Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | GRAYSON |
Highway | US0075 |
From | VARIOUS LOCATIONS IN |
To | GRAYSON COUNTY |
CSJ | 6456-37-001 |
Proj ID | RMC - 645637001 |
Work Type | CLEANING AND SWEEPING HIGHWAYS |
|
| 0.010 | 277719.00 | | 195136.00 | 70.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 245 |
Percent Time Used | 33 |
Contractor(s) |
TEXAS TMA RENTAL |
SUBCONTRACTOR(S) FOR CCSJ: 6456-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234037 |
| Totals | 277719.00 | 0.00 | 195136.00 | 70.2 |
|
County | HUNT |
Highway | SH0034 |
From | VARIOUS LOCATIONS IN |
To | HUNT COUNTY |
CSJ | 6457-50-001 |
Proj ID | BPM - 645750001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 416470.00 | | 498150.60 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 90 |
Addl Days Granted | 0 |
Working Days Charged | 67 |
Percent Time Used | 74 |
Contractor(s) |
DCC CONSTRUCTION AND SERVICES, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244217 |
| Totals | 416470.00 | 0.00 | 498150.60 | 99.9 |
|
County | FANNIN |
Highway | SH0056 |
From | VARIOUS LOCATIONS IN |
To | FANNIN COUNTY |
CSJ | 6457-53-001 |
Proj ID | BPM - 645753001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 720186.52 | | 799396.20 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-24-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 42 |
Addl Days Granted | 10 |
Working Days Charged | 51 |
Percent Time Used | 98 |
Contractor(s) |
L & N BRIDGE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6457-53-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244203 |
| Totals | 720186.52 | 12562.00 | 799396.20 | 99.9 |
|
County | FANNIN |
Highway | SH0056 |
From | VARIOUS ROADWAYS IN |
To | FANNIN COUNTY |
CSJ | 6458-13-001 |
Proj ID | RMC - 645813001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 287920.00 | | 184935.00 | 64.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 76 |
Addl Days Granted | 0 |
Working Days Charged | 61 |
Percent Time Used | 80 |
Contractor(s) |
PREMIER CONTRACTORS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234038 |
| Totals | 287920.00 | 50455.00 | 184935.00 | 64.2 |
|
County | GRAYSON |
Highway | US0069 |
From | VARIOUS ROADWAYS IN |
To | GRAYSON COUNTY |
CSJ | 6458-27-001 |
Proj ID | RMC - 645827001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 290019.80 | | 135045.40 | 46.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-10-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 74 |
Addl Days Granted | 0 |
Working Days Charged | 61 |
Percent Time Used | 82 |
Contractor(s) |
DOUBLE S TRACTOR SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-27-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234217 |
| Totals | 290019.80 | 0.00 | 135045.40 | 46.5 |
|
County | GRAYSON |
Highway | US0075 |
From | VARIOUS ROADWAYS IN |
To | GRAYSON AND FANNIN COUNTY |
CSJ | 6458-29-001 |
Proj ID | RMC - 645829001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 350423.40 | | 233645.90 | 71.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-08-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 58 |
Addl Days Granted | 0 |
Working Days Charged | 83 |
Percent Time Used | 143 |
Contractor(s) |
AMS TRACTOR SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234218 |
| Totals | 350423.40 | 12973.00 | 233645.90 | 71.0 |
|
County | HOPKINS |
Highway | IH0030 |
From | VARIOUS ROADWAYS IN |
To | HOPKINS, HUNT, AND FRANKLIN CO. |
CSJ | 6458-33-001 |
Proj ID | RMC - 645833001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 273394.00 | | 191729.00 | 70.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 54 |
Addl Days Granted | 0 |
Working Days Charged | 22 |
Percent Time Used | 40 |
Contractor(s) |
EASTGATE SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6458-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234039 |
| Totals | 273394.00 | 0.00 | 191729.00 | 70.1 |
|
County | GRAYSON |
Highway | SH0005 |
From | GRAYSON COUNTY |
To | MAINTENANCE GROUNDS |
CSJ | 6459-59-001 |
Proj ID | MMC - 645959001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 941000.00 | | 382444.55 | 40.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 245 |
Percent Time Used | 67 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234219 |
| Totals | 941000.00 | 137487.24 | 382444.55 | 40.6 |
|
County | HUNT |
Highway | US0069 |
From | VARIOUS LOCATIONS IN |
To | HUNT AND RAINS COUNTY |
CSJ | 6460-87-001 |
Proj ID | RMC - 646087001 |
Work Type | DITCH CLEANING AND RESHAPING |
|
| 0.010 | 370506.00 | | 22272.80 | 6.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 31 |
Percent Time Used | 8 |
Contractor(s) |
RHINO EQUITY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244212 |
| Totals | 370506.00 | 22272.80 | 22272.80 | 6.0 |
|
County | HOPKINS |
Highway | IH0030 |
From | VARIOUS ROADWAYS IN |
To | IN HOPKINS COUNTY |
CSJ | 6460-90-001 |
Proj ID | MMC - 646090001 |
Work Type | EMULSION |
|
| 0.010 | 267750.00 | | 3860.00 | 1.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 153 |
Percent Time Used | 84 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6460-90-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244017 |
| Totals | 267750.00 | 0.00 | 3860.00 | 1.4 |
|
County | GRAYSON |
Highway | US0075 |
From | VARIOUS LOCATIONS |
To | ALONG US75 |
CSJ | 6461-91-001 |
Proj ID | RMC - 646191001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 737885.00 | | 207708.04 | 28.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 47 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 53 |
Contractor(s) |
STX CIVIL |
SUBCONTRACTOR(S) FOR CCSJ: 6461-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244031 |
| Totals | 737885.00 | 120221.84 | 207708.04 | 28.1 |
|
County | LAMAR |
Highway | US0082 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6462-78-001 |
Proj ID | RMC - 646278001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 357322.00 | | 39977.50 | 11.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-08-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 177 |
Percent Time Used | 48 |
Contractor(s) |
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 6462-78-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244218 |
| Totals | 357322.00 | 2922.50 | 39977.50 | 11.1 |
|
County | FANNIN |
Highway | US0069 |
From | VARIOUS LOCATIONS IN |
To | FANNIN COUNTY |
CSJ | 6463-19-001 |
Proj ID | MMC - 646319001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 769200.00 | | 749786.08 | 97.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-22-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 120 |
Working Days Charged | 193 |
Percent Time Used | 80 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244018 |
| Totals | 769200.00 | 0.00 | 749786.08 | 97.4 |
|
County | LAMAR |
Highway | US0271 |
From | VARIOUS LOCATIONS |
To | IN LAMAR COUNTY |
CSJ | 6463-20-001 |
Proj ID | MMC - 646320001 |
Work Type | EMULSION |
|
| 0.010 | 512150.00 | | 384625.89 | 75.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 183 |
Working Days Charged | 184 |
Percent Time Used | 50 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-20-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244019 |
| Totals | 512150.00 | 7352.45 | 384625.89 | 75.1 |
|
County | RAINS |
Highway | US0069 |
From | VARIOUS LOCATIONS |
To | IN RAINS COUNTY |
CSJ | 6463-21-001 |
Proj ID | MMC - 646321001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 665000.00 | | 247253.16 | 37.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-13-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 120 |
Working Days Charged | 172 |
Percent Time Used | 71 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244020 |
| Totals | 665000.00 | 3213.56 | 247253.16 | 37.1 |
|
County | FRANKLIN |
Highway | US0067 |
From | VARIOUS ROADWAYS |
To | IN FRANKLIN COUNTY |
CSJ | 6463-24-001 |
Proj ID | MMC - 646324001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 832000.00 | | 323287.35 | 38.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 120 |
Working Days Charged | 153 |
Percent Time Used | 63 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244219 |
| Totals | 832000.00 | 0.00 | 323287.35 | 38.8 |
|
County | RED RIVER |
Highway | SH0037 |
From | VARIOUS ROADWAYS |
To | IN RED RIVER COUNTY |
CSJ | 6463-26-001 |
Proj ID | MMC - 646326001 |
Work Type | EMULSION |
|
| 0.010 | 300300.00 | | 295045.78 | 98.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 183 |
Working Days Charged | 184 |
Percent Time Used | 50 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244220 |
| Totals | 300300.00 | 4804.70 | 295045.78 | 98.2 |
|
County | LAMAR |
Highway | US0082 |
From | VARIOUS ROADWAYS IN |
To | THE PARIS DISTRICT |
CSJ | 6463-28-001 |
Proj ID | MMC - 646328001 |
Work Type | FLEXIBLE BASE |
|
| 0.010 | 1592700.00 | | 1348994.68 | 84.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-24-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 130 |
Percent Time Used | 71 |
Contractor(s) |
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244019 |
| Totals | 1592700.00 | 145785.90 | 1348994.68 | 84.6 |
|
County | HUNT |
Highway | IH0030 |
From | VARIOUS ROADWAYS |
To | IN HUNT COUNTY |
CSJ | 6463-31-001 |
Proj ID | MMC - 646331001 |
Work Type | EMULSION |
|
| 0.010 | 267750.00 | | 361781.95 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 165 |
Percent Time Used | 45 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244212 |
| Totals | 267750.00 | 0.00 | 361781.95 | 99.9 |
|
County | RAINS |
Highway | US0069 |
From | VARIOUS ROADWAYS |
To | IN RAINS COUNTY |
CSJ | 6463-32-001 |
Proj ID | MMC - 646332001 |
Work Type | EMULSION |
|
| 0.010 | 267750.00 | | 198314.11 | 74.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 165 |
Percent Time Used | 45 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244020 |
| Totals | 267750.00 | 0.00 | 198314.11 | 74.0 |
|