Monthly State Let Construction Report For Pharr District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyZAPATA ETC
HighwayUS 83 ETC
From0.45 MI N OF BUS 83N (N. INT.)
ToFM 3169
CSJ0038-03-041
Proj IDSTP 2020(851)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.8092749448.882050779.6574.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-20
Work Began09-02-20
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted0
Working Days Charged199
Percent Time Used62
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0038-03-041
VALLEY STRIPING CORP. (0.74)
MATTHEW GREEN LLC (5.48)
G & E ESCOBEDO CONSTRUCTION, INC. (0.52)
Contract #05203220
Totals2749448.8870038.902050779.6574.5

CountyZAPATA
HighwayUS 83
From17TH ST.
To1ST ST.
CSJ0038-04-069
Proj IDF 2021(731)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
549124.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0038-04-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213234
Totals549124.050.000.000.0

CountyHIDALGO
HighwayUS 83
From0.85 MI E OF FM 886 (EL FARO RD)
To232' W OF FM 1427
CSJ0039-02-040
Proj IDNH 1502(464)
Work TypeGR., STRS. AND SURF
 
6.70057163619.4963788688.7099.9
CountyHIDALGO
HighwayUS 83
From232' W OF FM 1427
To0.28 MI WEST OF SHOWERS RD
CSJ0039-17-131
Proj IDNH 1502(464)
Work TypeGR., STRS., AND SURF
 
1.63830058578.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-15
Work Began02-01-18
Work Completed
Time Computed00-00-00
Contract Working Days805
Addl Days Granted95
Working Days Charged717
Percent Time Used79
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-02-040
REIM CONSTRUCTION, INC. (9.14)
MUSTANG COLT SERVICES, INC. (2.49)
A. H. BECK FOUNDATION CO., INC. (3.45)
D&S TEXAS ICON CONSTRUCTION (0.33)
IZAGUIRRE CONSTRUCTION (0.61)
S & S BRIDGE PAINTING, INC. (0.16)
HIGHWAY BARRICADES AND SERVICES, LLC (0.27)
PRIMATE CONSTRUCTION, INC. (0.08)
GUERRA CONSTRUCTION COMPANY (0.35)
WEST TEXAS RUMBLE STRIP (0.01)
GULF COAST CONTRACTORS, INC. (0.07)
TEXAS HIGHWAY SYSTEMS, INC. (0.01)
FOREMOST PAVING, INC. (18.26)
WEBBER BARRIER SERVICES, LLC. (0.73)
CHOCTAW ERECTORS, INC. (1.98)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.08)
CERTIFIED PLACERS LLC (0.09)
HURFCO INDUSTRIES, INC. DBA HURRICANE FENCE COMPANY (0.04)
THE LEVY COMPANY, INC. (0.74)
AARON CONCRETE CONTRACTORS, L.P. (0.38)
Contract #07153002
Totals87222198.041180654.5263788688.7073.1

CountyHIDALGO
HighwayCS
FromFM 2221(JARA CHINAS ROAD)
To0.28 MI WEST OF SHOWERS ROAD
CSJ0039-02-063
Proj IDNH 1902(056)
Work TypeNEW LOCATION FREEWAY
 
5.13295910808.0963339188.5866.0
CountyHIDALGO
HighwayUS 83
FromFM 1427
ToBUSINESS 83 S
CSJ0039-17-202
Proj IDNH 2020(112)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.48083214.740.000.0
Work Order11-20-19
Work Began01-21-20
Work Completed
Time Computed01-02-20
Contract Working Days851
Addl Days Granted0
Working Days Charged392
Percent Time Used46
Contractor(s)
PULICE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-02-063
HIGHWAY BARRICADES AND SERVICES, LLC (0.56)
IOC COMPANY LLC (43.60)
GULF COAST CONTRACTORS, INC. (0.40)
IZAGUIRRE CONSTRUCTION LLC (5.35)
MOBILE ENTERPRISES, INC. (0.18)
THE LEVY COMPANY, INC. (4.42)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.17)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.39)
A. H. BECK FOUNDATION CO., INC. (2.65)
CERTIFIED PLACERS LLC (0.08)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
CHOCTAW ERECTORS, INC. (3.79)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.02)
Contract #10193201
Totals95994022.832894877.8963339188.5865.9

CountyHIDALGO ETC
HighwayUS 83 ETC
FromTOM GILL RD.
ToFM 1427
CSJ0039-02-068
Proj IDSTP 2019(275)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
18.6606096123.005693580.5093.3
Work Order01-22-19
Work Began06-10-19
Work Completed
Time Computed02-22-19
Contract Working Days320
Addl Days Granted0
Working Days Charged305
Percent Time Used95
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-02-068
PAVEMENT MARKINGS INC. (6.38)
G & E ESCOBEDO CONSTRUCTION, INC. (0.22)
Contract #12183212
Totals6096123.0098368.405693580.5093.3

CountyHIDALGO
HighwayUS 83
From2.164 MILES WEST OF FM 2221
ToFM 2221
CSJ0039-02-070
Proj IDNH 2019(954)
Work TypeREHABILITATE ROADWAY
 
2.1647504996.846423318.5585.3
Work Order05-14-19
Work Began03-02-20
Work Completed
Time Computed12-02-19
Contract Working Days190
Addl Days Granted0
Working Days Charged270
Percent Time Used142
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-02-070
SOIL-TECH, INC. (1.13)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (1.97)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
PAVEMENT MARKINGS INC. (3.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (3.96)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.33)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
Contract #04193209
Totals7504996.84577839.806423318.5585.3

CountyHIDALGO
HighwayUS 83
FromTABASCO RD.
ToFM 1427
CSJ0039-02-072
Proj IDSTP 1902(312)HES
Work TypeSFT
 
1.515526589.97410137.5899.9
CountyHIDALGO
HighwayIH 69C
FromBUS 281 W
ToFM 2812
CSJ0255-07-143
Proj IDSTP 1902(312)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.815881461.93949530.1899.9
CountyHIDALGO
HighwaySH 107
FromFM 493
ToMILE 6 W. RD.
CSJ0342-01-094
Proj IDSTP 1902(312)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
390176.35231815.7059.4
CountyHIDALGO
HighwaySH 107
From0.4 MI SOUTH OF FM 676
To0.28 MI NORHT OF FM 1924
CSJ0528-01-122
Proj IDSTP 1902(312)HES
Work TypeSFT
 
1.327379600.54336669.4988.6
Work Order10-17-19
Work Began04-08-20
Work Completed
Time Computed02-03-20
Contract Working Days90
Addl Days Granted0
Working Days Charged246
Percent Time Used273
Contractor(s)
CLORE EQUIPMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0039-02-072
GULF COAST CONTRACTORS, INC. (3.52)
HIGHWAY BARRICADES AND SERVICES, LLC (1.50)
TENORIO"S CONCRETE (5.79)
Contract #08193224
Totals2177828.7955114.501928152.9594.1

CountyHIDALGO ETC
HighwayBU 83-S ETC
FromAT SS 433
To.
CSJ0039-04-129
Proj IDSTP 2020(986)HES
Work TypeTRAFFIC CONTROL DEVICES
 
2.4002216223.851218778.0054.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began03-02-21
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged83
Percent Time Used41
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-04-129
HIGHWAY BARRICADES AND SERVICES, LLC (6.33)
IZAGUIRRE CONSTRUCTION LLC (1.03)
G & E ESCOBEDO CONSTRUCTION, INC. (0.91)
Contract #07203024
Totals2216223.8595495.001218778.0054.9

CountyCAMERON
HighwayIH 69E
FromWHALEN RD.
ToFM 2994
CSJ0039-07-256
Proj IDNH 2B20(151)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2248369.131998873.5788.9
CountyCAMERON
HighwayBU 77-X
FromON BUSINESS 77, FROM WASHINGTON AVE
ToLOOP 499
CSJ0327-08-100
Proj IDNH 2B20(151)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1368580.06602924.3944.0
CountyCAMERON
HighwaySS 206
FromON HARRISON & TYLER AVE
ToFROM DIXIELAND RD. TO "F" ST
CSJ1425-03-068
Proj IDNH 2B20(151)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.0011777504.85349766.2319.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-24-20
Work Began10-26-20
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted0
Working Days Charged141
Percent Time Used76
Contractor(s)
EARTHWORKS ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 0039-07-256
TEXAS HIGHWAY SYSTEMS, INC. (0.26)
SOIL TECH ADVANCE INC. (6.44)
MVP INSTALLATIONS, L.P. (0.74)
GP7 CONSTRUCTION INC. (39.78)
PAVEMENT MARKINGS INC. (1.38)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.67)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (12.51)
ARTILLERY, LLC (4.43)
Contract #08203017
Totals5394454.04261340.972951564.1954.7

CountyCAMERON ETC
HighwayBU 77-X ETC
From@ PFC JUAN GARZA RD.
To.
CSJ0039-12-058
Proj IDSTP 2018(523)HES
Work TypeINSTALL INT. FLASHING BEACON
 
4.8251094325.401115111.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began11-16-18
Work Completed
Time Computed00-00-00
Contract Working Days216
Addl Days Granted10
Working Days Charged221
Percent Time Used97
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-12-058
VALLEY INFRASTRUCTURE, INC. (7.80)
PAVEMENT MARKINGS INC. (3.79)
G & E ESCOBEDO CONSTRUCTION, INC. (3.81)
Contract #02183226
Totals1094325.400.001115111.0099.9

CountyCAMERON ETC
HighwayBU 77-X ETC
From@ FM 509
To.
CSJ0039-12-252
Proj IDSTP 2020(041)HES
Work TypeTRAFFIC CONTROL DEVICES
 
3330767.382330336.3469.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-21-20
Work Began10-12-20
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted0
Working Days Charged165
Percent Time Used62
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-12-252
VALLEY STRIPING CORP. (12.98)
MATTHEW GREEN LLC (1.24)
GP7 CONSTRUCTION INC. (0.76)
G & E ESCOBEDO CONSTRUCTION, INC. (1.14)
Contract #01203011
Totals3330767.3844660.512330336.3469.9

CountyCAMERON
HighwayBU 77-X
FromON BUS 77 @ ARROYO COLORADO
ToSTR #:_0039-12-035
CSJ0039-12-261
Proj IDBR 2B20(152)
Work TypeBRIDGE MAINTENANCE
 
397948.75386229.3597.0
CountyCAMERON
HighwayBU 77-X
FromON BUS 77NB @ DRAINAGE DITCH
ToSTR #:_0039-12-050
CSJ0039-12-262
Proj IDBR 2B20(152)
Work TypeBRIDGE MAINTENANCE
 
137294.1082015.7059.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-20
Work Began10-16-20
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged77
Percent Time Used89
Contractor(s)
LUCANIA CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0039-12-261
MOBILE ENTERPRISES, INC. (13.47)
TEXAS HIGHWAY SYSTEMS, INC. (6.95)
PAVEMENT MARKINGS INC. (5.93)
GULF COAST CONTRACTORS, INC. (0.93)
Contract #08203038
Totals535242.850.00468245.0587.4

CountyHIDALGO
HighwayIH 2
From0.209 MI W OF SP 115
To0.203 MI E OF SH 336
CSJ0039-17-180
Proj IDNH 2016(326)
Work TypeINT. IMP. @ MAIN ST & BICENTENNIAL
 
1.23943588077.4345222286.6399.9
CountyHIDALGO
HighwayIH 2
FromIH 2
To@ BICENTENNIAL RAMP,STR#0039-17-278
CSJ0039-17-186
Proj IDBR 2016(044)
Work TypeREPLACE BRIDGE
 
0.1252514579.512645490.8199.9
Work Order01-29-16
Work Began06-27-16
Work Completed
Time Computed02-29-16
Contract Working Days610
Addl Days Granted127
Working Days Charged1,073
Percent Time Used145
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-17-180
A & A CONSTRUCTION (0.31)
A. H. BECK FOUNDATION CO., INC. (1.50)
AARON CONCRETE CONTRACTORS, L.P. (2.62)
CERTIFIED PLACERS LLC (0.21)
SOIL-TECH, INC (0.95)
HIGHWAY BARRICADES AND SERVICES, LLC (1.12)
IZAGUIRRE CONSTRUCTION (2.96)
PRIMATE CONSTRUCTION, INC. (0.15)
WEST TEXAS RUMBLE STRIP (0.01)
SOUTH TEXAS PAINTING COMPANY (0.14)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.85)
FOREMOST PAVING, INC. (26.40)
GULF COAST CONTRACTORS, INC. (0.12)
MUSTANG COLT SERVICES, INC. (3.40)
VALLEY BORING SERVICE, LTD (0.06)
HUNTER DEMOLITION & WRECKING CORPORATION (1.31)
GIBSON & ASSOCIATES, INC. (0.16)
ROVAN TEXAS, LLC (0.62)
REIM CONSTRUCTION, INC. (0.34)
GUERRA CONSTRUCTION COMPANY (0.02)
G & E ESCOBEDO CONSTRUCTION, INC. (0.02)
Contract #11153203
Totals46102656.9442955.3447867777.4499.9

CountyHIDALGO
HighwayIH 2
FromLOS EBANOS RD. UNDERPASS
ToFM 2220 (WARE RD.)
CSJ0039-17-198
Proj IDNH 2020(562)
Work TypeOVERLAY
 
5.8128488894.257944285.1094.4
CountyHIDALGO
HighwayFM 2061
FromTRENTON RD.
ToFM 3461
CSJ1939-01-055
Proj IDNH 2020(562)
Work TypeOVERLAY
 
2.0951440510.251391801.9696.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-21-20
Work Began08-17-20
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged137
Percent Time Used201
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-17-198
CHEROKEE SERVICES (0.23)
HUDSON, INC. SOUTH (3.97)
(INACTIVE)D&S TEXAS ICON CONSTRUCTION (9.00)
THE LEVY COMPANY, INC. (0.48)
HIGHWAY BARRICADES AND SERVICES, LLC (2.82)
GP7 CONSTRUCTION INC. (0.08)
FOREMOST PAVING, INC. (35.16)
Contract #02203004
Totals9929404.506815.009336087.0694.8

CountyHIDALGO
HighwayIH 2
From0.07 MI WEST OF FM 2061 (MCCOLL RD)
ToFM 2557
CSJ0039-17-200
Proj IDNH 2019(112)
Work TypeOVERLAY (MAIN LANES)
 
4.0032519803.992547610.7299.9
CountyCAMERON
HighwayIH 2
FromHIDALGO/CAMERON CL
ToDIXIELAND RD.
CSJ0039-19-061
Proj IDNH 2019(112)
Work TypeOVERLAY
 
9.2766214214.384526756.8774.4
Work Order11-27-18
Work Began08-26-19
Work Completed
Time Computed12-27-18
Contract Working Days152
Addl Days Granted0
Working Days Charged241
Percent Time Used158
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0039-17-200
HIGHWAY BARRICADES AND SERVICES, LLC (3.98)
RIO-TECH (0.00)
DUSTROL, INC. (4.16)
Contract #10183016
Totals8734018.370.007074367.5982.1

CountyCAMERON
HighwaySS 54
FromCHESTER PARK ROAD
ToIH-69E SB FRONTAGE ROAD
CSJ0039-20-008
Proj IDNH 2019(773)
Work TypeWIDEN ROADWAY
 
0.1007086524.207462575.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-19
Work Began06-24-19
Work Completed
Time Computed00-00-00
Contract Working Days318
Addl Days Granted16
Working Days Charged325
Percent Time Used97
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0039-20-008
HIGHWAY BARRICADES AND SERVICES, LLC (1.27)
HUDSON, INC. SOUTH (0.77)
TRAF-TEX, INC. (5.99)
EXTERIOR DESIGNS (3.79)
MVP INSTALLATIONS, L.P. (5.33)
MATTHEW GREEN LLC (0.13)
Contract #04193013
Totals7086524.207385.007462575.0499.9

CountyBROOKS
HighwaySH 285
FromFM 2191
ToKLEBERG/BROOKS CL
CSJ0102-07-044
Proj IDSTP 1502(583)
Work TypeREHABILITATE ROADWAY
 
4.83912283376.6914218884.3899.9
Work Order11-10-15
Work Began01-28-16
Work Completed
Time Computed12-30-15
Contract Working Days359
Addl Days Granted181
Working Days Charged896
Percent Time Used165
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-07-044
HIGHWAY BARRICADES AND SERVICES, LLC (0.49)
WEST TEXAS RUMBLE STRIP (0.03)
HUDSON, INC. (1.01)
PAVEMENT MARKINGS INC. (1.18)
J & P TRUCKING AND HAULING (4.67)
CEDOSCA CONSTRUCTION, LLC (2.23)
IZAGUIRRE CONSTRUCTION LLC (1.49)
HOT FOOT AMERICA (0.29)
EARTHCO (0.00)
LAREDO STRIPING INC. (1.00)
TEXAS CORDIA CONSTRUCTION, LLC (0.83)
SHINN AND GREGORY, INC. (0.55)
D&S TEXAS ICON CONSTRUCTION (1.96)
TNT CRANE & RIGGING, INC. (0.18)
Contract #08153013
Totals12283376.690.0014218884.3899.9

CountyBROOKS ETC
HighwaySH 285 ETC
FromFM 1418
ToFM 2191
CSJ0102-07-045
Proj IDSTP 1902(052)
Work TypeOVERLAY
 
20.85011330610.739254148.8082.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-19
Work Began08-17-20
Work Completed
Time Computed00-00-00
Contract Working Days138
Addl Days Granted0
Working Days Charged220
Percent Time Used159
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-07-045
ANDERSON COLUMBIA CO., INC. (11.45)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.94)
CHEROKEE SERVICES (0.64)
TEXAS ICON CONSTRUCTION, LLC (0.83)
HIGHWAY BARRICADES AND SERVICES, LLC (4.31)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.86)
IOC COMPANY LLC (16.09)
Contract #06193011
Totals11330610.73836241.009254148.8082.6

CountyCAMERON
HighwayUS 281
FromFM 509
To0.499 MI W OF FM 732
CSJ0220-03-031
Proj IDC 220-4-44
Work TypeREHAB EXISTING ROADWAY
 
3.9568463989.828959768.0199.9
CountyCAMERON
HighwayUS 281
From0.499 MI W OF FM 732
To0.114 MI E OF FM 732
CSJ0220-04-044
Proj IDC 220-4-44
Work TypeREHAB EXISTING ROADWAY
 
0.6131354488.931289534.4295.2
Work Order07-19-18
Work Began11-05-18
Work Completed
Time Computed08-19-18
Contract Working Days440
Addl Days Granted14
Working Days Charged452
Percent Time Used99
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-031
SOIL-TECH, INC. (1.08)
PAVEMENT MARKINGS INC. (2.30)
HIGHWAY BARRICADES AND SERVICES, LLC (0.50)
GP7 CONSTRUCTION INC. (1.44)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.76)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (9.26)
GULF COAST CONTRACTORS, INC. (0.09)
G & E ESCOBEDO CONSTRUCTION, INC. (0.04)
GP7 CONSTRUCTION INC. (0.70)
Contract #06183015
Totals9818478.7549700.0010249302.4399.9

CountyCAMERON
HighwaySH 48 ETC
FromMCLELLAND ST.
ToMEDICAL ST.
CSJ0220-05-070
Proj IDSTP 2018(636)MM
Work TypeINSTALL TRAFFIC SIGNAL
 
1.6001198847.311221046.2199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-18-18
Work Began01-07-19
Work Completed
Time Computed00-00-00
Contract Working Days331
Addl Days Granted24
Working Days Charged355
Percent Time Used100
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-05-070
TEXAS HIGHWAY SYSTEMS, INC. (1.06)
A&B STRUCTURAL CONSTRUCTION CO. LLC (12.08)
HIGHWAY BARRICADES AND SERVICES, LLC (1.40)
Contract #03183005
Totals1198847.310.001221046.2199.9

page 1 | page 2 | page 3