Monthly State Let Construction Report For Lubbock District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARMER
HighwayUS 70
FromNEW MEXICO STATE LINE
ToEAST CITY LIMITS OF FARWELL
CSJ0052-01-042
Proj IDNH 2020(385)
Work TypeOVERLAY
 
3.96115350631.508747143.3260.1
Work Order02-24-20
Work Began03-28-20
Work Completed
Time Computed03-02-20
Contract Working Days375
Addl Days Granted0
Working Days Charged726
Percent Time Used193
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0052-01-042
FC TRAFFIC CONTROL, INC. (0.83)
HUDSON, INC. SOUTH (1.57)
DOUBLE A CONTRACTING, L.P. (1.86)
HJC FARMS, INC. (0.65)
WILLIS ELECTRIC CO., LP (4.37)
DTM TRUCKING, INC. (5.70)
HERITAGE MATERIALS, LLC (2.17)
M CO ASPHALT MILLING AND CONSTRUCTION, LLC (1.40)
BUTCH"S RAT HOLE & ANCHOR SERVICE, INC. (0.29)
FUSION COMMUNICATIONS, LLC (0.19)
ARTEX ELECTRIC CO. (0.56)
H & F TRUCKING (0.45)
INDUSTRIAL FABRICS, INC. (4.93)
FLAT LINE, INC. (1.53)
LMN TRANSPORT (1.15)
BARRICADES UNLIMITED (1.65)
TRP CONSTRUCTION GROUP, LLC (1.65)
BIG R TRUCKING TX LLC (0.65)
A BROTHERS MILLING, LLC (0.65)
Contract #12193006
Totals15350631.5017990.008747143.3260.1

CountyBAILEY ETC
HighwayUS 70 ETC
From0.2 MI WEST OF FM 1760
To0.2 MI EAST OF FM 1760
CSJ0052-02-037
Proj IDSTP 2023(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.7131843790.001808121.6398.0
Work Order06-28-23
Work Began10-09-23
Work Completed
Time Computed09-26-23
Contract Working Days121
Addl Days Granted0
Working Days Charged107
Percent Time Used88
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0052-02-037
DK CONTRACTING, LLC (5.85)
FC TRAFFIC CONTROL, INC. (1.93)
MICA CORPORATION (23.08)
FIBERTEX, LLC (4.22)
BARRICADES UNLIMITED (100.00)
Contract #05233239
Totals1843790.0097.071808121.6398.0

CountyLAMB ETC
HighwayUS 84 ETC
FromBAILEY COUNTY LINE
ToWEST SUDAN CITY LIMITS
CSJ0052-04-053
Proj IDF 2024(390)
Work TypeSEAL COAT
 
2.99522788746.1921647613.1894.9
Work Order02-02-24
Work Began06-11-24
Work Completed
Time Computed03-03-24
Contract Working Days64
Addl Days Granted0
Working Days Charged58
Percent Time Used90
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0052-04-053
FLAT LINE, INC. (5.78)
RED SIXTEEN CONSTRUCTION, INC (0.80)
Contract #11233202
Totals22788746.19286389.3121647613.1894.9

CountyLUBBOCK ETC
HighwayUS 84 ETC
FromCR 3300
ToFM 400
CSJ0053-01-135
Proj IDF 2025(164)
Work TypeSEAL COAT
 
6.78020682233.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0053-01-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243007
Totals20682233.920.000.000.0

CountyLUBBOCK ETC
HighwayUS 84 ETC
From0.37 MI NORTH OF LYNN COUNTY LINE
ToLYNN COUNTY LINE
CSJ0053-01-136
Proj IDF 2024(906)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
15.89113888521.250.000.0
Work Order05-16-24
Work Began00-00-00
Work Completed
Time Computed08-14-24
Contract Working Days350
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-01-136
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243005
Totals13888521.250.000.000.0

CountyLUBBOCK
HighwayUS 84
FromUS 82
ToIH 27
CSJ0053-18-048
Proj IDCR 2023(042)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.9689876826.698859557.0389.7
Work Order12-02-22
Work Began01-02-23
Work Completed
Time Computed01-02-23
Contract Working Days389
Addl Days Granted10
Working Days Charged335
Percent Time Used83
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-18-048
A BROTHERS MILLING, LLC (0.74)
DK CONTRACTING, LLC (0.58)
ALAMO BROTHERS CONCRETE INC (16.94)
TRP CONSTRUCTION GROUP, LLC (3.51)
BARRICADES UNLIMITED (0.40)
ARTEX ELECTRIC, INC. (13.85)
FIBERTEX, LLC (1.15)
H & F TRUCKING (0.70)
Contract #11223008
Totals9876826.69150119.868859557.0389.7

CountySWISHER
HighwayIH 27
FromON FM 1881
ToAT ATSF RAILROAD
CSJ0067-02-071
Proj IDBR 2021(558)
Work TypeBRIDGE MAINTENANCE
 
1.0002387019.202299331.9799.9
CountySWISHER
HighwayIH 27
FromON CR 113
ToAT ATSF RAILROAD
CSJ0067-02-072
Proj IDBR 2021(558)
Work TypeBRIDGE MAINTENANCE
 
1.0001355446.371604287.4299.9
Work Order09-01-21
Work Began09-13-21
Work Completed
Time Computed09-13-21
Contract Working Days354
Addl Days Granted0
Working Days Charged473
Percent Time Used133
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0067-02-071
ALAMO BROTHERS CONCRETE INC (0.00)
BARRICADES UNLIMITED (0.00)
DUSTROL, INC. (0.00)
S&S BRIDGE PAINTING (0.00)
TEXOP CONSTRUCTION (0.00)
STRUCTURAL INTEGRITY GROUP LLC (12.49)
TRP CONSTRUCTION GROUP, LLC (4.41)
GIBSON & ASSOCIATES, INC. (15.93)
Contract #05213215
Totals3742465.578400.003903619.3999.9

CountyHALE
HighwayIH 27
FromIH 27 SB
ToAT FM 54
CSJ0067-06-062
Proj IDBR 2B24(127)
Work TypeBRIDGE MAINTENANCE
 
285771.200.000.0
CountyHALE
HighwayIH 27
FromIH 27 NORTHBOUND
ToAT FM 54
CSJ0067-06-063
Proj IDBR 2B24(127)
Work TypeBRIDGE MAINTENANCE
 
296991.200.000.0
CountyLUBBOCK
HighwaySL 289
FromNE SL 289 EB
ToAT US 62/82
CSJ0783-02-104
Proj IDBR 2B24(126)
Work TypeBRIDGE MAINTENANCE
 
1545430.570.000.0
CountyLUBBOCK
HighwaySL 289
FromNE LP 289 WB
ToAT US 62/82
CSJ0783-02-105
Proj IDBR 2B24(126)
Work TypeBRIDGE MAINTENANCE
 
1645420.570.000.0
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed09-30-24
Contract Working Days248
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0067-06-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243020
Totals3773613.540.000.000.0

CountyLUBBOCK
HighwayIH 27
From0.5 MILES SOUTH OF YUCCA LANE
To0.5 MILES NORTH OF YUCCA LANE
CSJ0067-07-094
Proj IDBR 2B23(042)
Work TypeBRIDGE REPLACEMENT
 
1.00012783073.219929898.0077.6
CountyLUBBOCK
HighwayIH 27
From0.5 MI NORTH OF SL 289
ToCLEMSON STREET
CSJ0067-07-103
Proj IDBR 2B23(042)
Work TypeBRIDGE REPLACEMENT
 
5683704.8286026.581.5
CountyLUBBOCK
HighwayIH 27
From0.5 MI NORTH OF LP 289
ToCLEMSON STREET
CSJ0067-07-104
Proj IDBR 2B23(042)
Work TypeBRIDGE REPLACEMENT
 
5863323.8826867.450.4
Work Order09-07-23
Work Began02-05-24
Work Completed
Time Computed11-14-23
Contract Working Days630
Addl Days Granted8
Working Days Charged179
Percent Time Used28
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0067-07-094
KING GEORGE TRAFFIC SOLUTIONS LLC (1.30)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.07)
HJC FARMS, INC. (1.81)
LMSE TRUCKING, LLC (1.24)
190 CONSTRUCTION LLC (4.43)
ARTEX ELECTRIC, INC. (1.92)
BEAVER CONTRACTORS, LLC (0.66)
DK CONTRACTING, LLC (0.44)
DUININCK, INC. (7.60)
DUSTROL, INC. (0.12)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.06)
SK CONCRETE SERVICES LLC (0.04)
TORO BRAVO CONSTRUCTION, LLC (3.05)
TORO BRAVO CONSTRUCTION, LLC (0.08)
ADRIAN CONTRACTING, INC (0.05)
CABELLO CONSTRUCTION LLC (0.20)
BARRICADES UNLIMITED (0.01)
Contract #08233209
Totals24330101.91747828.1310042792.0341.2

CountyLUBBOCK
HighwayIH 27
From0.5 MILE SOUTH OF FM 1294
To0.5 MIL NORTH OF FM 1294
CSJ0067-07-100
Proj IDBR 2023(366)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1475120.502647772.460.0
CountyLUBBOCK
HighwayIH 27
From0.5 SOUTH OF FM 1294
To0.5 MILE NORTH OF FM 1294
CSJ0067-07-101
Proj IDBR 2023(366)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
636350.001420487.100.0
CountyLUBBOCK
HighwayIH 27
From0.5 MILE SOUTH OF BRIDGE
To0.5 MILE NORTH OF BRIDGE
CSJ0067-11-046
Proj IDF 2023(366)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
175460.00204727.610.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-23
Work Began05-12-23
Work Completed
Time Computed05-01-23
Contract Working Days223
Addl Days Granted45
Working Days Charged277
Percent Time Used103
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0067-07-100
BARRICADES UNLIMITED (1.14)
DIIBS SPECIALISTS, LLC (1.89)
DUSTROL, INC. (0.81)
NELSON INDUSTRIAL SERVICES, INC. (0.78)
ALAMO BROTHERS CONCRETE INC (25.90)
TEXAS CUTTING & CORING GP, INC. (1.74)
TRUMBLE CRANE & RIGGING (2.85)
TRP CONSTRUCTION GROUP, LLC (3.23)
GIBSON & ASSOCIATES, INC. (37.73)
Contract #01233229
Totals2286930.500.004272987.170.0

CountyLUBBOCK
HighwayUS 87
From0.5 MI NORTH OF FM 41
To0.5 MI SOUTH OF FM 41
CSJ0068-01-074
Proj IDC 68-1-74
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.00021657408.6114059354.6964.9
Work Order09-20-21
Work Began10-11-21
Work Completed
Time Computed10-11-21
Contract Working Days547
Addl Days Granted5
Working Days Charged546
Percent Time Used98
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-01-074
J. H. ODEN CONTRACTING COMPANY (0.12)
BARRICADES UNLIMITED (0.95)
ARTEX ELECTRIC, INC. (1.26)
INDUSTRIAL FABRICS, INC. (1.35)
PRIMATE CONSTRUCTION, LP (0.05)
SCOTT DERR PAINTING CO, LLC (0.04)
TEXOP CONSTRUCTION (0.74)
WAYNE BRYANT TRANSPORT, LLC. (1.27)
D & E LOGISTICS, LLC (3.66)
K.A. FARMER TRUCKING, INC. (0.12)
URBAN INFRACONSTRUCTION LLC (4.83)
TORO BRAVO CONSTRUCTION, LLC (0.57)
KELLER NORTH AMERICA, INC. (0.59)
PINNACLE GRINDING AND GROOVING LLC (0.02)
WESTEX COOPERATIVE GIN (0.03)
JRS UNLIMITED, LLC (0.03)
MARKS CRANE & RIGGING (0.19)
DE NOVO TRUCKING, LLC (0.04)
GORMAN OUTDOOR, INC. (0.01)
Contract #08213209
Totals21657408.610.0014059354.6964.9

CountyDAWSON
HighwayUS 87
FromCR 1026
ToUS 180
CSJ0068-05-040
Proj IDC 68-5-40
Work TypeWIDEN NON-FREEWAY
 
14793665.350.000.0
Work Order05-08-24
Work Began00-00-00
Work Completed
Time Computed07-07-24
Contract Working Days236
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-05-040
BARRICADES UNLIMITED (0.45)
W. S. CONSTRUCTION COMPANY (4.43)
A BROTHERS MILLING, LLC (0.56)
APOLLO CONSTRUCTORS, INC. (5.65)
HJC FARMS, INC. (0.67)
INDUSTRIAL FABRICS, INC. (1.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TRP CONSTRUCTION GROUP, LLC (2.78)
JVH4 SERVICES, LLC (0.22)
Contract #04243041
Totals14793665.350.000.000.0

CountyHOCKLEY
HighwaySH 114
FromUS 385
ToLUBBOCK COUNTY LINE
CSJ0130-04-035
Proj IDSTP 2022(894)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
16.605840659.00747773.8093.4
CountyLAMB
HighwayFM 168
From14TH STREET IN OLTON
ToFM 54
CSJ0874-03-016
Proj IDSTP 2022(894)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
17.6261049671.00958541.0091.3
Work Order09-28-22
Work Began11-28-22
Work Completed
Time Computed10-28-22
Contract Working Days165
Addl Days Granted0
Working Days Charged213
Percent Time Used129
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0130-04-035
FC TRAFFIC CONTROL, INC. (0.98)
VALLEY CONSTRUCTION, LLC (25.70)
BARRICADES UNLIMITED (0.29)
ROCK HILL INDUSTRIAL LLC (1.77)
Contract #08223025
Totals1890330.0020931.001706314.8092.2

CountyLUBBOCK
HighwayUS 62
FromMEMPHIS AVE
ToIH-27
CSJ0130-05-085
Proj IDC 130-5-85
Work TypeRESTORATION
 
3.10025690813.0015844054.0861.6
Work Order03-16-22
Work Began06-23-22
Work Completed
Time Computed06-13-22
Contract Working Days656
Addl Days Granted6
Working Days Charged517
Percent Time Used78
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 0130-05-085
BARRICADES UNLIMITED (3.45)
ARTEX ELECTRIC, INC. (11.31)
LMN TRANSPORT (0.00)
DUSTROL, INC. (1.18)
INDUSTRIAL FABRICS, INC. (0.77)
EAST TEXAS R&D SERVICES, INC. (0.03)
UTILITY CONTRACTORS OF AMERICA, INC. (0.01)
FIBERTEX, LLC (0.07)
FIBERTEX, LLC (0.57)
TRP CONSTRUCTION GROUP, LLC (3.11)
WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.97)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.01)
COBB, FENDLEY & ASSOCIATES, INC. (0.76)
DEERWOOD CONSTRUCTION, INC. (3.86)
MAKO MIX ENTERPRISE, LLC (0.03)
Contract #02223201
Totals25690813.001112429.7515844054.0861.6

CountyLUBBOCK
HighwayUS 62
FromINTERSECTION OF US0062
ToAND MLK JR. BLVD
CSJ0130-05-089
Proj IDSTP 2023(765)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001340196.25321186.2594.4
Work Order07-19-23
Work Began03-18-24
Work Completed
Time Computed10-17-23
Contract Working Days32
Addl Days Granted0
Working Days Charged26
Percent Time Used81
Contractor(s)
APOLLO CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0130-05-089
BARRICADES UNLIMITED (0.82)
Contract #06233253
Totals340196.250.00321186.2594.4

CountyHOCKLEY
HighwayUS 385
FromSH 114
ToBS 114B (HOUSTON ST.)
CSJ0130-07-033
Proj IDC 130-7-33
Work TypeREHABILITATION OF EXISTING ROAD
 
3994251.709182180.1299.9
CountyHOCKLEY
HighwayUS 385
FromBRAZIL COUNTY ROAD
ToELLIS STREET
CSJ0227-05-023
Proj IDC 227-5-23
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7535369.090.000.0
CountyHOCKLEY
HighwayUS 385
FromBS 114B (HOUSTON ST.)
ToFM 300
CSJ0227-12-012
Proj IDC 227-12-12
Work TypeREHABILITATION OF EXISTING ROAD
 
6050073.200.000.0
Work Order05-03-24
Work Began07-02-24
Work Completed
Time Computed07-02-24
Contract Working Days136
Addl Days Granted0
Working Days Charged71
Percent Time Used52
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0130-07-033
BARRICADES UNLIMITED (0.33)
DK CONTRACTING, LLC (0.30)
INDUSTRIAL FABRICS, INC. (2.30)
LMN TRANSPORT (0.85)
LMSE TRUCKING, LLC (0.28)
TEX OP CONSTRUCTION, LP (1.50)
TRP CONSTRUCTION GROUP, LLC (2.26)
V-TECH ENVIROMENTAL SERVICES (0.16)
W. S. CONSTRUCTION COMPANY (2.86)
Contract #03243203
Totals17579693.992889790.089182180.1252.2

CountyPARMER
HighwayUS 60
FromNEW MEXICO STATE LINE
To5.3 MILES WEST OF BOVINA
CSJ0168-01-030
Proj IDNH 2019(611)
Work TypePLANING,CEMENT TREAT,TYPE B MIX,SMA
 
7.34225525377.9621765775.6390.7
Work Order07-16-19
Work Began03-18-20
Work Completed
Time Computed09-14-19
Contract Working Days277
Addl Days Granted10
Working Days Charged830
Percent Time Used289
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0168-01-030
FC TRAFFIC CONTROL, INC. (0.05)
TEXOP CONSTRUCTION (1.17)
MARCOM"S MOWING SERVICE, LLC (0.25)
J. H. ODEN CONTRACTING COMPANY (0.07)
PMI PAVEMENT MARKING, LLC (1.72)
BLACKTOP INDUSTRIES LLC (0.05)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.21)
HERITAGE MATERIALS, LLC (3.79)
H & F TRUCKING (0.35)
DTM TRUCKING, INC. (2.13)
HJC FARMS, INC. (0.08)
BUTCH"S RAT HOLE & ANCHOR SERVICE, INC. (0.17)
FLAT LINE, INC. (1.68)
EAGLE CONSTRUCTION LLC (1.56)
LMN TRANSPORT (0.19)
BARRICADES UNLIMITED (1.16)
BIG R TRUCKING TX LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
INDUSTRIAL FABRICS, INC. (5.70)
Contract #03193202
Totals25525377.961050722.9421765775.6390.7

CountyPARMER
HighwayUS 60
FromCR 13
ToCR 17
CSJ0168-02-032
Proj IDC 168-2-32
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
2.00069925101.4619204615.3327.4
Work Order02-28-24
Work Began04-15-24
Work Completed
Time Computed04-01-24
Contract Working Days721
Addl Days Granted0
Working Days Charged123
Percent Time Used17
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-02-032
A BROTHERS MILLING, LLC (0.35)
APOLLO CONSTRUCTORS, INC. (1.41)
FC TRAFFIC CONTROL, INC. (0.08)
HJC FARMS, INC. (0.68)
J & M CONTRACTING, COMPANY (0.92)
J. LEE MILLIGAN, INC. (29.67)
LMSE TRUCKING, LLC (3.17)
PRIMATE CONSTRUCTION, LP (0.02)
PROFESSIONAL TRAFFIC CONTROL LLC (0.02)
S & S BRIDGE PAINTING, INC. (0.07)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.41)
TRP CONSTRUCTION GROUP, LLC (0.66)
AMERICAN CONCRETE TRUCKING, LLC (0.12)
CABELLO CONSTRUCTION LLC (0.17)
TORO BRAVO CONSTRUCTION, LLC (0.52)
ADRIAN CONTRACTING, INC (0.05)
PANHANDLE STEEL ERECTORS (0.30)
GORMAN OUTDOOR, INC. (0.02)
Contract #10233003
Totals69925101.464193158.2119204615.3327.4

CountyCASTRO
HighwayUS 385
FromDEAF SMITH COUNTY LINE
ToRAILROAD TRACKS
CSJ0226-06-036
Proj IDC 226-6-36
Work TypeSUPER-2 HIGHWAY
 
20.97854353806.7316794800.2930.8
Work Order05-16-24
Work Began05-20-24
Work Completed
Time Computed05-20-24
Contract Working Days288
Addl Days Granted0
Working Days Charged100
Percent Time Used34
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0226-06-036
A BROTHERS MILLING, LLC (0.16)
ARTEX ELECTRIC, INC. (0.47)
BARRICADES UNLIMITED (0.11)
HJC FARMS, INC. (0.15)
INDUSTRIAL FABRICS, INC. (7.22)
JR WEST TEXAS CONCRETE LLC (4.96)
LMSE TRUCKING, LLC (0.45)
MURRAY CONSTRUCTION (0.52)
PROFESSIONAL TRAFFIC CONTROL LLC (0.10)
TRP CONSTRUCTION GROUP, LLC (1.48)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.26)
WITHERS CONSTRUCTION, LLC (0.13)
Contract #02243002
Totals54353806.73174104.4816794800.2930.8

CountyTERRY
HighwayUS 62
FromFM 213 IN WELLMAN
ToBEG OF 4 LN DIVIDED S OF BROWNFIELD
CSJ0228-01-056
Proj IDNH 2017(462)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.69020746921.6913314781.4764.1
CountyTERRY
HighwayUS 62
FromWELLMAN
ToBROWNFIELD
CSJ0228-01-061
Proj IDSTP 2B23(223)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2037985.200.000.0
Work Order11-16-23
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days289
Addl Days Granted12
Working Days Charged165
Percent Time Used54
Contractor(s)
JAMES HAMILTON CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0228-01-056
BARRICADES UNLIMITED (0.38)
A BROTHERS MILLING, LLC (0.62)
BERT WHITAKER (0.04)
SQUARE ROOT SERVICES LLC (0.85)
MURRAY CONSTRUCTION (1.00)
TRP CONSTRUCTION GROUP, LLC (2.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.64)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
NM AC & COMPANY LLC (2.08)
INDUSTRIAL FABRICS, INC. (5.59)
ROADWAY SPECIALTIES, INC. (8.12)
Contract #09233205
Totals22784906.89617505.3213314781.4758.4

page 1 | page 2