Monthly State Let Maintenance Report For Lufkin District As Of Jul 13, 2021 Page 1 Of 1

Last Update: Friday, July 16, 2021
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN NACOGDOCHES,SABINE,
ToSAN AUGUSTINE AND SHELBY MAINT SECTIONS
CSJ6349-12-001
Proj IDRMC - 634912001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0101293555.241725664.5599.9
Work Order10-31-19
Work Began11-01-19
Work Completed
Time Computed11-01-19
Contract Working Days365
Addl Days Granted365
Working Days Charged608
Percent Time Used83
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194214
Totals1293555.24157488.901725664.5599.9

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN POLK AND
ToSAN JACINTO MAINTENANCE SECTIONS
CSJ6349-13-001
Proj IDRMC - 634913001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.010520270.28578538.4499.9
Work Order00-00-00
Work Began11-15-19
Work Completed
Time Computed11-15-19
Contract Working Days365
Addl Days Granted365
Working Days Charged594
Percent Time Used81
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194215
Totals520270.2852226.50578538.4499.9

CountyANGELINA
HighwayUS0059
FromANGELINA, NACOGDOCHES & SHELBY COUNTIES
ToVARIOUS LOCATIONS
CSJ6353-47-001
Proj IDRMC - 635347001
Work TypeMILL AND INLAY
 
0.010939518.46885680.6094.2
Work Order10-12-20
Work Began11-01-20
Work Completed
Time Computed11-01-20
Contract Working Days30
Addl Days Granted0
Working Days Charged18
Percent Time Used60
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6353-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07204008
Totals939518.460.00885680.6094.2

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO,TRINITY AND HOUSTON COUNTIES
ToVARIOUS LOCATIONS
CSJ6353-48-001
Proj IDRMC - 635348001
Work TypeOVERLAY & MILL AND INLAY
 
0.0101721052.241703045.9898.9
Work Order00-00-00
Work Began10-07-20
Work Completed
Time Computed10-08-20
Contract Working Days40
Addl Days Granted0
Working Days Charged36
Percent Time Used90
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6353-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07204215
Totals1721052.240.001703045.9898.9

CountyTRINITY
HighwaySH0019
FromVARIOUS ROADWAYS IN TRINITY,
ToHOUSTON AND ANGELINA MAINT SECTIONS
CSJ6355-20-001
Proj IDRMC - 635520001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0011156905.101492123.3799.9
Work Order04-29-20
Work Began05-15-20
Work Completed
Time Computed05-15-20
Contract Working Days365
Addl Days Granted365
Working Days Charged412
Percent Time Used56
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6355-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204202
Totals1156905.10108526.261492123.3799.9

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE
ToSAN JACINTO COUNTY MAINTENANCE
CSJ6361-08-001
Proj IDMMC - 636108001
Work TypeHOT MIX ASPHALT TY C & D (MATERIAL ONLY)
 
0.001516880.00263505.2550.9
Work Order00-00-00
Work Began09-20-20
Work Completed
Time Computed09-20-20
Contract Working Days120
Addl Days Granted131
Working Days Charged251
Percent Time Used100
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6361-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204217
Totals516880.000.00263505.2550.9

CountyNACOGDOCHES
HighwaySL0224
FromNACOGDOCHES COUNTY MAINTENANCE YARD
ToNACOGDOCHES COUNTY MAINTENANCE YARD
CSJ6361-11-001
Proj IDMMC - 636111001
Work TypeHOT MIX ASPHALT TY B,C&D (MATERIAL ONLY)
 
0.001460500.001402887.2499.9
Work Order09-03-20
Work Began09-03-20
Work Completed
Time Computed09-03-20
Contract Working Days120
Addl Days Granted240
Working Days Charged301
Percent Time Used83
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6361-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204214
Totals460500.00469356.211402887.2499.9

CountySABINE
HighwayFM0083
FromSABINE COUNTY MAINTENANCE YARD
ToSABINE COUNTY MAINTENANCE YARD
CSJ6361-17-001
Proj IDMMC - 636117001
Work TypeHOT MIX ASPHALT TY B & F (MATERIAL ONLY)
 
0.001530250.00240418.0845.3
Work Order08-06-20
Work Began08-10-20
Work Completed
Time Computed08-10-20
Contract Working Days120
Addl Days Granted240
Working Days Charged325
Percent Time Used90
Contractor(s)
EAST TEXAS ASPHALT CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6361-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204216
Totals530250.00189366.48240418.0845.3

CountySABINE
HighwayFM0083
FromDLVR TO SAB & SAN AUG CO. MAINT. YARD
ToDLVR TO SAB & SAN AUG CO. MAINT. YARD
CSJ6365-72-001
Proj IDMMC - 636572001
Work TypeLIMESTONE ROCK & ASPHALT (MATERIAL ONLY)
 
0.001416560.000.000.0
Work Order10-07-20
Work Began10-07-20
Work Completed
Time Computed10-07-20
Contract Working Days120
Addl Days Granted120
Working Days Charged240
Percent Time Used100
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6365-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204008
Totals416560.000.000.000.0

CountyTRINITY
HighwaySH0019
FromTRINITY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6379-85-001
Proj IDRMC - 637985001
Work TypeMILL AND INLAY
 
0.0101653621.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6379-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214208
Totals1653621.730.000.000.0

CountyANGELINA
HighwayBU0069J
FromANG HOU & TRIN COUNTIES MAINT. YARD
ToANG HOU & TRIN COUNTIES MAINT. YARD
CSJ6382-62-001
Proj IDMMC - 638262001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.0101203960.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6382-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214216
Totals1203960.000.000.000.0

CountyNACOGDOCHES
HighwayFM0343
FromNAC AND SAB COUNTY MAINTENANCE YARDS
ToNAC AND SAB COUNTY MAINTENANCE YARD
CSJ6382-69-001
Proj IDMMC - 638269001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010428880.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6382-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214217
Totals428880.000.000.000.0

page 1