Monthly State Let Maintenance Report For San Antonio District As Of Nov 10, 2024 Page 2 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN KENDALL
ToBEXAR, AND COMAL COUNTIES
CSJ6423-34-001
Proj IDRMC - 642334001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010790344.50398677.5350.4
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed05-30-23
Contract Working Days730
Addl Days Granted0
Working Days Charged521
Percent Time Used71
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234013
Totals790344.500.00398677.5350.4

CountyBANDERA
HighwaySH0016
FromVARIOUS LOCATIONS
ToIN BANDERA COUNTY
CSJ6423-38-001
Proj IDRMC - 642338001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010398370.50235424.0459.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged519
Percent Time Used71
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234213
Totals398370.500.00235424.0459.0

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN COMAL
ToAND GUADALUPE COUNTIES
CSJ6423-40-001
Proj IDRMC - 642340001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010693048.50340787.5149.1
Work Order06-14-23
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days730
Addl Days Granted0
Working Days Charged494
Percent Time Used67
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234014
Totals693048.500.00340787.5149.1

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS
ToIN UVALDE COUNTY
CSJ6423-42-001
Proj IDRMC - 642342001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010635540.30372570.9558.6
Work Order00-00-00
Work Began06-19-23
Work Completed
Time Computed06-19-23
Contract Working Days730
Addl Days Granted0
Working Days Charged501
Percent Time Used68
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234214
Totals635540.305703.81372570.9558.6

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN WILSON
ToAND ATASCOSA COUNTIES
CSJ6423-44-001
Proj IDRMC - 642344001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010573644.00286011.0049.8
Work Order06-20-23
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days730
Addl Days Granted0
Working Days Charged494
Percent Time Used67
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6423-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234015
Totals573644.000.00286011.0049.8

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6428-56-001
Proj IDMMC - 642856001
Work TypeEMULSION
 
0.010707100.001473911.1799.9
Work Order02-17-23
Work Began02-23-23
Work Completed
Time Computed02-21-23
Contract Working Days365
Addl Days Granted366
Working Days Charged619
Percent Time Used84
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234215
Totals707100.00133522.391473911.1799.9

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN SEGUIN
ToMAINTENANCE SECTION
CSJ6428-58-001
Proj IDMMC - 642858001
Work TypeHOT MIX
 
0.010325250.002275835.4399.9
Work Order00-00-00
Work Began03-06-23
Work Completed
Time Computed02-27-23
Contract Working Days365
Addl Days Granted366
Working Days Charged613
Percent Time Used83
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234016
Totals325250.00155038.572275835.4399.9

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN BOERNE
ToMAINTENANCE SECTION
CSJ6428-60-001
Proj IDMMC - 642860001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010606041.202018490.1699.9
Work Order00-00-00
Work Began03-22-23
Work Completed
Time Computed03-07-23
Contract Working Days365
Addl Days Granted365
Working Days Charged592
Percent Time Used81
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234216
Totals606041.20158145.182018490.1699.9

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN FLORESVILLE
ToMAINTENANCE SECTION
CSJ6428-62-001
Proj IDMMC - 642862001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010783436.002037066.6799.9
Work Order00-00-00
Work Began03-23-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged611
Percent Time Used83
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234017
Totals783436.0054693.492037066.6799.9

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERRVILLE
ToMAINTENANCE SECTION
CSJ6428-64-001
Proj IDMMC - 642864001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010620100.001052550.5199.9
Work Order00-00-00
Work Began03-27-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged611
Percent Time Used83
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234217
Totals620100.0063524.861052550.5199.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN PEARSALL AND TILDEN
ToMAINTENANCE SECTIONS
CSJ6428-66-001
Proj IDMMC - 642866001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010630200.002441118.1799.9
Work Order02-22-23
Work Began03-30-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged580
Percent Time Used79
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234018
Totals630200.00182644.862441118.1799.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6444-96-001
Proj IDRMC - 644496001
Work TypePAVEMENT MARKINGS
 
0.0101122677.502250472.7799.9
Work Order00-00-00
Work Began10-02-23
Work Completed
Time Computed10-02-23
Contract Working Days365
Addl Days Granted365
Working Days Charged392
Percent Time Used53
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234036
Totals1122677.5047165.302250472.7799.9

CountyATASCOSA
HighwayFM0478
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6449-73-001
Proj IDRMC - 644973001
Work TypeSEAL COAT
 
0.0102429817.692740134.8699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-30-23
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged46
Percent Time Used71
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6449-73-001
INTERSTATE BARRICADES & MARKINGS, INC. (20.64)
Contract #10234025
Totals2429817.69729472.782740134.8699.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6450-04-001
Proj IDRMC - 645004001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101131650.00973887.7386.0
Work Order00-00-00
Work Began01-02-23
Work Completed
Time Computed01-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6450-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234026
Totals1131650.00129270.05973887.7386.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6450-06-001
Proj IDRMC - 645006001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101716300.001994629.6499.9
Work Order00-00-00
Work Began01-01-24
Work Completed
Time Computed01-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6450-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234212
Totals1716300.00287179.281994629.6499.9

CountyMEDINA
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-07-001
Proj IDRMC - 645107001
Work TypeDEBRIS REMOVAL
 
0.010713692.00574404.2580.4
Work Order00-00-00
Work Began01-02-23
Work Completed
Time Computed01-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
DIAMOND R CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234033
Totals713692.0059120.25574404.2580.4

CountyCOMAL
HighwayBI0035H
FromBI 35H
ToAT GUADALUPE RIVER
CSJ6459-47-001
Proj IDBPM - 645947001
Work TypeBRIDGE JOINT CLEANING AND SEALING
 
0.010479057.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed10-15-24
Contract Working Days31
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-47-001
INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
LONE STAR PAVING COMPANY (0.00)
Contract #07244035
Totals479057.420.000.000.0

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS
ToIN ATASCOSA COUNTY
CSJ6461-68-001
Proj IDRMC - 646168001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010716883.50114233.4915.9
Work Order00-00-00
Work Began05-13-24
Work Completed
Time Computed05-13-24
Contract Working Days730
Addl Days Granted0
Working Days Charged172
Percent Time Used23
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6461-68-001
THE RANGER CO (9.70)
Contract #01244028
Totals716883.500.00114233.4915.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToIN FRIO COUNTY
CSJ6461-69-001
Proj IDRMC - 646169001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010805476.80129006.2516.0
Work Order00-00-00
Work Began05-15-24
Work Completed
Time Computed05-15-24
Contract Working Days730
Addl Days Granted0
Working Days Charged170
Percent Time Used23
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6461-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244216
Totals805476.800.00129006.2516.0

CountyBEXAR
HighwayFM1976
FromIH 410
ToWALZEM RD
CSJ6463-41-001
Proj IDRMC - 646341001
Work TypeMILL AND INLAY
 
0.0101088977.581101377.6399.9
Work Order00-00-00
Work Began07-29-24
Work Completed
Time Computed06-17-24
Contract Working Days365
Addl Days Granted0
Working Days Charged95
Percent Time Used26
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6463-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244213
Totals1088977.580.001101377.6399.9