Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | NACOGDOCHES |
Highway | US0059 |
From | NACOGDOCHES COUNTY MAINTENANCE |
To | VARIOUS LOCATIONS |
CSJ | 6411-53-001 |
Proj ID | RMC - 641153001 |
Work Type | CABLE BARRIER REPAIR |
|
| 0.010 | 189150.00 | | 335245.00 | 100.0 |
Work Order | 00-00-00 |
Work Began | 10-01-22 |
Work Completed | 11-06-24 |
Time Computed | 10-01-22 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 730 |
Percent Time Used | 100 |
Contractor(s) |
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6411-53-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08224022 |
| Totals | 189150.00 | 0.00 | 335245.00 | 100.0 |
|
County | ANGELINA |
Highway | US0059 |
From | ANGELINA COUNTY |
To | VARIOUS LOCATIONS |
CSJ | 6429-90-001 |
Proj ID | RMC - 642990001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 445235.00 | | 812835.86 | 99.9 |
Work Order | 00-00-00 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 05-01-23 |
Contract Working Days | 57 |
Addl Days Granted | 57 |
Working Days Charged | 81 |
Percent Time Used | 71 |
Contractor(s) |
ACE CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6429-90-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234033 |
| Totals | 445235.00 | 211429.00 | 812835.86 | 99.9 |
|
County | ANGELINA |
Highway | US0059 |
From | VARIOUS LOCATIONS |
To | DISTRICTWIDE |
CSJ | 6443-34-001 |
Proj ID | RMC - 644334001 |
Work Type | THERMOPLASTIC PAVEMENT MARKINGS |
|
| 0.010 | 635450.00 | | 445050.05 | 70.0 |
Work Order | 00-00-00 |
Work Began | 01-09-24 |
Work Completed | |
Time Computed | 01-09-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 297 |
Percent Time Used | 81 |
Contractor(s) |
REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6443-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234028 |
| Totals | 635450.00 | 0.00 | 445050.05 | 70.0 |
|
County | ANGELINA |
Highway | US0059 |
From | ANGELINA COUNTY MAINTENANCE SECTION |
To | VARIOUS LOCATIONS |
CSJ | 6444-10-001 |
Proj ID | RMC - 644410001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1307515.43 | | 1368224.73 | 100.0 |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | 11-06-24 |
Time Computed | 12-01-23 |
Contract Working Days | 39 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 58 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6444-10-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234030 |
| Totals | 1307515.43 | 0.00 | 1368224.73 | 100.0 |
|
County | HOUSTON |
Highway | SH0019 |
From | HOUSTON COUNTY MAINTENANCE SECTION |
To | VARIOUS LOCATIONS |
CSJ | 6444-12-001 |
Proj ID | RMC - 644412001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1188488.45 | | 2618178.34 | 99.9 |
Work Order | 00-00-00 |
Work Began | 01-08-24 |
Work Completed | |
Time Computed | 01-08-24 |
Contract Working Days | 24 |
Addl Days Granted | 9 |
Working Days Charged | 28 |
Percent Time Used | 84 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6444-12-001 STRIPING TECHNOLOGY, L.P. (0.00) DUSTROL, INC. (0.00) INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
|
Contract # | 08234223 |
| Totals | 1188488.45 | 0.00 | 2618178.34 | 99.9 |
|
County | POLK |
Highway | US0059 |
From | SAN JACINTO/POLK MAINT SECTIONS |
To | VARIOUS LOCATIONS |
CSJ | 6447-46-001 |
Proj ID | RMC - 644746001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 716170.00 | | 791424.05 | 99.9 |
Work Order | 00-00-00 |
Work Began | 01-02-24 |
Work Completed | |
Time Computed | 01-02-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 305 |
Percent Time Used | 83 |
Contractor(s) |
AWP SAFETY |
SUBCONTRACTOR(S) FOR CCSJ: 6447-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234207 |
| Totals | 716170.00 | 44492.00 | 791424.05 | 99.9 |
|
County | POLK |
Highway | US0059 |
From | POLK COUNTY MAINTENANCE |
To | VARIOUS LOCATIONS |
CSJ | 6449-57-001 |
Proj ID | RMC - 644957001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 410196.25 | | 271067.89 | 66.0 |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 06-01-24 |
Contract Working Days | 74 |
Addl Days Granted | 0 |
Working Days Charged | 58 |
Percent Time Used | 78 |
Contractor(s) |
ROY LEE WALKER |
SUBCONTRACTOR(S) FOR CCSJ: 6449-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244214 |
| Totals | 410196.25 | 66284.46 | 271067.89 | 66.0 |
|
County | SAN JACINTO |
Highway | US0059 |
From | SAN JACINTO COUNTY MAINTENANCE |
To | VARIOUS LOCATIONS |
CSJ | 6451-35-001 |
Proj ID | RMC - 645135001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 183650.47 | | 184062.02 | 99.9 |
Work Order | 00-00-00 |
Work Began | 06-03-24 |
Work Completed | |
Time Computed | 06-03-24 |
Contract Working Days | 42 |
Addl Days Granted | 0 |
Working Days Charged | 57 |
Percent Time Used | 135 |
Contractor(s) |
ROY LEE WALKER |
SUBCONTRACTOR(S) FOR CCSJ: 6451-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244210 |
| Totals | 183650.47 | 53034.59 | 184062.02 | 99.9 |
|
County | ANGELINA |
Highway | US0059 |
From | VARIOUS LOCATIONS |
To | DISTRICT WIDE |
CSJ | 6451-37-001 |
Proj ID | RMC - 645137001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (LONG LINE) |
|
| 0.010 | 399400.00 | | 128875.40 | 32.2 |
Work Order | 00-00-00 |
Work Began | 01-09-24 |
Work Completed | |
Time Computed | 01-09-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 297 |
Percent Time Used | 81 |
Contractor(s) |
BATTERSON, LLP |
SUBCONTRACTOR(S) FOR CCSJ: 6451-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234213 |
| Totals | 399400.00 | 0.00 | 128875.40 | 32.2 |
|
County | NACOGDOCHES |
Highway | US0059 |
From | NACOGDOCHES COUNTY MAINTENANCE |
To | VARIOUS LOCATIONS |
CSJ | 6451-75-001 |
Proj ID | RMC - 645175001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 272318.18 | | 268502.99 | 98.5 |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 06-01-24 |
Contract Working Days | 56 |
Addl Days Granted | 0 |
Working Days Charged | 32 |
Percent Time Used | 57 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6451-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244009 |
| Totals | 272318.18 | 97593.50 | 268502.99 | 98.5 |
|
County | SHELBY |
Highway | US0059 |
From | SHELBY COUNTY |
To | VARIOUS LOCATIONS |
CSJ | 6452-61-001 |
Proj ID | RMC - 645261001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 239608.19 | | 186066.77 | 82.5 |
Work Order | 04-05-24 |
Work Began | 04-05-24 |
Work Completed | |
Time Computed | 04-05-24 |
Contract Working Days | 50 |
Addl Days Granted | 0 |
Working Days Charged | 62 |
Percent Time Used | 124 |
Contractor(s) |
SERVIN MOWING |
SUBCONTRACTOR(S) FOR CCSJ: 6452-61-001 AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY (0.00)
|
Contract # | 02244010 |
| Totals | 239608.19 | 91994.17 | 186066.77 | 82.5 |
|
County | ANGELINA |
Highway | BU0069J |
From | ANG HOU & TRIN COUNTIES MAINT. YARD |
To | ANG HOU & TRIN COUNTIES MAINT. YARD |
CSJ | 6453-49-001 |
Proj ID | MMC - 645349001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 1066720.00 | | 543697.34 | 50.9 |
Work Order | 00-00-00 |
Work Began | 11-27-23 |
Work Completed | |
Time Computed | 11-27-23 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 340 |
Percent Time Used | 94 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6453-49-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234021 |
| Totals | 1066720.00 | 0.00 | 543697.34 | 50.9 |
|
County | SAN JACINTO |
Highway | US0059 |
From | POLK, SAN JACINTO |
To | VARIOUS LOCATIONS |
CSJ | 6453-67-001 |
Proj ID | RMC - 645367001 |
Work Type | DEBRIS REMOVAL |
|
| 0.010 | 251307.19 | | 526080.63 | 99.9 |
Work Order | 00-00-00 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 02-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 274 |
Percent Time Used | 75 |
Contractor(s) |
AAD CONTRACTING INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-67-001 ROY LEE WALKER (0.00) L & M MOWING CONTRACTORS, LLC (0.00)
|
Contract # | 11234023 |
| Totals | 251307.19 | 59190.24 | 526080.63 | 99.9 |
|
County | ANGELINA |
Highway | US0059 |
From | WITHIN THE LUFKIN DISTRICT |
To | VARIOUS LOCATIONS |
CSJ | 6456-17-001 |
Proj ID | BPM - 645617001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 583220.00 | | 3053169.86 | 99.9 |
Work Order | 00-00-00 |
Work Began | 05-01-24 |
Work Completed | |
Time Computed | 05-01-24 |
Contract Working Days | 60 |
Addl Days Granted | 145 |
Working Days Charged | 90 |
Percent Time Used | 43 |
Contractor(s) |
GARRET SHIELDS INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 6456-17-001 4-HORN TRAFFIC & BARRICADE, LLC (0.00) FARR FOUNDATION, INC. (0.00) STRIPING TECHNOLOGY, L.P. (0.00)
|
Contract # | 11234024 |
| Totals | 583220.00 | 614991.11 | 3053169.86 | 99.9 |
|
County | POLK |
Highway | BU0059J |
From | WITHIN THE LUFKIN DISTRICT |
To | VARIOUS LOCATIONS |
CSJ | 6456-19-001 |
Proj ID | BPM - 645619001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 330272.00 | | 529657.30 | 99.9 |
Work Order | 00-00-00 |
Work Began | 06-03-24 |
Work Completed | |
Time Computed | 06-03-24 |
Contract Working Days | 45 |
Addl Days Granted | 25 |
Working Days Charged | 28 |
Percent Time Used | 40 |
Contractor(s) |
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234214 |
| Totals | 330272.00 | 142928.25 | 529657.30 | 99.9 |
|
County | HOUSTON |
Highway | US0287 |
From | HOUSTON COUNTY |
To | VARIOUS LOCATIONS |
CSJ | 6460-42-001 |
Proj ID | RMC - 646042001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 274421.42 | | 249487.84 | 90.9 |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 06-01-24 |
Contract Working Days | 52 |
Addl Days Granted | 0 |
Working Days Charged | 34 |
Percent Time Used | 65 |
Contractor(s) |
SERVIN MOWING |
SUBCONTRACTOR(S) FOR CCSJ: 6460-42-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244026 |
| Totals | 274421.42 | 25608.24 | 249487.84 | 90.9 |
|
County | ANGELINA |
Highway | SH0007 |
From | VARIOUS ROADWAYS IN HOUSTON, |
To | TRINITY AND ANGELINA MAINT SECTIONS |
CSJ | 6462-57-001 |
Proj ID | RMC - 646257001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1289920.00 | | 683471.25 | 52.9 |
Work Order | 00-00-00 |
Work Began | 05-01-24 |
Work Completed | |
Time Computed | 05-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 184 |
Percent Time Used | 50 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244230 |
| Totals | 1289920.00 | 164453.50 | 683471.25 | 52.9 |
|
County | SHELBY |
Highway | SH0007 |
From | SHEL/NAC/SAB/SA COUNTIES |
To | VARIOUS LOCATIONS |
CSJ | 6464-59-001 |
Proj ID | RMC - 646459001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1030325.00 | | 661681.75 | 64.2 |
Work Order | 05-22-24 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 06-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 153 |
Percent Time Used | 41 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6464-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244034 |
| Totals | 1030325.00 | 117398.50 | 661681.75 | 64.2 |
|
County | SHELBY |
Highway | US0059 |
From | SHELBY COUNTY MAINTENANCE SECTION |
To | VARIOUS LOCATIONS |
CSJ | 6466-25-001 |
Proj ID | RMC - 646625001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 717798.97 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-23-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 11-01-24 |
Contract Working Days | 20 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6466-25-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244210 |
| Totals | 717798.97 | 0.00 | 0.00 | 0.0 |
|
County | SAN JACINTO |
Highway | US0059 |
From | ANGELINA COUNTY MAINTENANCE SECTION |
To | VARIOUS LOCATIONS |
CSJ | 6466-35-001 |
Proj ID | RMC - 646635001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 1073614.30 | | 0.00 | 0.0 |
Work Order | 00-00-00 |
Work Began | 10-22-24 |
Work Completed | |
Time Computed | 10-22-24 |
Contract Working Days | 44 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6466-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244029 |
| Totals | 1073614.30 | 0.00 | 0.00 | 0.0 |
|