Monthly Local Let Maintenance Report For Tyler District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCHEROKEE
HighwayUS0069
FromPICNIC AREA MAINTENANCE
ToCHEROKEE COUNTY
CSJ6440-87-001
Proj IDSUP - 644087001
Work TypePICNIC AREA MAINTENANCE
 
0.01086247.8442376.7449.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-87-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00)
Contract #08231011
Totals86247.842513.9142376.7449.1

CountyCHEROKEE
HighwayUS0069
FromJACKSONVILLE/RUSK MAINTENANCE
ToCHEROKEE COUNTY
CSJ6440-89-001
Proj IDSUP - 644089001
Work TypeLITTER REMOVAL
 
0.010320427.00192046.8559.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-89-001
RUCON, INC. (100.00)
Contract #08231021
Totals320427.0021704.12192046.8559.9

CountySMITH
HighwayUS0069
FromTYLER MAINTENANCE SECTION
ToSMITH COUNTY
CSJ6440-91-001
Proj IDSUP - 644091001
Work TypeLITTER REMOVAL
 
0.010381232.85234563.8061.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-91-001
RUCON, INC. (100.00)
Contract #08231016
Totals381232.8521215.84234563.8061.5

CountyANDERSON
HighwayUS0084
FromPALESTINE MAINTENANCE SECTION
ToANDERSON COUNTY
CSJ6440-93-001
Proj IDSUP - 644093001
Work TypeLITTER REMOVAL
 
0.010211151.92113155.4453.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-93-001
ANDREWS CENTER (100.00)
Contract #08231022
Totals211151.920.00113155.4453.5

CountyWOOD
HighwayUS0069
FromMINEOLA MAINTENANCE SECTION
ToWOOD COUNTY
CSJ6440-95-001
Proj IDSUP - 644095001
Work TypeLITTER REMOVAL
 
0.010190504.2197844.5851.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231012
Totals190504.2119309.7397844.5851.3

CountyRUSK
HighwaySH0064
FromHENDERSON MAINTENANCE SECTION
ToRUSK OFFICE
CSJ6440-97-001
Proj IDSUP - 644097001
Work TypeLITTER REMOVAL
 
0.010267622.39171582.2664.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-97-001
RUCON, INC. (97.81)
Contract #08231013
Totals267622.3940701.07171582.2664.1

CountyVAN ZANDT
HighwayUS0080
FromCANTON MAINTENANCE SECTION
ToVAN ZANDT COUNTY
CSJ6446-42-001
Proj IDMMC - 644642001
Work TypeHYDRAULIC CEMENT
 
0.010317500.00256823.3480.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged395
Percent Time Used54
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6446-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231001
Totals317500.000.00256823.3480.8

CountyGREGG
HighwayUS0080
FromLONGVIEW AND HENDERSON MTCE SECTIONS
ToGREGG AND RUSK COUNTIES
CSJ6446-46-001
Proj IDMMC - 644646001
Work TypeEMULSION
 
0.010290100.0075796.9226.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-02-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged394
Percent Time Used53
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231003
Totals290100.000.0075796.9226.1

CountyWOOD
HighwayUS0080
FromMINEOLA AND CANTON MTCE SECTION
ToWOOD AND VAN ZANDT COUNTIES
CSJ6446-48-001
Proj IDMMC - 644648001
Work TypeEMULSION
 
0.010298400.00104728.3035.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-30-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged364
Percent Time Used49
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231004
Totals298400.0050.00104728.3035.0

CountyVAN ZANDT
HighwaySH0064
FromCANTON MTCE SECTION
ToVAN ZANDT COUNTY
CSJ6450-83-001
Proj IDRMC - 645083001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010179720.21179717.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed09-12-24
Time Computed00-00-00
Contract Working Days139
Addl Days Granted0
Working Days Charged112
Percent Time Used80
Contractor(s)
S FOWLER SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231001
Totals179720.210.00179717.52100.0

CountyRUSK
HighwayUS0079
FromHENDERSON MAINTENANCE SECTION
ToRUSK COUNTY
CSJ6450-85-001
Proj IDRMC - 645085001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010140728.61140735.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-15-24
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged74
Percent Time Used86
Contractor(s)
S FOWLER SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231002
Totals140728.6161386.60140735.1099.9

CountyANDERSON
HighwayUS0287
FromPALESTINE MAINTENANCE SECTION
ToANDERSON COUNTY
CSJ6451-01-001
Proj IDRMC - 645101001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010194976.11158944.0081.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged117
Percent Time Used95
Contractor(s)
S FOWLER SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231006
Totals194976.1175472.00158944.0081.5

CountyRUSK
HighwayFM1798
FromVARIOUS LOCATIONS
ToIN THE TYLER DISTRICT
CSJ6459-89-001
Proj IDBPM - 645989001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010143400.00107700.0075.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-03-24
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged25
Percent Time Used71
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6459-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06241001
Totals143400.0081150.00107700.0075.1

CountySMITH
HighwayUS0069
FromSMITH COUNTY
ToCHEROKEE COUNTY
CSJ6460-51-001
Proj IDMMC - 646051001
Work TypeEMULSION
 
0.010179310.0073104.4840.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6460-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231001
Totals179310.000.0073104.4840.7

CountyRUSK
HighwayFM1249
FromFM 1249 RUSK CO.
ToGREGG CO.
CSJ6463-57-001
Proj IDRMC - 646357001
Work TypePAVEMENT MARKINGS
 
0.010266909.75253168.4094.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-22-24
Work Completed
Time Computed00-00-00
Contract Working Days21
Addl Days Granted0
Working Days Charged11
Percent Time Used52
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6463-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241003
Totals266909.750.00253168.4094.8

CountyGREGG
HighwaySH0031
FromVARIOUS LOCATIONS
ToIN GREGG COUNTY
CSJ6464-13-001
Proj IDRMC - 646413001
Work TypeTREE REMOVAL
 
0.010173660.00160270.0092.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-30-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged149
Percent Time Used20
Contractor(s)
LG SOLAR, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04241002
Totals173660.0037225.00160270.0092.2

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN HENDERSON, ANDERSON,
ToSMITH, AND CHEROKEE COUNTIES
CSJ6466-81-001
Proj IDRMC - 646681001
Work TypeCRACK SEAL
 
0.0100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6466-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241003
Totals0.000.000.000.0

CountyWOOD
HighwaySH0154
FromVARIOUS ROADWAYS IN WOOD, VAN ZANDT,
ToGREGG, AND RUSK COUNTIES
CSJ6466-82-001
Proj IDRMC - 646682001
Work TypeCRACK SEAL
 
0.010199087.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6466-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241004
Totals199087.800.000.000.0

CountyWOOD
HighwaySL0564
FromMINEOLA AO/MO LAWN MTCE
ToMINEOLA AO/MO LAWN MTCE
CSJ6469-15-001
Proj IDSUP - 646915001
Work TypeGROUNDS MAINTENANCE
 
0.010106200.4215669.1114.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged107
Percent Time Used14
Contractor(s)
WORKQUEST
REDIRECTION OPPORTUNITIES
SUBCONTRACTOR(S) FOR CCSJ: 6469-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06241003
Totals106200.424457.1615669.1114.7

CountyVAN ZANDT
HighwaySH0019
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6470-09-001
Proj IDEMC - 647009001
Work TypeDEBRIS REMOVAL
 
0.0107198590.007167531.22100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-28-24
Work Completed09-19-24
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged52
Percent Time Used86
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6470-09-001
DREWERY BROS. TREE SERVICE, INC. (12.45)
KENT TREE SERVICE LLC (12.45)
NEXT CONSTRUCTION SOLUTIONS LLC (0.09)
Contract #06241002
Totals7198590.000.007167531.22100.0

page 1 | page 2 | page 3 | page 4