Monthly State Let Maintenance Report For Paris District As Of Jan 10, 2023 Page 1 Of 3

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromUS 82 W
ToUS 271 N
CSJ6203-38-001
Proj IDRMC - 620338001
Work TypeSEAL COAT SHOULDERS/CLEAN & SEAL JOINTS
 
3.560372768.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05104002
Totals372768.260.000.000.0

CountyHUNT
HighwayUS0069
FromVARIOUS LOCATIONS IN HUNT AND
ToRAINS COUNTY
CSJ6355-91-001
Proj IDRMC - 635591001
Work TypeDITCH CLEANING AND RESHAPING_PROJECT
 
0.010324125.00551167.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged579
Percent Time Used79
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6355-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214017
Totals324125.000.00551167.9099.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN PARIS
ToDISTRICT
CSJ6369-87-001
Proj IDRMC - 636987001
Work TypeILLUMINATION MAINTENANCE
 
0.001314750.00219669.2069.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted365
Working Days Charged468
Percent Time Used75
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204019
Totals314750.0014620.00219669.2069.7

CountyHUNT
HighwayIH0030
FromIH 30 THROUGH HUNT, HOPKINS
ToAND FRANKLIN COUNTY
CSJ6374-45-001
Proj IDRMC - 637445001
Work TypeDEBRIS REMOVAL
 
0.010298730.00473045.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted254
Working Days Charged412
Percent Time Used81
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6374-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214017
Totals298730.0019768.50473045.0099.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6381-35-001
Proj IDRMC - 638135001
Work TypeRAISED PAVEMENT MARKERS
 
0.010403212.00439504.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-16-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged472
Percent Time Used64
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6381-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214212
Totals403212.000.00439504.5099.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6385-37-001
Proj IDRMC - 638537001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010334171.00342883.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6385-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214220
Totals334171.009340.00342883.0099.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6388-72-001
Proj IDRMC - 638872001
Work TypePAINT
 
0.0101559210.001420547.2091.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged125
Percent Time Used49
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6388-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214023
Totals1559210.00111513.401420547.2091.1

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6388-73-001
Proj IDRMC - 638873001
Work TypePAINT
 
0.0101536660.00818889.3353.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged90
Percent Time Used35
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6388-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214222
Totals1536660.000.00818889.3353.2

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN
ToGRAYSON COUNTY
CSJ6390-01-001
Proj IDRMC - 639001001
Work TypeDEBRIS REMOVAL
 
0.010467884.00457153.0097.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6390-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214020
Totals467884.0017034.00457153.0097.7

CountyFANNIN
HighwaySH0056
FromVARIOUS LOCATIONS IN
ToFANNIN COUNTY
CSJ6392-70-001
Proj IDRMC - 639270001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010254354.00232666.0091.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted76
Working Days Charged60
Percent Time Used39
Contractor(s)
PREMIER CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214015
Totals254354.0069649.50232666.0091.4

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN
ToGRAYSON AND FANNIN COUNTY
CSJ6392-77-001
Proj IDRMC - 639277001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010321090.38295055.1791.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted53
Working Days Charged48
Percent Time Used45
Contractor(s)
PRESLEY LAND MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214216
Totals321090.380.00295055.1791.8

CountyHOPKINS
HighwayIH0030
FromIH 30 THROUGH
ToHOPKINS, FRANKLIN, AND HUNT COUNTY
CSJ6392-79-001
Proj IDRMC - 639279001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010276283.90276231.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted54
Working Days Charged31
Percent Time Used28
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6392-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214217
Totals276283.900.00276231.9099.9

CountyRAINS
HighwayUS0069
From0.001
To0.001
CSJ6393-05-001
Proj IDMMC - 639305001
Work TypeDENSE GRADED HOT MIX
 
0.010543375.00316523.2558.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-23-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged223
Percent Time Used61
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214016
Totals543375.000.00316523.2558.2

CountyFANNIN
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToFANNIN COUNTY
CSJ6393-34-001
Proj IDRMC - 639334001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010758000.0071462.509.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224010
Totals758000.0013180.0071462.509.4

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHUNT AND RAINS COUNTY
CSJ6393-38-001
Proj IDRMC - 639338001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101511217.5045402.253.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224427
Totals1511217.5023944.2545402.253.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToLAMAR, DELTA AND RED RIVER COUNTY
CSJ6393-40-001
Proj IDRMC - 639340001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101236500.00184972.5014.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224614
Totals1236500.0087472.50184972.5014.9

CountyGRAYSON
HighwayUS0069
FromVARIOUS LOCATIONS IN
ToGRAYSON COUNTY
CSJ6393-41-001
Proj IDRMC - 639341001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010963650.00263661.2527.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6393-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224213
Totals963650.0031786.25263661.2527.3

CountyHOPKINS
HighwaySH0019
FromVARIOUS LOCATIONS IN
ToHOPKINS AND FRANKLIN COUNTY
CSJ6393-42-001
Proj IDRMC - 639342001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101360000.00176217.5012.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224615
Totals1360000.0022310.00176217.5012.9

CountyGRAYSON
HighwaySH0005
From0.001
To0.001
CSJ6393-44-001
Proj IDMMC - 639344001
Work TypeDENSE GRADED HOT MIX
 
0.010623000.00613373.1798.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged306
Percent Time Used85
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224017
Totals623000.0032882.01613373.1798.4

CountyFANNIN
HighwaySH0078
From0.001
To0.001
CSJ6393-45-001
Proj IDMMC - 639345001
Work TypeASPHALT
 
0.010281110.00221156.1678.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-27-22
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged219
Percent Time Used91
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224219
Totals281110.000.00221156.1678.6

page 1 | page 2 | page 3