Monthly State Let Construction Report For Fort Worth District As Of Jul 13, 2021 Page 1 Of 5

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayUS 180
FromUS 180 WB OVER DRY CREEK
To.
CSJ0008-02-073
Proj IDF 2021(342)
Work TypeBRIDGE REPLACEMENT
 
0.0262139284.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days216
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213224
Totals2139284.220.000.000.0

CountyPARKER
HighwayIH 20
From450 FT WEST OF FM 5
To550 FT EAST OF FM 5
CSJ0008-03-089
Proj IDNH 1702(087)
Work TypeGRADING, PAVEMENT, STRIPING, & SIGN
 
0.1893921685.616520858.1199.9
Work Order09-21-17
Work Began01-07-19
Work Completed
Time Computed10-22-17
Contract Working Days192
Addl Days Granted367
Working Days Charged614
Percent Time Used109
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-089
BOWMAN ENGINEERING & CONSULTING, INC. (2.64)
RAMBO CONTRACTING, INC. (3.04)
MARCOM"S MOWING SERVICE, LLC (0.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.47)
FARR FOUNDATION, INC. (6.15)
DK CONTRACTING, LLC (0.65)
NORTHEASTERN PAVERS, INC. (7.16)
MICA CORPORATION (10.05)
TRP CONSTRUCTION GROUP, LLC (1.37)
DURABLE SPECIALTIES, INC. (5.60)
AAA DRILLING FOUNDATION CO., INC. (0.09)
NOLAND"S CONSTRUCTION, LLC (0.82)
Contract #08173237
Totals3921685.6116600.866520858.1199.9

CountyTARRANT
HighwayIH 20
FromAT TRANSVISION TRAFFIC MANAGEMENT CENTER
ToON IH 20 AT MCCART
CSJ0008-12-095
Proj IDCM 2021(341)
Work TypeTRANSPORTATION NON-ROADWAY
 
1729558.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-04-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-12-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213222
Totals1729558.350.000.000.0

CountyTARRANT
HighwayIH 820 ETC
FromSH 121/SH 183 INTERCHANGE
ToRANDOL MILL ROAD
CSJ0008-13-221
Proj IDNH 2018(321)
Work TypeGR,DR,BS,STR,PAV,ITS,SGNL,ILLUM&SGN
 
8.944173724094.74124197904.8771.4
Work Order02-05-18
Work Began07-23-18
Work Completed
Time Computed06-06-18
Contract Working Days1,126
Addl Days Granted0
Working Days Charged872
Percent Time Used77
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-221
VENUS CONSTRUCTION COMPANY (3.23)
ATS DRILLING, L.P. (2.99)
DUSTROL, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
SOUTH TEXAS PAINTING CONTRACTORS (0.26)
STRUCTURAL TECHNOLOGIES, LLC (0.15)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
STORM WATER MANAGEMENT, INC. (0.14)
ADF EXCAVATION, LLC (0.13)
ANTIGO CONSTRUCTION, INC. (0.02)
PANIOLO CONSTRUCTION SERVICES, LLC (0.82)
MICA CORPORATION (5.11)
PREMIER PAVING, LTD. (9.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.26)
OSCAR ORDUNO, INC. (2.38)
(INACTIVE)AR DANIEL CONSTRUCTION SERVICES, INC. (0.69)
EPCS ENVIRONMENTAL, LLC (0.53)
JE CASEY, LLC (0.24)
ROYAL REBAR (0.81)
LINDAMOOD DEMOLITION, INC. (0.02)
BREDA COMPANY, INC. (0.01)
DURABLE SPECIALTIES, INC. (0.44)
LAWN PATROL SERVICE INC. (0.19)
PROTEX EROSION CONTROL, LLC (0.14)
SACE SERVICES, LLC (0.19)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.58)
BUYERS BARRICADES, INC. (0.40)
W.O.E. CONSTRUCTION, INC. (1.31)
PRIMATE CONSTRUCTION, LP (0.09)
HERMANOS STEEL, LLC (0.03)
Contract #12173001
Totals173724094.741344855.18124197904.8771.4

CountyTARRANT
HighwayIH 20
FromIH 35W
ToCAMPUS DRIVE
CSJ0008-13-234
Proj IDCM 2B20(019)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.6571779729.961570340.3388.2
Work Order08-26-20
Work Began10-05-20
Work Completed
Time Computed09-26-20
Contract Working Days169
Addl Days Granted0
Working Days Charged165
Percent Time Used97
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-234
BUYERS BARRICADES, INC. (0.39)
SYNERGY SIGNS & SERVICES LLC (0.83)
D & S ENGINEERING LABS (0.09)
MICA CORPORATION (28.06)
PEACHTREE CONSTRUCTION, LTD. (3.72)
DUSTROL, INC. (0.48)
BREDA COMPANY, INC. (2.92)
ACTION SERVICES (1.21)
ACT SAW CUTTING & REMOVAL (0.32)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.59)
Contract #07203034
Totals1779729.96362322.601570340.3388.2

CountyTARRANT
HighwayIH 820
FromMEADOWBROOK DR
ToIH 20
CSJ0008-13-247
Proj IDC 8-13-247
Work TypeOVERLAY
 
1909076.401441046.5475.4
Work Order04-16-21
Work Began05-27-21
Work Completed
Time Computed05-17-21
Contract Working Days44
Addl Days Granted0
Working Days Charged24
Percent Time Used54
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-247
TEXAS TRAFFIC AND BARRICADE, LLC (0.35)
STRIPING TECHNOLOGY, L.P. (7.97)
JVH4 SERVICES, LLC (0.12)
Contract #03213014
Totals1909076.401441046.541441046.5475.4

CountyTARRANT
HighwayIH 820
FromAT AZLE AVE.
To.
CSJ0008-14-133
Proj IDC 8-14-133
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.100236887.00260388.5399.9
Work Order07-20-20
Work Began08-20-20
Work Completed
Time Computed08-20-20
Contract Working Days150
Addl Days Granted10
Working Days Charged50
Percent Time Used31
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-14-133
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06203031
Totals236887.002400.00260388.5399.9

CountyTARRANT
HighwayIH 820
FromIH 820/IH 20 SPLIT
ToWESTPOINT BLVD
CSJ0008-15-052
Proj IDC 8-15-52
Work TypeOVERLAY
 
2.9443195838.303460138.6099.9
Work Order07-07-20
Work Began08-03-20
Work Completed
Time Computed08-07-20
Contract Working Days128
Addl Days Granted40
Working Days Charged182
Percent Time Used108
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-052
STATEWIDE SAFETY SYSTEMS (0.53)
W.O.E. CONSTRUCTION, INC. (0.68)
PENHALL COMPANY (22.59)
FORTSON CONTRACTING, INC. (13.67)
TRP CONSTRUCTION GROUP, LLC (5.77)
BRENDA PRICE TRUCKING (0.75)
Contract #05203008
Totals3195838.30141419.523460138.6099.9

CountyTARRANT
HighwayIH 20
FromBRYANT IRVIN
ToWINSCOTT
CSJ0008-16-042
Proj IDNH 1902(222)
Work TypeWIDEN FREEWAY
 
2.20020961181.948741607.7941.7
Work Order06-09-20
Work Began08-10-20
Work Completed
Time Computed07-10-20
Contract Working Days371
Addl Days Granted0
Working Days Charged210
Percent Time Used56
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-042
STRIPING TECHNOLOGY, L.P. (0.31)
ATS DRILLING, INC. (5.23)
EROSION PREVENTION PRODUCTS (4.89)
ACT SAW CUTTING & REMOVAL (0.07)
KELLER NORTH AMERICA, INC. (1.30)
PEACHTREE CONSTRUCTION, LTD. (3.98)
PROTEX EROSION CONTROL, LLC (0.11)
A BROTHERS MILLING, LLC (0.07)
COMEN ENTERPRISE LLC (0.03)
PINNACLE GRINDING AND GROOVING LLC (1.71)
COWBOY TRUCKING (0.45)
E.P. DRILLING, INC. (1.04)
THELIN RECYCLING COMPANY, L.P. (0.03)
PANIOLO CONSTRUCTION SERVICES, LLC (4.89)
BREDA COMPANY, INC. (0.63)
SELECT MAINTENANCE, L.L.C. (6.13)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.28)
ALLIANCE GEOTECHNICAL GROUP, INC. (0.45)
FUTURE INFRASTRUCTURE, LLC (0.07)
C.B. SERVICES, INC. (0.14)
SLATON BROTHERS, INC. (1.51)
TX DOWN UNDER CONSTRUCTION, LLC (0.08)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
Contract #04203202
Totals20961181.941399554.498741607.7941.7

CountyPALO PINTO
HighwayUS 180
FromSTEPHENS C/L
To0.978 MI EAST OF SH 16 SOUTH
CSJ0011-10-027
Proj IDSTP 2021(166)
Work TypeOVERLAY
 
13.3768439322.10126261.921.4
Work Order12-04-20
Work Began07-06-21
Work Completed
Time Computed01-04-21
Contract Working Days448
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-10-027
JAY MILLS CONTRACTING, INCORPORATED (2.13)
JR WEST TEXAS CONCRETE LLC (8.35)
SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (3.20)
STATEWIDE SAFETY SYSTEMS (0.62)
TRP CONSTRUCTION GROUP, LLC (3.59)
CHEROKEE SERVICES (0.36)
Contract #11203010
Totals8439322.100.00126261.921.4

CountyWISE
HighwayUS 81
FromMONTAGUE COUNTY LINE
ToSOUTH OF CR 1590
CSJ0013-06-046
Proj IDNH 2021(495)
Work TypeOVERLAY
 
5.2482006415.220.000.0
CountyWISE
HighwayUS 81
From0.3 MILES NORTH OF CR 1591
ToCR 1591
CSJ0013-06-047
Proj IDSTP 2021(494)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.30019051.170.000.0
CountyWISE
HighwayUS 81
From.455 MILES NORTH OF CR 1596
To.057 MILES NORTH OF CR 1596
CSJ0013-06-048
Proj IDSTP 2021(494)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.398699023.460.000.0
CountyWISE
HighwayFM 2048
FromFM 51
To0.20 MILES EAST OF FM 51
CSJ2466-01-010
Proj IDSTP 2021(494)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20025504.480.000.0
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed06-20-21
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-06-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213209
Totals2749994.330.000.000.0

CountyTARRANT
HighwayBU 287P
FromNORTH OF BAILEY BOSWELL RD
ToIH 820
CSJ0013-10-084
Proj IDC 13-10-84
Work TypeOVERLAY
 
6.0974404395.362473623.3256.1
Work Order09-18-20
Work Began10-19-20
Work Completed
Time Computed10-19-20
Contract Working Days192
Addl Days Granted0
Working Days Charged107
Percent Time Used55
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-084
TEXAS TRAFFIC AND BARRICADE, LLC (0.47)
STRAIGHT LINE SAWING & SEALING, INC. (8.24)
TRP CONSTRUCTION GROUP, LLC (3.97)
FORTSON CONTRACTING, INC. (2.89)
Contract #05203216
Totals4404395.36439575.012473623.3256.1

CountyJOHNSON
HighwaySH 174
FromVAUGHN ST
ToHULEN ST
CSJ0019-01-147
Proj IDSTP 2B20(191)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
167768.15532.300.3
CountyJOHNSON
HighwayVA
FromVARIOUS LOCATIONS IN JOHNSON COUNTY
To.
CSJ0902-50-131
Proj IDSTP 2B20(190)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3624138.801617980.9444.6
CountyJOHNSON
HighwayFM 917
FromAPPLEWOOD CT.
ToEAST OF FM 2738
CSJ1181-04-050
Proj IDSTP 2B20(190)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.970196611.30184810.6593.9
Work Order08-26-20
Work Began03-10-21
Work Completed
Time Computed09-26-20
Contract Working Days320
Addl Days Granted0
Working Days Charged123
Percent Time Used38
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-147
STATEWIDE SAFETY SYSTEMS (2.25)
TRP CONSTRUCTION GROUP, LLC (0.55)
FOX CONTRACTING KY, INC. (22.83)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.63)
Contract #07203209
Totals3988518.25618745.091803323.8945.2

CountyJOHNSON
HighwaySH 171
FromHILL COUNTY LINE
ToSH 174
CSJ0019-02-034
Proj IDF 2021(340)
Work TypeOVERLAY
 
6387249.33501416.357.8
Work Order03-25-21
Work Began06-09-21
Work Completed
Time Computed04-25-21
Contract Working Days320
Addl Days Granted0
Working Days Charged34
Percent Time Used10
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0019-02-034
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
MARCOM"S MOWING SERVICE, LLC (0.38)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53)
FORTSON CONTRACTING, INC. (1.81)
J & M CONTRACTING, COMPANY (1.65)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
Contract #02213205
Totals6387249.33499486.35501416.357.8

CountyHOOD
HighwayUS 377
FromAPPROX. 1.4 MI SOUTH OF SH 171
ToJOHNSON COUNTY LINE
CSJ0080-11-001
Proj IDNH 1802(546)
Work TypeGR, DR, STR, BS AND PAVEMENT
 
1.70046969449.3529606144.8863.0
CountyJOHNSON
HighwayUS 377
FromHOOD COUNTY LINE
ToAPPROX. 1.1 MI NORTH OF SH 171
CSJ0080-12-001
Proj IDSTP 1802(547)
Work TypeGR, DR, STR, BS AND PAVEMENT
 
1.80613744380.856191093.2145.0
Work Order04-16-19
Work Began11-18-19
Work Completed
Time Computed08-14-19
Contract Working Days756
Addl Days Granted0
Working Days Charged361
Percent Time Used47
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0080-11-001
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.28)
T-BAR FENCE, INC. (0.05)
STRIPING TECHNOLOGY, L.P. (0.39)
ROYAL REBAR (4.74)
MICA CORPORATION (2.17)
C.B. SERVICES, INC. (0.47)
DUSTROL, INC. (0.24)
COMEN ENTERPRISE LLC (0.31)
J.E. GUZMAN CONSTRUCTION, INC. (0.69)
HERDEZ TRUCKING, INC. (2.78)
CHOCTAW ERECTORS, INC. (1.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
ATS DRILLING, INC. (1.31)
MCL CONTRACTING, LLC (0.05)
OSCAR ORDUNO, INC. (0.15)
J. H. ODEN CONTRACTING COMPANY (0.09)
PREMIER PAVING, LTD. (8.26)
J.H. PAINTING COMPANY (0.21)
JE CASEY, LLC (0.32)
TOR TEXAS, LLC DBA THE ORGANIC RECYCLER (0.01)
LINDAMOOD CONSTRUCTION COMPANY, INC. (3.10)
COWBOY TRUCKING (0.63)
LINDAMOOD DEMOLITION, INC. (3.10)
MCRYAN HAULING, INC. (0.02)
Contract #08183002
Totals60713830.20319815.8535797238.0958.9

CountyTARRANT
HighwayUS 377
FromSH 183
ToWEST OF BEACH ST
CSJ0081-01-049
Proj IDC 81-1-49
Work TypeOVERLAY
 
2.1211193706.58426354.7735.7
Work Order03-19-21
Work Began04-19-21
Work Completed
Time Computed04-19-21
Contract Working Days107
Addl Days Granted0
Working Days Charged49
Percent Time Used45
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-049
JVH4 SERVICES, LLC (0.19)
STRIPE-A-ZONE, INC. (3.06)
ACT SAW CUTTING & REMOVAL (2.65)
BRENDA PRICE TRUCKING (1.23)
SYNERGY SIGNS & SERVICES LLC (0.98)
O. TREVINO CONSTRUCTION, LLC (37.32)
BARRICADES UNLIMITED (0.85)
Contract #02213018
Totals1193706.58126235.28426354.7735.7

CountyTARRANT
HighwayUS 377
FromNORTH TARRANT PARKWAY
ToWATAUGA ROAD
CSJ0081-02-073
Proj IDNH 2B20(016)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
451588.66239354.5553.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-16-20
Work Began02-01-21
Work Completed
Time Computed01-16-21
Contract Working Days64
Addl Days Granted0
Working Days Charged56
Percent Time Used87
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0081-02-073
CENTRAL NORTH CONSTRUCTION, LLC (69.86)
Contract #11203019
Totals451588.660.00239354.5553.0

CountyWISE
HighwayFM 1810
FromFM 2127
ToBS 101B
CSJ0134-06-052
Proj IDSTP 1902(258)
Work TypeREHABILITATION OF EXISTING ROAD
 
11.34610846609.876376446.6858.7
Work Order11-13-19
Work Began05-26-20
Work Completed
Time Computed12-14-19
Contract Working Days320
Addl Days Granted0
Working Days Charged262
Percent Time Used81
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-06-052
BRENDA PRICE TRUCKING (1.48)
XROADS, L.P. (0.66)
JAGOE-PUBLIC COMPANY (36.92)
OSCAR ORDUNO, INC. (1.03)
STRIPING TECHNOLOGY, L.P. (1.12)
SYNERGY SIGNS & SERVICES LLC (0.42)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.30)
TOTAL HIGHWAY MAINTENANCE, LLC (0.09)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.38)
W. S. CONSTRUCTION COMPANY (7.31)
DALE BROWN, INC. (0.90)
DUSTROL, INC. (1.46)
ODUM SERVICES, LLC (1.08)
KLP COMMERCIAL, L.L.C. (0.75)
Contract #08193213
Totals10846609.87492860.956376446.6858.7

CountyWISE
HighwaySH 101
FromAPPROX. 3 MI N OF US 380
ToAPPROX. 1 MI S OF FM 1810
CSJ0134-06-053
Proj IDC 134-6-53
Work TypeREHABILITATION OF EXISTING ROAD
 
1.0804701956.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-06-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213015
Totals4701956.700.000.000.0

CountyJACK
HighwaySH 199
FromUS 281
ToWISE COUNTY LINE
CSJ0171-01-034
Proj IDNH 2019(872)
Work TypeOVERLAY
 
11.0005282831.684954340.6394.0
Work Order07-23-19
Work Began09-16-19
Work Completed
Time Computed08-23-19
Contract Working Days107
Addl Days Granted0
Working Days Charged121
Percent Time Used113
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0171-01-034
BUYERS BARRICADES, INC. (0.20)
COMEN ENTERPRISE LLC (4.78)
DUSTROL, INC. (7.30)
SCR CIVIL CONSTRUCTION, LLC (0.36)
TOTAL HIGHWAY MAINTENANCE, LLC (2.16)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
W.O.E. CONSTRUCTION, INC. (0.16)
Contract #06193022
Totals5282831.680.004954340.6394.0

page 1 | page 2 | page 3 | page 4 | page 5