Monthly State Let Construction Report For Lubbock District As Of Sep 13, 2021 Page 2 Of 2

Last Update: Wednesday, September 15, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySWISHER
HighwayFM 2301
From1.0 MILE NORTH OF SH 86
To0.92 MILE NORTH OF SH 86
CSJ0789-04-006
Proj IDBR 2020(862)
Work TypeBRIDGE REPLACEMENT
 
0.0081543187.50798349.4951.7
Work Order07-13-20
Work Began08-04-20
Work Completed
Time Computed08-04-20
Contract Working Days178
Addl Days Granted0
Working Days Charged134
Percent Time Used75
Contractor(s)
BLACKSTONE CONCRETE VENTURES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0789-04-006
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.68)
DRILL PIER CONSTRUCTION, LLC (1.34)
Contract #05203230
Totals1543187.5020625.00798349.4951.7

CountyLUBBOCK
HighwayFM 179
From800 FT NORTH OF SH 114
ToDONALD PRESTON DR.
CSJ0880-04-032
Proj IDSTP 2013(649)
Work TypeGRADE, BASE, ACP
 
4.15318836295.2518598200.2498.9
Work Order04-02-19
Work Began04-16-19
Work Completed
Time Computed04-16-19
Contract Working Days463
Addl Days Granted0
Working Days Charged493
Percent Time Used106
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0880-04-032
BARRICADES UNLIMITED (2.29)
BUILDER"S ENVIRONMENTAL SERVICES, LLC (0.60)
A BROTHERS MILLING, LLC (0.16)
ARTEX ELECTRIC, INC. (1.99)
BLACKTOP INDUSTRIES LLC (0.77)
BO SIMON INC (2.78)
INDUSTRIAL FABRICS, INC. (4.11)
SAENZ TRANSPORT, LLC (2.23)
SEALS COMMERCIAL CONCRETE, LLC (1.51)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.20)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
WAYNE BRYANT LOGISTICS, LLC (0.02)
LMN TRANSPORT (0.19)
DTM TRUCKING, INC. (0.05)
GORMAN OUTDOOR, INC. (0.00)
K.A. FARMER TRUCKING, INC. (0.05)
D & E LOGISTICS, LLC (0.13)
DIIBS SPECIALISTS, LLC (0.28)
Contract #02193003
Totals18836295.2528416.1718598200.2498.9

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToLUBBOCK DISTRICT
CSJ0905-00-081
Proj IDSTP 2020(750)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011723006.001597612.4093.7
Work Order06-09-20
Work Began09-02-20
Work Completed
Time Computed08-08-20
Contract Working Days85
Addl Days Granted0
Working Days Charged107
Percent Time Used125
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04203024
Totals1723006.0020.001597612.4093.7

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-093
Proj IDC 905-00-93
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011705956.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213006
Totals1705956.000.000.000.0

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-100
Proj IDC 905-00-100
Work TypeTRAFFIC CONTROL DEVICES
 
0.001355560.378130.002.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-02-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-100
CONCRETE CONNECTION, LLC (0.00)
Contract #06213239
Totals355560.378130.008130.002.2

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-103
Proj IDC 905-00-103
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012185433.47213278.709.7
Work Order03-19-21
Work Began06-08-21
Work Completed
Time Computed04-19-21
Contract Working Days90
Addl Days Granted0
Working Days Charged26
Percent Time Used28
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02213217
Totals2185433.47167406.20213278.709.7

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-110
Proj IDC 905-00-110
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.0014034018.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days408
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213220
Totals4034018.840.000.000.0

CountyLUBBOCK
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ0905-00-122
Proj IDC 905-00-122
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011923911.471898398.5898.6
Work Order04-08-21
Work Began05-14-21
Work Completed
Time Computed05-10-21
Contract Working Days70
Addl Days Granted0
Working Days Charged48
Percent Time Used68
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-122
FLAT LINE, INC. (16.21)
Contract #03213215
Totals1923911.4781174.211898398.5898.6

CountySWISHER
HighwayCR
From0.23 MILES SOUTH OF FM 1318
To0.25 MILES SOUTH OF FM 1318
CSJ0905-17-016
Proj IDBR 2020(305)
Work TypeBRIDGE REPLACEMENT
 
552000.00581926.5099.9
Work Order10-07-20
Work Began12-10-20
Work Completed
Time Computed12-06-20
Contract Working Days165
Addl Days Granted0
Working Days Charged91
Percent Time Used55
Contractor(s)
BLACKSTONE CONCRETE VENTURES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-17-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203025
Totals552000.004091.50581926.5099.9

CountyCROSBY
HighwayCR
From3.7 MILES EAST OF SH 207
To3.69 MILES EAST OF SH 207
CSJ0905-21-004
Proj IDBR 2019(810)
Work TypeBRIDGE REPLACEMENT
 
795162.000.000.0
CountyCROSBY
HighwayCR
From6.49 MILES EAST OF SH 207
To6.48 MILES EAST OF SH 207
CSJ0905-21-005
Proj IDBR 2019(802)
Work TypeBRIDGE REPLACEMENT
 
527142.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days213
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0905-21-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213050
Totals1322304.000.000.000.0

CountyLUBBOCK
HighwayFM 1585
FromMEMPHIS AVE
ToCR 2240 (AVE U)
CSJ1502-01-029
Proj IDSTP 2021(576)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
2.03483284145.940.000.0
CountyLUBBOCK
HighwayFM 1585
FromCHICAGO
ToMEMPHIS AVE
CSJ1502-01-030
Proj IDSTP 2021(576)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
1.91071589219.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-28-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,031
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 1502-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213201
Totals154873365.000.000.000.0

page 1 | page 2