES (0.10)
TRAFCO INDUSTRIES, INC. (0.21)
POTTER TRUCKING (0.26)
Contract #02213205
Totals6387249.330.004033438.3363.1

CountyERATH
HighwayUS 377
FromUS 377 AT SOUTH PALUXY RIVER
To.
CSJ0080-02-061
Proj IDBR 2022(473)
Work TypeBRIDGE MAINTENANCE
 
437790.00765608.2599.9
Work Order06-16-22
Work Began08-15-22
Work Completed
Time Computed07-17-22
Contract Working Days22
Addl Days Granted0
Working Days Charged45
Percent Time Used204
Contractor(s)
WESSON CONSTRUCTION SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0080-02-061
MOBILE ENTERPRISES, INC. (0.00)
QMF STEEL, INC. (0.00)
DIIBS SPECIALISTS, LLC (0.00)
FC TRAFFIC CONTROL, INC. (0.00)
S&S BRIDGE PAINTING (0.00)
TEX OP CONSTRUCTION, LP (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
NORTHEASTERN PAVERS, LLC (0.00)
NORTH TEXAS CORING, INC. (0.00)
Contract #05223026
Totals437790.00218750.00765608.2599.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6