Monthly State Let Construction Report For Lubbock District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTERRY
HighwayUS 62
FromGAINES COUNTY LINE
To1559.2 FT NORTH OF GAINES COUNTY LINE
CSJ0228-01-058
Proj IDC 228-1-58
Work TypeREHABILITATION OF EXISTING ROAD
 
2.57518670289.1613817330.9672.8
Work Order03-16-23
Work Began07-06-23
Work Completed
Time Computed04-17-23
Contract Working Days393
Addl Days Granted17
Working Days Charged269
Percent Time Used65
Contractor(s)
JAMES HAMILTON CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0228-01-058
FC TRAFFIC CONTROL, INC. (0.47)
INDUSTRIAL FABRICS, INC. (3.12)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
WILLIAMS ROAD, LLC (1.09)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.11)
Z-TEK CONSTRUCTION, LLC (4.90)
NM AC & COMPANY LLC (1.65)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.91)
W. S. CONSTRUCTION COMPANY (16.44)
Contract #01233004
Totals18670289.16371381.0013817330.9672.8

CountyTERRY
HighwayUS 62
FromSOUTHWEST WELLMAN CITY LIMITS
ToFM 303 N
CSJ0228-01-062
Proj IDF 2024(427)
Work TypeREHABILITATION OF EXISTING ROAD
 
11297925.799994850.2988.4
CountyTERRY
HighwayUS 62
FromWELLMAN CITY LIMITS
ToCOUNTY ROAD 835
CSJ0228-01-063
Proj IDBR 2024(428)
Work TypeBRIDGE MAINTENANCE
 
110593.000.000.0
Work Order01-25-24
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days132
Addl Days Granted0
Working Days Charged95
Percent Time Used71
Contractor(s)
JAMES HAMILTON CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0228-01-062
A BROTHERS MILLING, LLC (1.14)
BARRICADES UNLIMITED (0.33)
INDUSTRIAL FABRICS, INC. (7.95)
MOBILE ENTERPRISES, INC. (0.20)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.32)
SQUARE ROOT SERVICES LLC (0.47)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.27)
TRP CONSTRUCTION GROUP, LLC (1.96)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
NM AC & COMPANY LLC (2.08)
MURRAY CONSTRUCTION (0.18)
Contract #12233226
Totals11408518.792175296.059994850.2987.6

CountyYOAKUM ETC
HighwayUS 380 ETC
FromWEST PLAINS CITY LIMITS
ToUS 82
CSJ0297-01-014
Proj IDC 297-1-14
Work TypeREHABILITATION OF EXISTING ROAD
 
6041330.004957358.1182.0
Work Order02-02-24
Work Began06-14-24
Work Completed
Time Computed05-02-24
Contract Working Days59
Addl Days Granted0
Working Days Charged56
Percent Time Used94
Contractor(s)
JAMES HAMILTON CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0297-01-014
A BROTHERS MILLING, LLC (1.70)
BARRICADES UNLIMITED (0.32)
NM AC & COMPANY LLC (2.35)
INDUSTRIAL FABRICS, INC. (12.18)
TRP CONSTRUCTION GROUP, LLC (2.75)
Contract #01243220
Totals6041330.001785216.074957358.1182.0

CountyHALE
HighwaySH 194
FromIH 27
ToFM 3466
CSJ0439-05-026
Proj IDC 439-5-26
Work TypeREHABILITATION OF EXISTING ROAD
 
2.64026114007.110.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days445
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0439-05-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243004
Totals26114007.110.000.000.0

CountyCROSBY
HighwaySH 207
From1109 FT NORTH OF FM 40 EAST
ToGARZA COUNTY LINE
CSJ0453-04-024
Proj IDF 2023(065)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.20023557970.656626018.2628.1
Work Order10-11-22
Work Began02-15-23
Work Completed
Time Computed01-02-23
Contract Working Days492
Addl Days Granted72
Working Days Charged342
Percent Time Used60
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0453-04-024
BARRICADES UNLIMITED (2.27)
HJC FARMS, INC. (2.83)
MARCOM"S MOWING SERVICE, LLC (0.26)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.08)
TEXOP CONSTRUCTION (0.97)
V-TECH ENVIROMENTAL SERVICES (0.60)
WITHERS CONSTRUCTION, LLC (0.14)
W. S. CONSTRUCTION COMPANY (11.56)
TRP CONSTRUCTION GROUP, LLC (1.86)
LMN TRANSPORT (0.21)
Contract #09223024
Totals23557970.65103788.006626018.2628.1

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-112
Proj IDC 905-00-112
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012731558.502508335.9092.1
Work Order01-26-23
Work Began04-26-23
Work Completed
Time Computed04-26-23
Contract Working Days260
Addl Days Granted0
Working Days Charged270
Percent Time Used103
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-112
TRP CONSTRUCTION GROUP, LLC (6.07)
Contract #12223016
Totals2731558.500.002508335.9092.1

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-116
Proj IDC 905-00-116
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011311802.101357078.0999.9
Work Order07-10-23
Work Began08-15-23
Work Completed
Time Computed08-09-23
Contract Working Days85
Addl Days Granted22
Working Days Charged107
Percent Time Used100
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02233029
Totals1311802.1018304.001357078.0999.9

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-120
Proj IDC 905-00-120
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011639160.001164234.2071.0
Work Order03-28-24
Work Began05-06-24
Work Completed
Time Computed04-27-24
Contract Working Days68
Addl Days Granted0
Working Days Charged68
Percent Time Used100
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243032
Totals1639160.000.001164234.2071.0

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-130
Proj IDC 905-00-130
Work TypeTRAFFIC CONTROL DEVICES
 
1783751.601808290.6099.9
Work Order08-01-24
Work Began08-06-24
Work Completed
Time Computed08-06-24
Contract Working Days90
Addl Days Granted0
Working Days Charged50
Percent Time Used55
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-130
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243032
Totals1783751.60421408.801808290.6099.9

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-134
Proj IDBR 2024(179)
Work TypeBRIDGE MAINTENANCE
 
1420057.001377075.8996.9
Work Order02-22-24
Work Began05-01-24
Work Completed
Time Computed04-22-24
Contract Working Days284
Addl Days Granted0
Working Days Charged82
Percent Time Used28
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233217
Totals1420057.009240.001377075.8996.9

CountyLUBBOCK
HighwayVA
FromVARIOUS BRIDGES IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-135
Proj IDF 2B24(570)
Work TypeBRIDGE MAINTENANCE
 
2795872.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days391
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243223
Totals2795872.300.000.000.0

CountyLUBBOCK
HighwayCS
FromUPLAND AVENUE, FROM 66TH STREET
To82ND STREET
CSJ0905-06-095
Proj IDSTP 2019(518)MM
Work TypeWIDEN NON-FREEWAY
 
19074046.675705997.8629.9
Work Order05-03-24
Work Began06-03-24
Work Completed
Time Computed06-03-24
Contract Working Days304
Addl Days Granted0
Working Days Charged85
Percent Time Used27
Contractor(s)
LONE STAR DIRT & PAVING, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-095
ALAMO BROTHERS CONCRETE INC (2.03)
ARTEX ELECTRIC, INC. (5.62)
FC TRAFFIC CONTROL, INC. (0.19)
LMN TRANSPORT (1.23)
TRP CONSTRUCTION GROUP, LLC (1.52)
TORO BRAVO CONSTRUCTION, LLC (0.84)
BUILDER"S ENVIRONMENTAL SERVICES, LLC (0.25)
FIBERTEX, LLC (0.26)
Contract #02243239
Totals19074046.67373245.855705997.8629.9

CountyLUBBOCK
HighwayCR
FromWOODROW ROAD, FROM INDIANA AVENUE
ToUS 87
CSJ0905-06-116
Proj IDSTP 2020(122)MM
Work TypeWIDEN NON-FREEWAY
 
37998646.4011022723.5229.0
Work Order07-26-23
Work Began10-30-23
Work Completed
Time Computed08-25-23
Contract Working Days726
Addl Days Granted10
Working Days Charged211
Percent Time Used28
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-116
FC TRAFFIC CONTROL, INC. (0.18)
DK CONTRACTING, LLC (0.15)
ACT SAW CUTTING & REMOVAL (0.08)
ARTEX ELECTRIC CO. (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.34)
USA WESTERN LOGISTICS (7.49)
A BROTHERS MILLING, LLC (0.23)
LONE STAR DIRT & PAVING, LTD. (11.18)
ARTEX ELECTRIC, INC. (1.09)
TORO BRAVO CONSTRUCTION, LLC (0.21)
LMSE TRUCKING, LLC (0.13)
Contract #06233457
Totals37998646.401387055.5711022723.5229.0

CountyLUBBOCK
HighwayCS
FromQUAKER AVE
ToINDIANA AVE
CSJ0905-06-118
Proj IDSTP 2021(423)MM
Work TypeWIDEN NON-FREEWAY
 
1.00012797068.2812797076.9799.9
Work Order09-15-22
Work Began10-10-22
Work Completed
Time Computed10-10-22
Contract Working Days256
Addl Days Granted123
Working Days Charged379
Percent Time Used100
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-118
DUSTROL, INC. (0.51)
BARRICADES UNLIMITED (0.15)
FC TRAFFIC CONTROL, INC. (0.64)
WAYNE BRYANT TRANSPORT, LLC. (0.39)
TORO BRAVO CONSTRUCTION, LLC (1.15)
PRIMATE CONSTRUCTION, LP (0.45)
WESTEX COOPERATIVE GIN (0.14)
DE NOVO TRUCKING, LLC (0.31)
ARTEX ELECTRIC, INC. (5.36)
TRP CONSTRUCTION GROUP, LLC (1.88)
GORMAN OUTDOOR, INC. (0.00)
(INACTIVE)HD WEAVER, INC. (0.00)
WESTON DRILLING, INC. (0.05)
SOUTHWEST CONTRACTING AND CONSTRUCTION (4.88)
E&E IRRIGATION & LANDSCAPING (0.90)
LONE STAR DIRT & PAVING, LTD. (17.82)
VACA UNDERGROUND UTILITIES INC (4.65)
H. D. WEAVER DITCHING SERVICE, INC. (0.99)
STRAIGHT LINE SAWING & SEALING, INC. (0.35)
Contract #06223613
Totals12797068.284070.7512797076.9799.9

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS INSIDE
ToOF LUBBOCK LOOP 289
CSJ0905-06-120
Proj IDSTP 2023(034)TP
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1201509.001168624.7797.2
Work Order12-27-23
Work Began02-12-24
Work Completed
Time Computed02-06-24
Contract Working Days200
Addl Days Granted0
Working Days Charged134
Percent Time Used67
Contractor(s)
STX CIVIL
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-120
ARTEX ELECTRIC, INC. (38.88)
FC TRAFFIC CONTROL, INC. (2.04)
FIBERTEX, LLC (3.69)
Contract #11233020
Totals1201509.00102844.001168624.7797.2

CountyLUBBOCK
HighwayCS
FromINDIAN TRAIL
ToAT BUFFALO LAKE SPILLWAY
CSJ0905-06-126
Proj IDBR 2024(658)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
267401.00211308.9584.8
Work Order02-15-24
Work Began04-01-24
Work Completed
Time Computed03-16-24
Contract Working Days29
Addl Days Granted0
Working Days Charged54
Percent Time Used186
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-126
BARRICADES UNLIMITED (1.73)
ONE WAY CONCRETE CONSTRUCTION, LLC (50.86)
Contract #01243041
Totals267401.002954.00211308.9584.8

CountyHALE
HighwayVA
FromVARIOUS LOCATIONS IN
ToHALE COUNTY
CSJ0905-12-045
Proj IDC 905-12-45
Work TypeREHABILITATION OF EXISTING ROAD
 
1747472.000.000.0
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed09-30-24
Contract Working Days146
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243037
Totals1747472.000.000.000.0

CountyCROSBY
HighwayFM 261
From2.5 MILES EAST OF FM 3385
To2.747 MILES EAST OF FM 3385
CSJ0949-02-011
Proj IDBR 2023(565)
Work TypeBRIDGE REPLACEMENT
 
7482764.606011875.4480.3
Work Order04-26-23
Work Began10-16-23
Work Completed
Time Computed05-26-23
Contract Working Days289
Addl Days Granted0
Working Days Charged212
Percent Time Used73
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0949-02-011
LANCO TURF & SEEDING, INC. (0.33)
FC TRAFFIC CONTROL, INC. (0.21)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.35)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.52)
TORO BRAVO CONSTRUCTION, LLC (0.70)
TRP CONSTRUCTION GROUP, LLC (0.65)
TORO BRAVO CONSTRUCTION, LLC (0.17)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.69)
Contract #03233214
Totals7482764.608000.006011875.4480.3

CountyLUBBOCK
HighwayFM 1585
FromMEMPHIS AVE
ToCR 2240 (AVE U)
CSJ1502-01-029
Proj IDSTP 2021(576)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
2.03483284145.9473733105.6588.3
CountyLUBBOCK
HighwayFM 1585
FromCHICAGO
ToMEMPHIS AVE
CSJ1502-01-030
Proj IDSTP 2021(576)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
1.91071589219.0644296093.6761.8
Work Order07-28-21
Work Began11-01-21
Work Completed
Time Computed10-26-21
Contract Working Days1,031
Addl Days Granted23
Working Days Charged635
Percent Time Used60
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 1502-01-029
BARRICADES UNLIMITED (1.35)
LONE STAR EROSION CONTROL (0.23)
A&J REBAR LLC (0.62)
LMN TRANSPORT (0.03)
DK CONTRACTING, LLC (0.28)
R&E DRAINAGE CONSTRUCTION (2.56)
UTILITY CONTRACTORS OF AMERICA, LTD (2.36)
L&H ELECTRICAL, LLC (5.40)
VECTOR UTILITIES LLC (0.19)
TORO BRAVO CONSTRUCTION, LLC (0.00)
BIG BEND SERVICES, LLC (0.04)
FARR FOUNDATION, INC. (1.05)
DUSTROL, INC. (0.21)
TORO BRAVO CONSTRUCTION, LLC (0.06)
HASS CO, LLC (0.27)
VIGO CONSTRUCTION GROUP, INC. (1.59)
TRP CONSTRUCTION GROUP, LLC (1.26)
WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.14)
STRAIGHT LINE SAWING & SEALING, INC. (0.05)
ARTEX ELECTRIC, INC. (1.92)
J. RUEDAS TRUCKING, LLC (0.05)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.03)
FIBERTEX, LLC (0.47)
COLLIER SERVICES LLC (0.05)
UTILITY CONTRACTORS OF AMERICA, INC. (2.36)
MAKO MIX ENTERPRISE, LLC (0.32)
BIG TRIBE SERVICES, LLC (1.22)
MKS CONSTRUCTION, LLC (0.96)
JORDAN"S POWER SWEEP (0.06)
Contract #06213201
Totals154873365.009224498.56118029199.3276.1

page 1 | page 2