Monthly Local Let Maintenance Report For Pharr District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwaySH0107
FromVARIOUS MAINTENANCE OFFICES
ToEDCOUCH, MISSION AND RAYMONDVILLE MNT
CSJ6192-98-001
Proj IDRMC - 619298001
Work TypeJANITORIAL MAINTENANCE
 
0.01038499.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days974
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RENFRO CONTRACT SERVICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11092101
Totals38499.840.000.000.0

CountyJIM HOGG
HighwaySH0016
FromVARIOUS LIMITS
ToVARIOUS COUNTIES
CSJ6193-07-001
Proj IDSUP - 619307001
Work TypeFIREBREAK MAINTENANCE
 
0.01074049.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6193-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092146
Totals74049.360.000.000.0

CountyJIM HOGG
HighwayFM1017
From004, 006, 008, 009
ToVARIOUS ROADWAYS
CSJ6212-33-001
Proj IDSUP - 621233001
Work TypeFIREBREAK MAINTENANCE
 
0.01037906.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6212-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09102138
Totals37906.220.000.000.0

CountyZAPATA
HighwaySH0016
FromSH 16 AND ALAMO STREET
ToZAPATA COUNTY
CSJ6257-03-001
Proj IDRMC - 625703001
Work TypeDRAINAGE SYSTEM
 
0.010210930.35224546.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-03-13
Work Began00-00-00
Work Completed
Time Computed01-02-14
Contract Working Days60
Addl Days Granted0
Working Days Charged30
Percent Time Used50
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6257-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11132101
Totals210930.350.00224546.5199.9

CountySTARR
HighwayUS0083
FromHEBBRONVILLE MNT, FALFURRIAS SUB,
ToZAPATA SUB, ROMA MNT/AO, RGC MAINTENANCE
CSJ6257-26-001
Proj IDSUP - 625726001
Work TypeJANITORIAL MAINTENANCE
 
0.01039358.0881450.71100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-13
Work Began00-00-00
Work Completed08-31-15
Time Computed09-02-13
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132106
Totals39358.080.0081450.71100.0

CountyHIDALGO
HighwayFM0490
FromVARIOUS ROADWAYS (FM ROADS)
ToEDCOUCH, MISSION AND PHARR MAINTENANCE
CSJ6257-45-001
Proj IDSUP - 625745001
Work TypeROADSIDE MOWING/LITTER REMOVAL
 
0.010312126.43130810.5841.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-31-13
Work Began00-00-00
Work Completed
Time Computed09-03-13
Contract Working Days730
Addl Days Granted0
Working Days Charged604
Percent Time Used82
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132132
Totals312126.430.00130810.5841.9

CountyJIM HOGG
HighwayFM1017
FromHEBBRONVILLE AND RIO GRANDE CITY MAINT
ToVARIOUS ROADWAYS
CSJ6257-56-001
Proj IDSUP - 625756001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010531653.36538293.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-29-13
Work Began00-00-00
Work Completed
Time Computed09-23-13
Contract Working Days730
Addl Days Granted30
Working Days Charged759
Percent Time Used99
Contractor(s)
WORKQUEST
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09132104
Totals531653.360.00538293.1799.9

CountyCAMERON
HighwayUS0077
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6268-93-001
Proj IDRMC - 626893001
Work TypeINTERSECTION & U-TURN IMPROVEMENTS
 
0.010436162.05601271.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-14
Work Began00-00-00
Work Completed
Time Computed05-01-14
Contract Working Days60
Addl Days Granted68
Working Days Charged128
Percent Time Used100
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03142101
Totals436162.050.00601271.6499.9

CountyHIDALGO
HighwayUS0083
FromVARIOUS COUNTIES
ToVARIOUS COUNTIES
CSJ6274-47-001
Proj IDRMC - 627447001
Work TypeTRAFFIC BARRIER REPAIR
 
0.010136650.00308265.9399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began01-15-15
Work Completed
Time Computed01-14-15
Contract Working Days60
Addl Days Granted40
Working Days Charged82
Percent Time Used82
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11142101
Totals136650.000.00308265.9399.9

CountyCAMERON
HighwayFM0511
FromFM 511, BETWEEN FM 802 AND
ToSH 04
CSJ6287-99-001
Proj IDEMC - 628799001
Work TypeREMOVING AND REPLACING THE EXISTING RUN
 
0.01023655.0023655.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-15
Work Began04-20-15
Work Completed04-24-15
Time Computed04-20-15
Contract Working Days7
Addl Days Granted0
Working Days Charged4
Percent Time Used57
Contractor(s)
G & T PAVING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152101
Totals23655.000.0023655.00100.0

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS_COUNTIES
CSJ6296-68-001
Proj IDRMC - 629668001
Work TypePALM TREE TRIMMING AND REMOVAL
 
0.010232322.00280536.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-10-18
Work Completed10-31-20
Time Computed00-00-00
Contract Working Days280
Addl Days Granted0
Working Days Charged114
Percent Time Used40
Contractor(s)
SAENZ UTILITY CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11172101
Totals232322.001400.00280536.00100.0

CountyCAMERON
HighwayIH0069E
FromCITY OF HARLINGEN
ToVARIOUS ROADWAYS
CSJ6302-44-001
Proj IDMMA - 630244001
Work TypeMAINTENANCE OF TRAFFIC SIGNALS
 
0.01099600.0099600.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
CITY OF HARLINGEN
SUBCONTRACTOR(S) FOR CCSJ: 6302-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162135
Totals99600.000.0099600.0099.9

CountyCAMERON
HighwayUS0077
FromVARIUOUS
To.
CSJ6308-46-001
Proj IDSUP - 630846001
Work TypeJANITORIAL AND GROUNDS
 
0.001218584.80218888.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged729
Percent Time Used101
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162101
Totals218584.800.00218888.3999.9

CountyHIDALGO
HighwayIH0002
FromVARIOUS ROADWAYS DISTRICTWIDE
ToVARIOUS ROADWAYS DISTRICTWIDE
CSJ6332-93-001
Proj IDRMC - 633293001
Work TypeON CALL PAVEMENT MARKINGS AND PAVEMENT M
 
0.010285928.10461740.4799.9
Work Order08-14-18
Work Began01-10-19
Work Completed
Time Computed01-10-19
Contract Working Days240
Addl Days Granted0
Working Days Charged46
Percent Time Used19
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6332-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08182101
Totals285928.1022529.07461740.4799.9

CountyHIDALGO
HighwayIH0002
FromIH 2 AND IH69C
ToHIDALGO COUNTY
CSJ6343-10-001
Proj IDSUP - 634310001
Work TypeROADSIDE LITTER REMOVAL
 
0.010238180.72127628.6053.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-02-19
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192130
Totals238180.720.00127628.6053.5

CountyCAMERON
HighwayIH0069E
FromIH 2, IH 69E, SP 54
ToCAMERON, WILLACY AND KENEDY COUNTY
CSJ6343-11-001
Proj IDSUP - 634311001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010992030.77619704.5762.4
Work Order08-29-19
Work Began10-28-19
Work Completed
Time Computed10-28-19
Contract Working Days731
Addl Days Granted0
Working Days Charged612
Percent Time Used83
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192131
Totals992030.7749878.55619704.5762.4

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6343-13-001
Proj IDSUP - 634313001
Work TypeTECHNICAL ASSISTANCE
 
0.01056617.6049349.8687.1
Work Order07-23-19
Work Began09-03-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged668
Percent Time Used91
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192133
Totals56617.602327.3149349.8687.1

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT COMPLEX
ToPHARR AREA/MAINTENANCE OFFICE
CSJ6343-14-001
Proj IDSUP - 634314001
Work TypeGROUNDS MAINTENANCE
 
0.01061812.0050496.0081.6
Work Order07-25-19
Work Began09-11-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192134
Totals61812.002079.0050496.0081.6

CountyCAMERON
HighwayIH0069E
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6343-15-001
Proj IDSUP - 634315001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010415015.18415015.2699.9
Work Order08-18-19
Work Began09-05-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged665
Percent Time Used90
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192135
Totals415015.180.00415015.2699.9

CountySTARR
HighwayUS0083
FromROMA AREA AND MAINTENANCE OFFICE
ToHEBBRONVILLE MAINTENANCE OFFICE
CSJ6343-16-001
Proj IDSUP - 634316001
Work TypeJANITORIAL MAINTENANCE
 
0.01084791.9473009.7386.1
Work Order08-08-19
Work Began09-03-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192136
Totals84791.942977.2673009.7386.1