Monthly State Let Maintenance Report For Lubbock District As Of Nov 10, 2024 Page 2 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6447-58-001
Proj IDBPM - 644758001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101699846.00616171.0036.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged25
Percent Time Used10
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244226
Totals1699846.00616171.00616171.0036.2

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6448-07-001
Proj IDRMC - 644807001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010363640.00318135.0087.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234026
Totals363640.0027777.00318135.0087.4

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6448-09-001
Proj IDRMC - 644809001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010334615.0073271.0021.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234027
Totals334615.003511.0073271.0021.8

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6448-11-001
Proj IDRMC - 644811001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101048565.002205095.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234211
Totals1048565.00147189.002205095.0099.9

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6448-13-001
Proj IDRMC - 644813001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010249070.00773612.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234212
Totals249070.0011401.10773612.8099.9

CountyLUBBOCK
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6451-53-001
Proj IDRMC - 645153001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010372420.00166558.0044.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-18-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged319
Percent Time Used43
Contractor(s)
MARLANE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234213
Totals372420.0035403.00166558.0044.7

CountyLUBBOCK
HighwayFM2255
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-55-001
Proj IDRMC - 645155001
Work TypeCULVERT REPAIR
 
0.010258006.80488119.7299.9
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed07-01-24
Contract Working Days34
Addl Days Granted0
Working Days Charged57
Percent Time Used167
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-55-001
ONE WAY CONCRETE CONSTRUCTION, LLC (99.99)
Contract #02244008
Totals258006.80385679.72488119.7299.9

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-39-001
Proj IDMMC - 645839001
Work TypeHOT MIX
 
0.010704000.002140297.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234035
Totals704000.00107023.582140297.2999.9

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-75-001
Proj IDRMC - 645875001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010312124.3264178.0220.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-11-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged174
Percent Time Used23
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6458-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244214
Totals312124.320.0064178.0220.5

CountyDAWSON
HighwayUS0087
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-77-001
Proj IDRMC - 645877001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010319620.0079901.0024.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-11-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged174
Percent Time Used23
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6458-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244215
Totals319620.000.0079901.0024.9

CountyGAINES
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-79-001
Proj IDRMC - 645879001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010569820.00160150.0028.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-11-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged82
Percent Time Used11
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6458-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244216
Totals569820.00160150.00160150.0028.1

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6459-39-001
Proj IDRMC - 645939001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.0101785911.50285544.5015.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6459-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244227
Totals1785911.50123557.00285544.5015.9

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-97-001
Proj IDMMC - 646497001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010911200.001203746.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244031
Totals911200.00411979.721203746.5999.9

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-98-001
Proj IDMMC - 646498001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010845995.00379606.5644.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244032
Totals845995.000.00379606.5644.8

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-99-001
Proj IDMMC - 646499001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010307910.0097994.6531.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244033
Totals307910.000.0097994.6531.8

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-00-001
Proj IDMMC - 646500001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010818740.00737107.8990.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244034
Totals818740.00246950.13737107.8990.0

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-04-001
Proj IDMMC - 646504001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010173840.00109192.3862.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6465-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244219
Totals173840.000.00109192.3862.8

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-05-001
Proj IDMMC - 646505001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010433600.001100567.4999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6465-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244220
Totals433600.000.001100567.4999.9

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-06-001
Proj IDMMC - 646506001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010416025.0085173.6620.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged153
Percent Time Used85
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6465-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244221
Totals416025.000.0085173.6620.4

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6468-88-001
Proj IDRMC - 646888001
Work TypeCRACK SEAL
 
0.010458987.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6468-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244008
Totals458987.120.000.000.0

page 1 | page 2 | page 3