Monthly State Let Maintenance Report For Lufkin District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6411-53-001
Proj IDRMC - 641153001
Work TypeCABLE BARRIER REPAIR
 
0.010189150.00335245.00100.0
Work Order00-00-00
Work Began10-01-22
Work Completed11-06-24
Time Computed10-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6411-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224022
Totals189150.000.00335245.00100.0

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6429-90-001
Proj IDRMC - 642990001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010445235.00812835.8699.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days57
Addl Days Granted57
Working Days Charged81
Percent Time Used71
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234033
Totals445235.00211429.00812835.8699.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6443-34-001
Proj IDRMC - 644334001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.010635450.00445050.0570.0
Work Order00-00-00
Work Began01-09-24
Work Completed
Time Computed01-09-24
Contract Working Days365
Addl Days Granted0
Working Days Charged297
Percent Time Used81
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6443-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234028
Totals635450.000.00445050.0570.0

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6444-10-001
Proj IDRMC - 644410001
Work TypeMILL AND INLAY
 
0.0101307515.431368224.73100.0
Work Order00-00-00
Work Began12-01-23
Work Completed11-06-24
Time Computed12-01-23
Contract Working Days39
Addl Days Granted0
Working Days Charged23
Percent Time Used58
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234030
Totals1307515.430.001368224.73100.0

CountyHOUSTON
HighwaySH0019
FromHOUSTON COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6444-12-001
Proj IDRMC - 644412001
Work TypeMILL AND INLAY
 
0.0101188488.452618178.3499.9
Work Order00-00-00
Work Began01-08-24
Work Completed
Time Computed01-08-24
Contract Working Days24
Addl Days Granted9
Working Days Charged28
Percent Time Used84
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-12-001
STRIPING TECHNOLOGY, L.P. (0.00)
DUSTROL, INC. (0.00)
INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
Contract #08234223
Totals1188488.450.002618178.3499.9

CountyPOLK
HighwayUS0059
FromSAN JACINTO/POLK MAINT SECTIONS
ToVARIOUS LOCATIONS
CSJ6447-46-001
Proj IDRMC - 644746001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010716170.00791424.0599.9
Work Order00-00-00
Work Began01-02-24
Work Completed
Time Computed01-02-24
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6447-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234207
Totals716170.0044492.00791424.0599.9

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6449-57-001
Proj IDRMC - 644957001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010410196.25271067.8966.0
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days74
Addl Days Granted0
Working Days Charged58
Percent Time Used78
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6449-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244214
Totals410196.2566284.46271067.8966.0

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6451-35-001
Proj IDRMC - 645135001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010183650.47184062.0299.9
Work Order00-00-00
Work Began06-03-24
Work Completed
Time Computed06-03-24
Contract Working Days42
Addl Days Granted0
Working Days Charged57
Percent Time Used135
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6451-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244210
Totals183650.4753034.59184062.0299.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6451-37-001
Proj IDRMC - 645137001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010399400.00128875.4032.2
Work Order00-00-00
Work Began01-09-24
Work Completed
Time Computed01-09-24
Contract Working Days365
Addl Days Granted0
Working Days Charged297
Percent Time Used81
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6451-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234213
Totals399400.000.00128875.4032.2

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6451-75-001
Proj IDRMC - 645175001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010272318.18268502.9998.5
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days56
Addl Days Granted0
Working Days Charged32
Percent Time Used57
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6451-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244009
Totals272318.1897593.50268502.9998.5

CountySHELBY
HighwayUS0059
FromSHELBY COUNTY
ToVARIOUS LOCATIONS
CSJ6452-61-001
Proj IDRMC - 645261001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010239608.19186066.7782.5
Work Order04-05-24
Work Began04-05-24
Work Completed
Time Computed04-05-24
Contract Working Days50
Addl Days Granted0
Working Days Charged62
Percent Time Used124
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6452-61-001
AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY (0.00)
Contract #02244010
Totals239608.1991994.17186066.7782.5

CountyANGELINA
HighwayBU0069J
FromANG HOU & TRIN COUNTIES MAINT. YARD
ToANG HOU & TRIN COUNTIES MAINT. YARD
CSJ6453-49-001
Proj IDMMC - 645349001
Work TypeLIMESTONE ROCK ASPHALT
 
0.0101066720.00543697.3450.9
Work Order00-00-00
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days120
Addl Days Granted240
Working Days Charged340
Percent Time Used94
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234021
Totals1066720.000.00543697.3450.9

CountySAN JACINTO
HighwayUS0059
FromPOLK, SAN JACINTO
ToVARIOUS LOCATIONS
CSJ6453-67-001
Proj IDRMC - 645367001
Work TypeDEBRIS REMOVAL
 
0.010251307.19526080.6399.9
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
AAD CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-67-001
ROY LEE WALKER (0.00)
L & M MOWING CONTRACTORS, LLC (0.00)
Contract #11234023
Totals251307.1959190.24526080.6399.9

CountyANGELINA
HighwayUS0059
FromWITHIN THE LUFKIN DISTRICT
ToVARIOUS LOCATIONS
CSJ6456-17-001
Proj IDBPM - 645617001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010583220.003053169.8699.9
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed05-01-24
Contract Working Days60
Addl Days Granted145
Working Days Charged90
Percent Time Used43
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6456-17-001
4-HORN TRAFFIC & BARRICADE, LLC (0.00)
FARR FOUNDATION, INC. (0.00)
STRIPING TECHNOLOGY, L.P. (0.00)
Contract #11234024
Totals583220.00614991.113053169.8699.9

CountyPOLK
HighwayBU0059J
FromWITHIN THE LUFKIN DISTRICT
ToVARIOUS LOCATIONS
CSJ6456-19-001
Proj IDBPM - 645619001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010330272.00529657.3099.9
Work Order00-00-00
Work Began06-03-24
Work Completed
Time Computed06-03-24
Contract Working Days45
Addl Days Granted25
Working Days Charged28
Percent Time Used40
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234214
Totals330272.00142928.25529657.3099.9

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6460-42-001
Proj IDRMC - 646042001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010274421.42249487.8490.9
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days52
Addl Days Granted0
Working Days Charged34
Percent Time Used65
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6460-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244026
Totals274421.4225608.24249487.8490.9

CountyANGELINA
HighwaySH0007
FromVARIOUS ROADWAYS IN HOUSTON,
ToTRINITY AND ANGELINA MAINT SECTIONS
CSJ6462-57-001
Proj IDRMC - 646257001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101289920.00683471.2552.9
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed05-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244230
Totals1289920.00164453.50683471.2552.9

CountySHELBY
HighwaySH0007
FromSHEL/NAC/SAB/SA COUNTIES
ToVARIOUS LOCATIONS
CSJ6464-59-001
Proj IDRMC - 646459001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101030325.00661681.7564.2
Work Order05-22-24
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244034
Totals1030325.00117398.50661681.7564.2

CountySHELBY
HighwayUS0059
FromSHELBY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6466-25-001
Proj IDRMC - 646625001
Work TypeMILL AND INLAY
 
0.010717798.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed11-01-24
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6466-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244210
Totals717798.970.000.000.0

CountySAN JACINTO
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6466-35-001
Proj IDRMC - 646635001
Work TypeMILL AND INLAY
 
0.0101073614.300.000.0
Work Order00-00-00
Work Began10-22-24
Work Completed
Time Computed10-22-24
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6466-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244029
Totals1073614.300.000.000.0

page 1 | page 2