Monthly State Let Maintenance Report For Fort Worth District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyERATH
HighwayUS0377
FromERATH
ToVARIOUS
CSJ6442-32-001
Proj IDRMC - 644232001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010469585.50366563.6578.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-11-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged320
Percent Time Used87
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234014
Totals469585.500.00366563.6578.0

CountyJOHNSON
HighwayFM1434
FromJOHNSON COUNTY
ToVARIOUS
CSJ6442-42-001
Proj IDRMC - 644242001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010767923.781658265.1099.9
Work Order00-00-00
Work Began02-13-24
Work Completed
Time Computed02-13-24
Contract Working Days365
Addl Days Granted0
Working Days Charged256
Percent Time Used70
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234018
Totals767923.78275428.651658265.1099.9

CountyHOOD
HighwayUS0377
FromHOOD, ERATH, SOMERVELL COUNTIES
ToVARIOUS LIMITS
CSJ6442-62-001
Proj IDRMC - 644262001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010339319.00413091.0099.9
Work Order00-00-00
Work Began10-19-23
Work Completed
Time Computed10-17-23
Contract Working Days730
Addl Days Granted0
Working Days Charged391
Percent Time Used53
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234219
Totals339319.000.00413091.0099.9

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
ToVARIOUS LIMITS
CSJ6445-12-001
Proj IDRMC - 644512001
Work TypeTREE REMOVAL
 
0.010396185.001337738.3099.9
Work Order00-00-00
Work Began01-12-24
Work Completed
Time Computed01-13-24
Contract Working Days365
Addl Days Granted0
Working Days Charged288
Percent Time Used78
Contractor(s)
PREMIER CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234019
Totals396185.00175961.601337738.3099.9

CountyJACK
HighwayUS0380
FromVARIOUS LOCATIONS WITHIN
ToJACK AND WISE COUNTIES
CSJ6446-32-001
Proj IDMMC - 644632001
Work TypeDENSE GRADED HOT MIX
 
0.010590000.00545405.7792.4
Work Order00-00-00
Work Began06-04-24
Work Completed
Time Computed11-17-23
Contract Working Days180
Addl Days Granted180
Working Days Charged344
Percent Time Used95
Contractor(s)
AUSTIN ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234025
Totals590000.00349767.34545405.7792.4

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6446-34-001
Proj IDRMC - 644634001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010523966.00183300.0034.9
Work Order00-00-00
Work Began09-03-24
Work Completed
Time Computed03-26-24
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234031
Totals523966.00183300.00183300.0034.9

CountyPALO PINTO
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPALO PINTO COUNTY
CSJ6447-63-001
Proj IDRMC - 644763001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010313206.00286067.0091.3
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed12-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged330
Percent Time Used90
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234015
Totals313206.000.00286067.0091.3

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToTARRANT COUNTY
CSJ6449-15-001
Proj IDBPM - 644915001
Work TypeBRIDGE JOINT REPAIR
 
0.0101669964.581758086.0699.9
Work Order00-00-00
Work Began05-19-24
Work Completed
Time Computed05-19-24
Contract Working Days121
Addl Days Granted0
Working Days Charged54
Percent Time Used44
Contractor(s)
12TWELVE ROAD AND BRIDGE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244006
Totals1669964.58411775.981758086.0699.9

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER COUNTY
CSJ6450-69-001
Proj IDRMC - 645069001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0103345738.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-31-24
Work Completed
Time Computed10-30-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6450-69-001
TEXOP CONSTRUCTION (0.00)
FC TRAFFIC CONTROL, INC. (0.00)
Contract #08244003
Totals3345738.000.000.000.0

CountyTARRANT
HighwayIH0820
FromTARRANT COUNTY
ToTARRANT COUNTY
CSJ6452-81-001
Proj IDRMC - 645281001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010924963.00955900.3499.9
Work Order00-00-00
Work Began04-14-24
Work Completed
Time Computed04-14-24
Contract Working Days365
Addl Days Granted0
Working Days Charged195
Percent Time Used53
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6452-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244019
Totals924963.00180699.48955900.3499.9

CountyERATH
HighwayUS0377
FromERATH COUNTY
ToHOOD COUNTY
CSJ6456-09-001
Proj IDRMC - 645609001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.010759555.00225038.1829.6
Work Order00-00-00
Work Began03-26-24
Work Completed
Time Computed03-14-24
Contract Working Days365
Addl Days Granted0
Working Days Charged226
Percent Time Used61
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244012
Totals759555.000.00225038.1829.6

CountyHOOD
HighwayBU0377H
FromVARIOUS LOCATIONS IN
ToHOOD AND SOMERVELL COUNTIES
CSJ6457-79-001
Proj IDRMC - 645779001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010440020.00677000.0099.9
Work Order00-00-00
Work Began03-19-24
Work Completed
Time Computed03-19-24
Contract Working Days365
Addl Days Granted0
Working Days Charged221
Percent Time Used60
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-79-001
CEN-TEX IRRIGATION SYSTEMS, INC. (0.00)
Contract #02244017
Totals440020.000.00677000.0099.9

CountyPALO PINTO
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPALO PINTO COUNTY
CSJ6460-15-001
Proj IDRMC - 646015001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101145494.00116860.0010.2
Work Order00-00-00
Work Began09-06-24
Work Completed
Time Computed09-04-24
Contract Working Days365
Addl Days Granted0
Working Days Charged52
Percent Time Used14
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6460-15-001
JUNIOR CONSTRUCTION COMPANY, INC. (0.00)
Contract #05244205
Totals1145494.0034305.00116860.0010.2

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6460-21-001
Proj IDRMC - 646021001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101599047.00129975.008.1
Work Order00-00-00
Work Began09-11-24
Work Completed
Time Computed09-11-24
Contract Working Days730
Addl Days Granted0
Working Days Charged52
Percent Time Used7
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6460-21-001
JUNIOR CONSTRUCTION COMPANY, INC. (0.00)
Contract #05244206
Totals1599047.0085396.00129975.008.1

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS IN
ToJOHNSON
CSJ6460-53-001
Proj IDRMC - 646053001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010400567.0560748.0415.1
Work Order00-00-00
Work Began08-14-24
Work Completed
Time Computed08-14-24
Contract Working Days730
Addl Days Granted0
Working Days Charged73
Percent Time Used10
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-53-001
TEXAS TMA RENTAL (0.00)
Contract #06244024
Totals400567.0543135.0460748.0415.1

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS IN
ToJOHNSON
CSJ6460-79-001
Proj IDRMC - 646079001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0103870005.40157387.004.0
Work Order00-00-00
Work Began10-21-24
Work Completed
Time Computed10-21-24
Contract Working Days730
Addl Days Granted0
Working Days Charged5
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6460-79-001
T&L CLEANING SERVICES LLC (0.00)
Contract #06244025
Totals3870005.40157387.00157387.004.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6462-02-001
Proj IDMMC - 646202001
Work TypeHOT MIX
 
0.010600500.00136887.4222.7
Work Order00-00-00
Work Began06-19-24
Work Completed
Time Computed06-19-24
Contract Working Days180
Addl Days Granted0
Working Days Charged130
Percent Time Used72
Contractor(s)
AUSTIN ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244011
Totals600500.0066959.64136887.4222.7

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6462-50-001
Proj IDMMC - 646250001
Work TypeHOT MIX
 
0.0101033100.008518.200.8
Work Order00-00-00
Work Began07-24-24
Work Completed
Time Computed07-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244207
Totals1033100.000.008518.200.8

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER & PALO PINTO COUNTIES
CSJ6463-48-001
Proj IDRMC - 646348001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010746149.606550.000.8
Work Order00-00-00
Work Began10-22-24
Work Completed
Time Computed10-22-24
Contract Working Days365
Addl Days Granted0
Working Days Charged4
Percent Time Used1
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6463-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244020
Totals746149.606550.006550.000.8

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToSOUTH TARRANT COUNTY
CSJ6464-52-001
Proj IDRMC - 646452001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0104459125.8649272.811.1
Work Order00-00-00
Work Began09-18-24
Work Completed
Time Computed09-18-24
Contract Working Days365
Addl Days Granted0
Working Days Charged38
Percent Time Used10
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244022
Totals4459125.8649272.8149272.811.1