Monthly Local Let Maintenance Report For Pharr District As Of Jan 10, 2023 Page 1 Of 2

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwaySH0107
FromVARIOUS MAINTENANCE OFFICES
ToEDCOUCH, MISSION AND RAYMONDVILLE MNT
CSJ6192-98-001
Proj IDRMC - 619298001
Work TypeJANITORIAL MAINTENANCE
 
0.01038499.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days974
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RENFRO CONTRACT SERVICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11092101
Totals38499.840.000.000.0

CountyJIM HOGG
HighwaySH0016
FromVARIOUS LIMITS
ToVARIOUS COUNTIES
CSJ6193-07-001
Proj IDSUP - 619307001
Work TypeFIREBREAK MAINTENANCE
 
0.01074049.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6193-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092146
Totals74049.360.000.000.0

CountyJIM HOGG
HighwayFM1017
From004, 006, 008, 009
ToVARIOUS ROADWAYS
CSJ6212-33-001
Proj IDSUP - 621233001
Work TypeFIREBREAK MAINTENANCE
 
0.01037906.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6212-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09102138
Totals37906.220.000.000.0

CountyCAMERON
HighwayUS0077
FromVARIUOUS
To.
CSJ6308-46-001
Proj IDSUP - 630846001
Work TypeJANITORIAL AND GROUNDS
 
0.001218584.80218888.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged729
Percent Time Used101
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162101
Totals218584.800.00218888.3999.9

CountyCAMERON
HighwayIH0069E
FromI-69E/I-2 INTERCHANGE
ToCAMERON COUNTY
CSJ6357-50-001
Proj IDSUP - 635750001
Work TypeLANDSCAPE MAINTENANCE
 
0.010318456.60314956.5598.9
Work Order09-25-20
Work Began11-03-20
Work Completed
Time Computed11-01-20
Contract Working Days731
Addl Days Granted0
Working Days Charged727
Percent Time Used99
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-50-001
RGR INDUSTRIES, INC. (0.00)
Contract #09202130
Totals318456.6010148.99314956.5598.9

CountyHIDALGO
HighwayIH0069C
FromVARIOUS ROADWAYS
ToHIDALGO COUNTY
CSJ6376-16-001
Proj IDSUP - 637616001
Work TypeLITTER REMOVAL
 
0.010256940.9849829.9619.3
Work Order08-09-21
Work Began09-14-21
Work Completed
Time Computed09-14-21
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-16-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212131
Totals256940.980.0049829.9619.3

CountyCAMERON
HighwayUS0077
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6376-17-001
Proj IDSUP - 637617001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010584184.00433164.0074.1
Work Order08-11-21
Work Began09-07-21
Work Completed
Time Computed09-07-21
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-17-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212135
Totals584184.000.00433164.0074.1

CountySTARR
HighwayUS0083
FromROMA MNT/AO
ToHEBBRONVILLE MNT
CSJ6376-18-001
Proj IDSUP - 637618001
Work TypeJANITORIAL MAINTENANCE
 
0.01086496.9853480.2861.8
Work Order08-19-21
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-18-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08212136
Totals86496.983036.8153480.2861.8

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6376-76-001
Proj IDSUP - 637676001
Work TypeSTATE USE CONTRACT
 
0.01056617.6036246.8464.0
Work Order09-01-21
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged479
Percent Time Used65
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-76-001
GOODWILL INDUSTRIES OF SOUTH TEXAS, (0.00)
Contract #08212133
Totals56617.602177.6036246.8464.0

CountyHIDALGO
HighwayIH0069C
FromPHARR DISTRICT COMPLEX
ToPHARR MNT/AO
CSJ6376-78-001
Proj IDSUP - 637678001
Work TypeGROUNDS MAINTENANCE
 
0.01061812.0033724.5054.5
Work Order08-19-21
Work Began09-20-21
Work Completed
Time Computed09-20-21
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-78-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08212134
Totals61812.002079.0033724.5054.5

CountyCAMERON
HighwayIH0002
FromIH 2, IH 69E AND SP 54
ToCAMERON, WILLACY AND KENEDY COUNTY
CSJ6377-13-001
Proj IDSUP - 637713001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010932713.33398978.1542.7
Work Order08-20-21
Work Began10-04-21
Work Completed
Time Computed09-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-13-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212132
Totals932713.3344349.17398978.1542.7

CountyHIDALGO
HighwaySH0495
FromVARIOUS COUNTIES
ToDISTRICTWIDE
CSJ6381-61-001
Proj IDMMC - 638161001
Work TypeHYDRAULIC CEMENT
 
0.010152932.50205864.7599.9
Work Order07-06-21
Work Began07-16-21
Work Completed
Time Computed07-16-21
Contract Working Days120
Addl Days Granted240
Working Days Charged359
Percent Time Used99
Contractor(s)
KLP COMMERCIAL, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6381-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06212103
Totals152932.500.00205864.7599.9

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6396-84-001
Proj IDSUP - 639684001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010451254.50129859.6328.7
Work Order08-30-22
Work Began09-08-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222135
Totals451254.5026775.50129859.6328.7

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6396-86-001
Proj IDSUP - 639686001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010984290.00197550.0020.0
Work Order08-26-22
Work Began09-07-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222136
Totals984290.0014130.00197550.0020.0

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6396-99-001
Proj IDSUP - 639699001
Work TypeDRAINAGE SYSTEM CLEANING
 
0.010591300.000.000.0
Work Order08-23-22
Work Began00-00-00
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222103
Totals591300.000.000.000.0

CountyHIDALGO
HighwayIH0002
FromEDCOUCH/ MISSION MAINTENANCE
ToRAYMONDVILLE MAINTENANCE
CSJ6397-00-001
Proj IDSUP - 639700001
Work TypeJANITORIAL MAINTENANCE
 
0.01061321.808176.2413.3
Work Order08-19-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222104
Totals61321.802044.068176.2413.3

CountyHIDALGO
HighwayIH0069C
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6397-01-001
Proj IDSUP - 639701001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010921137.0096138.1310.4
Work Order08-06-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222105
Totals921137.0018858.0596138.1310.4

CountyHIDALGO
HighwayIH0069C
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6397-02-001
Proj IDSUP - 639702001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010778710.0069225.008.8
Work Order08-26-22
Work Began00-00-00
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222106
Totals778710.009045.0069225.008.8

CountySTARR
HighwayUS0083
FromROMA/HEBBRONVILLE MAINTENANCE
ToVARIOUS ROADWAYS
CSJ6397-03-001
Proj IDSUP - 639703001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010679093.9040310.135.9
Work Order08-30-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222133
Totals679093.909645.6340310.135.9

CountySTARR
HighwayUS0083
FromVARIOUS LOCATIONS IN STARR AND JIM HOGG
ToROMA AND HEBBRONVILLE MAINTENANCE
CSJ6397-04-001
Proj IDSUP - 639704001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010211102.0030740.0014.5
Work Order08-26-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222134
Totals211102.0030740.0030740.0014.5

page 1 | page 2