Monthly Local Let Maintenance Report For Pharr District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6463-44-001
Proj IDSUP - 646344001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010439393.5058442.0013.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6463-44-001
RGR INDUSTRIES, INC. (0.00)
Contract #08242101
Totals439393.5029495.0058442.0013.3

CountyCAMERON
HighwayBU0077X
FromCAMERON COUNTY
ToVARIOUS ROADWAYS IN PHARR DISTRICT
CSJ6465-36-001
Proj IDSUP - 646536001
Work TypeCABLE BARRIER REPAIR
 
0.010785685.0041420.005.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged58
Percent Time Used15
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-36-001
RGR INDUSTRIES, INC. (0.00)
Contract #08242102
Totals785685.0028210.0041420.005.2

CountySTARR
HighwayUS0083
FromSTARR, ZAPATA, JIM HOGG, BROOKS COUNTIES
ToVARIOUS ROADWAYS
CSJ6465-37-001
Proj IDSUP - 646537001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010529902.0093347.0017.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged58
Percent Time Used7
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-37-001
RGR INDUSTRIES, INC. (0.00)
Contract #08242139
Totals529902.0091547.0093347.0017.6

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6465-38-001
Proj IDSUP - 646538001
Work TypeDRAINAGE SYSTEM CLEANING
 
0.010753500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-38-001
RGR INDUSTRIES, INC. (0.00)
Contract #08242130
Totals753500.000.000.000.0

CountyHIDALGO
HighwayIH0002
FromIH 2, IH 69, US 281
ToHIDALGO CAMERON COUNTY
CSJ6468-66-001
Proj IDSUP - 646866001
Work TypeDEBRIS REMOVAL
 
0.010652546.4247877.317.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6468-66-001
RGR INDUSTRIES, INC. (0.00)
Contract #08242104
Totals652546.4224585.6947877.317.3

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT COMPLEX
ToPHARR AREA/ MAINTENANCE OFFICE
CSJ6468-73-001
Proj IDSUP - 646873001
Work TypeJANITORIAL MAINTENANCE
 
0.010362410.9227941.407.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6468-73-001
E.Q.U.I.P. ENTERPRISES (0.00)
Contract #08242105
Totals362410.9214030.7027941.407.7

CountyCAMERON
HighwayUS0077
FromSAN BENITO MAINTENANCE
ToSAN BENITO AREA OFFICE
CSJ6469-49-001
Proj IDSUP - 646949001
Work TypeJANITORIAL MAINTENANCE
 
0.01059223.843882.246.5
Work Order09-01-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6469-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08242109
Totals59223.841941.123882.246.5

CountyHIDALGO
HighwaySH0495
FromVARIOUS COUNTIES
ToIN THE PHARR DISTRICT
CSJ6471-22-001
Proj IDMMC - 647122001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010159950.0046323.5128.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-28-24
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged8
Percent Time Used6
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08242107
Totals159950.0046323.5146323.5128.9

CountyCAMERON
HighwayIH0069E
FromCITY OF HARLINGEN
ToVARIOUS ROADWAYS
CSJ6471-71-001
Proj IDMMA - 647171001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.01099600.008300.008.3
Work Order09-01-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
CITY OF HARLINGEN
SUBCONTRACTOR(S) FOR CCSJ: 6471-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08242135
Totals99600.004150.008300.008.3