Monthly State Let Maintenance Report For San Antonio District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6338-00-001
Proj IDRMC - 633800001
Work TypeMOWING HWY ROW
 
0.001601862.00780543.0099.9
Work Order07-09-19
Work Began06-25-19
Work Completed
Time Computed07-25-19
Contract Working Days211
Addl Days Granted211
Working Days Charged154
Percent Time Used36
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-00-001
K-BAR SERVICES, INC. (11.05)
MISSOURI-TEXAS FARMS, LTD. (5.64)
Contract #01194220
Totals601862.0022447.92780543.0099.9

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKERR COUNTY
CSJ6338-01-001
Proj IDRMC - 633801001
Work TypeMOWING AND LITTER REMOVAL
 
0.001656697.00902740.1999.9
Work Order03-25-19
Work Began04-01-19
Work Completed
Time Computed04-01-19
Contract Working Days200
Addl Days Granted200
Working Days Charged151
Percent Time Used37
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-01-001
R&M INCORPORATED (0.00)
Contract #01194222
Totals656697.00111357.04902740.1999.9

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA, ATASCOSA
ToAND FRIO COUNTIES
CSJ6338-02-001
Proj IDRMC - 633802001
Work TypeMOWING AND LITTER REMOVAL
 
0.001665750.00912547.4199.9
Work Order05-30-19
Work Began06-13-19
Work Completed
Time Computed06-13-19
Contract Working Days239
Addl Days Granted239
Working Days Charged100
Percent Time Used20
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6338-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194223
Totals665750.0025898.40912547.4199.9

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKENDALL COUNTY
CSJ6338-03-001
Proj IDRMC - 633803001
Work TypeMOWING
 
0.001558476.00753016.5799.9
Work Order05-24-19
Work Began06-03-19
Work Completed
Time Computed06-03-19
Contract Working Days166
Addl Days Granted166
Working Days Charged105
Percent Time Used31
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194221
Totals558476.0095920.82753016.5799.9

CountyBANDERA
HighwaySH0016
FromVARIOUS LOCATIONS IN
ToBANDERA COUNTY
CSJ6338-04-001
Proj IDRMC - 633804001
Work TypeMOWING
 
0.001333050.00380883.0999.9
Work Order05-15-19
Work Began06-03-19
Work Completed
Time Computed06-03-19
Contract Working Days138
Addl Days Granted138
Working Days Charged146
Percent Time Used52
Contractor(s)
CLASSIC IRRIGATION & LANDSCAPE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194219
Totals333050.000.00380883.0999.9

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToCOMAL COUNTY
CSJ6338-05-001
Proj IDRMC - 633805001
Work TypeMOWING
 
0.001384507.20429189.1099.9
Work Order07-01-19
Work Began07-08-19
Work Completed
Time Computed07-08-19
Contract Working Days130
Addl Days Granted130
Working Days Charged86
Percent Time Used33
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194027
Totals384507.200.00429189.1099.9

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS IN
ToUVALDE COUNTY
CSJ6338-06-001
Proj IDRMC - 633806001
Work TypeMOWING
 
0.001588783.74677071.9799.9
Work Order06-10-19
Work Began06-18-19
Work Completed
Time Computed06-18-19
Contract Working Days190
Addl Days Granted190
Working Days Charged130
Percent Time Used34
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6338-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194028
Totals588783.740.00677071.9799.9

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN
ToWILSON COUNTY
CSJ6338-07-001
Proj IDRMC - 633807001
Work TypeMOWING
 
0.001497369.42664502.05100.0
Work Order05-30-19
Work Began06-06-19
Work Completed12-30-22
Time Computed06-06-19
Contract Working Days188
Addl Days Granted188
Working Days Charged166
Percent Time Used44
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6338-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194029
Totals497369.4261818.60664502.05100.0

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN ATASCOSA
ToCOUNTY
CSJ6354-23-001
Proj IDRMC - 635423001
Work TypeMOWING HWY ROW AND LITTER REMOVAL
 
0.001519032.24627883.1699.9
Work Order05-13-20
Work Began05-13-20
Work Completed
Time Computed05-20-20
Contract Working Days222
Addl Days Granted229
Working Days Charged103
Percent Time Used22
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6354-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204216
Totals519032.24101155.88627883.1699.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN FRIO, ATASCOSA AND
ToLASALLE COUNTIES
CSJ6354-38-001
Proj IDRMC - 635438001
Work TypeMOWING AND LITTER REMOVAL
 
0.001649631.60683165.5599.9
Work Order00-00-00
Work Began05-15-20
Work Completed
Time Computed05-11-20
Contract Working Days252
Addl Days Granted252
Working Days Charged128
Percent Time Used25
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6354-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204219
Totals649631.60111931.95683165.5599.9

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN
ToTHE SAN ANTONIO DISTRICT
CSJ6354-47-001
Proj IDRMC - 635447001
Work TypeGUARDRAIL REPAIR
 
0.0012522000.006752818.0199.9
Work Order03-05-20
Work Began04-06-20
Work Completed
Time Computed04-06-20
Contract Working Days730
Addl Days Granted730
Working Days Charged1,000
Percent Time Used68
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6354-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204218
Totals2522000.00304766.016752818.0199.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6370-38-001
Proj IDRMC - 637038001
Work TypeCALL OUT TRAFFIC CONTROL
 
0.0011076200.002886781.99100.0
Work Order11-30-20
Work Began12-01-20
Work Completed12-01-22
Time Computed12-01-20
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6370-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204011
Totals1076200.002236.692886781.99100.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6372-50-001
Proj IDRMC - 637250001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
0.01014977836.1615259195.0599.9
Work Order03-25-21
Work Began03-25-21
Work Completed
Time Computed04-01-21
Contract Working Days730
Addl Days Granted731
Working Days Charged640
Percent Time Used43
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6372-50-001
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (11.33)
BK FIELD OPERATIONS LLC (23.83)
AIMS COMPANIES (0.97)
JCW CONSTRUCTION, LLC (0.33)
Contract #01214020
Totals14977836.16649941.0415259195.0599.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6372-51-001
Proj IDRMC - 637251001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
0.01014188793.2412561337.5488.5
Work Order03-25-21
Work Began03-25-21
Work Completed
Time Computed03-25-21
Contract Working Days730
Addl Days Granted0
Working Days Charged640
Percent Time Used87
Contractor(s)
ATLANTIC SPECIALTY INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6372-51-001
ALAMO ENVIRONMENTAL, INC. (0.00)
BADGER DAYLIGHTING CORP. (0.00)
DIAMOND R CONSTRUCTION COMPANY (0.00)
EARTHTONES MAINTENANCE LLC (0.00)
MPR SERVICES (0.00)
STATEWIDE SAFETY SYSTEMS (0.00)
WASTE PARTNERS OF TEXAS, INC (0.00)
BIG RIVER CONTRACTORS LLC (0.00)
P-VILLE, INCORPORATED (0.00)
Contract #01214220
Totals14188793.24898682.5212561337.5488.5

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL AND
ToGUADALUPE COUNTIES
CSJ6372-52-001
Proj IDRMC - 637252001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
0.0105393594.001979043.4336.6
Work Order03-25-21
Work Began04-05-21
Work Completed
Time Computed04-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged640
Percent Time Used87
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6372-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214221
Totals5393594.00165247.001979043.4336.6

CountyGUADALUPE
HighwayUA0090
FromSH 123
ToGONZALES COUNTY LINE
CSJ6374-41-001
Proj IDRMC - 637441001
Work TypeMETAL BEAM GUARD FENCE UPGRADE
 
0.010711960.80881558.48100.0
Work Order07-14-22
Work Began07-22-22
Work Completed12-20-22
Time Computed07-22-22
Contract Working Days64
Addl Days Granted5
Working Days Charged62
Percent Time Used89
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6374-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224022
Totals711960.8021591.06881558.48100.0

CountyMEDINA
HighwayFM2676
From1.4 MILES WEST OF CO. RD. 271
To1.0 MILES WEST OF CO. RD. 271
CSJ6375-06-001
Proj IDRMC - 637506001
Work TypeCULVERT REPLACEMENT
 
0.010393370.50453580.3999.9
Work Order02-21-22
Work Began02-28-22
Work Completed
Time Computed02-28-22
Contract Working Days32
Addl Days Granted2
Working Days Charged29
Percent Time Used85
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-06-001
H. L. ZUMWALT CONSTRUCTION, INC. (19.12)
Contract #12214017
Totals393370.500.00453580.3999.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6379-83-001
Proj IDRMC - 637983001
Work TypePAVEMENT MARKINGS
 
0.0102806412.007279335.5599.9
Work Order07-22-21
Work Began07-28-21
Work Completed
Time Computed07-28-21
Contract Working Days365
Addl Days Granted365
Working Days Charged519
Percent Time Used71
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6379-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214026
Totals2806412.00883809.757279335.5599.9

page 1 | page 2 | page 3 | page 4