Monthly State Let Maintenance Report For Lufkin District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwaySH0103
FromSAN AUG, ANG, NAC, SAB, & SHELBY
ToVARIOUS LOCATIONS
CSJ6469-04-001
Proj IDRMC - 646904001
Work TypeCRACK SEAL
 
0.010609907.60611434.1099.9
Work Order00-00-00
Work Began10-14-24
Work Completed
Time Computed10-14-24
Contract Working Days49
Addl Days Granted0
Working Days Charged12
Percent Time Used24
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244030
Totals609907.60611434.10611434.1099.9

CountyHOUSTON
HighwayUS0287
FromTRINITY, HOUSTON, POLK & SAN JACINTO
ToVARIOUS LOCATIONS
CSJ6469-05-001
Proj IDRMC - 646905001
Work TypeCRACK SEAL
 
0.010359478.74359466.7499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged8
Percent Time Used23
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6469-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244211
Totals359478.74359466.74359466.7499.9

page 1 | page 2