Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHILL ETC
HighwayIH 35 ETC
FromCOUNTY LINE ROAD
ToSH 81
CSJ0014-07-105
Proj IDSTP 2B20(189)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
75.5825295309.252212272.7541.7
Work Order09-08-20
Work Began11-30-20
Work Completed
Time Computed10-08-20
Contract Working Days210
Addl Days Granted2
Working Days Charged111
Percent Time Used52
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203065
Totals5295309.25263461.252212272.7541.7

CountyMCLENNAN
HighwayIH 35
FromN LP 340
ToCRAVEN AVE
CSJ0015-01-226
Proj IDNH 2019(312)
Work TypeCNSTR FLUSH MEDIAN/DRNG&CONCTRAFBAR
 
1.24610654777.909107388.9885.4
CountyMCLENNAN
HighwayIH 35
FromS LP 340
ToN LP 340
CSJ0015-01-234
Proj IDNH 1402(012)
Work TypeACQ, RELOC, ASSIST, & ADJ, OF UTIL.
 
7.9296056337.0011764409.5099.9
CountyMCLENNAN
HighwayIH 35
From12TH STREET
ToN LP 340
CSJ0015-01-243
Proj IDNH 2019(312)
Work TypeWDN, GR, STRS, & SURF
 
4.580305112618.35247867124.0180.1
CountyMCLENNAN
HighwayIH 35
From12TH STREET
ToBU 77
CSJ0015-01-244
Proj IDNH 2019(312)
Work TypeREPL BR
 
2.54619391266.7514008325.2572.2
Work Order01-31-19
Work Began04-29-19
Work Completed
Time Computed04-01-19
Contract Working Days1,150
Addl Days Granted0
Working Days Charged643
Percent Time Used55
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-01-226
PMI PAVEMENT MARKING, LLC (0.28)
ALTUS TRAFFIC MANAGEMENT LLC (0.08)
STRAIGHT LINE SAWING & SEALING, INC. (0.17)
ANTIGO CONSTRUCTION, INC. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.72)
BOWMAN ENGINEERING & CONSULTING, INC. (1.03)
A BROTHERS MILLING, LLC (0.17)
ADCOCK 4 INVESTMENTS, LLC (1.71)
RENAISSANCE CONTRACTORS, INC. (8.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
ADRIAN CONTRACTING (0.02)
CND CONTRACTING (0.86)
DBI SERVICES, LLC (0.40)
C-HOP CONSTRUCTION (0.49)
KNIFE RIVER CORPORATION - SOUTH (5.97)
COWBOY AND SONS LP DBA COWBOY TRUCKING (0.31)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.98)
ROADWAY SPECIALTIES, INC. (0.15)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (3.75)
B-CORP UTILITIES INC (1.61)
AREA WIDE PROTECTIVE, INC. (0.13)
SOUTH TEXAS PAINTING COMPANY (0.07)
GILLIAM CONTRACTING, INC. (1.41)
K.B.L. CONSTRUCTION, LLC (0.36)
BEAIRD DRILLING (1.12)
GK CONSTRUCTION, LLC (0.05)
ANCORTEX, INC. (0.90)
FLASHER EQUIPMENT COMPANY (0.12)
TX DOWN UNDER CONSTRUCTION LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38)
STEEL EFFECTS (0.08)
RAY"S THREADING AND FAB SHOP (0.31)
INDUS ROAD & BRIDGE, INC (1.52)
URBAN INFRACONSTRUCTION, LLC. (1.37)
BLACK ROCK CONSTRUCTION (0.08)
HB FARMER FOUNDATION, LLC (0.77)
U.S. UNDERWATER SERVICES, LP (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.03)
CAPITAL PUMPING, LP (0.05)
STRUCTURAL TECHNOLOGIES, LLC (0.00)
SCOTT DERR PAINTING CO, LLC (0.02)
PENHALL COMPANY (0.09)
CHOCTAW ERECTORS, INC. (0.44)
FORT WORTH CIVIL CONSTRUCTORS, LLC (0.35)
U.S. UNDERWATER SERVICES, LP (0.00)
MONARREZ TRUCKING LLC. (0.53)
B&R WELDING AND MECHANICAL SERVICE LLC (0.01)
AMERICAN INSHORE DIVERS CORP. (0.00)
T-BAR FENCE, INC. (0.01)
TORO BRAVO CONSTRUCTION, LLC (0.88)
Contract #12183001
Totals341215000.006593400.79282747247.7481.8

CountyBELL
HighwayIH 35
From0.5 MI S OF FM 436
ToFM 436
CSJ0015-06-087
Proj IDC 15-6-87
Work TypeOVERLAY
 
1.5711390231.41247970.1517.8
Work Order04-08-21
Work Began06-21-21
Work Completed
Time Computed05-10-21
Contract Working Days45
Addl Days Granted0
Working Days Charged4
Percent Time Used8
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-06-087
CHEROKEE SERVICES (4.10)
PINNACLE GRINDING AND GROOVING LLC (0.27)
PMI PAVEMENT MARKING, LLC (4.80)
TEXAS TRAFFIC AND BARRICADE, LLC (0.42)
TEX OP CONSTRUCTION, LP (5.85)
Contract #03213214
Totals1390231.41247970.15247970.1517.8

CountyHILL
HighwayIH 35E
FromIH 35W
ToELLIS CO LINE
CSJ0048-09-029
Proj IDNH 2019(834)
Work TypeWIDEN FREEWAY
 
7.887117517085.9859649877.6950.7
Work Order06-18-19
Work Began09-09-19
Work Completed
Time Computed07-18-19
Contract Working Days1,090
Addl Days Granted0
Working Days Charged532
Percent Time Used48
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 0048-09-029
ROADWAY SPECIALTIES, INC. (0.60)
PROTEX EROSION CONTROL, LLC (1.21)
ALTUS TRAFFIC MANAGEMENT LLC (0.22)
TEXAS SCORPION HAULERS LLC, DBA TEXAS PRIDE HAULERS (2.26)
KLP COMMERCIAL, L.L.C. (2.12)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
BIG CREEK CONSTRUCTION, LTD. (8.88)
Q. ROBERTS TRUCKING INCORPORATED (4.98)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (1.53)
ALAVA INTERNATIONAL, INC. (1.04)
A.Z. REBAR CONSTRUCTION, INC. (0.77)
PMI PAVEMENT MARKING, LLC (0.51)
FARR FOUNDATION, INC. (1.22)
DUSTROL, INC. (0.65)
DBI SERVICES, LLC (0.00)
BROOKLYN SWEEPS, INCORPORATED (0.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.92)
BEAIRD DRILLING (0.48)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.11)
O. TREVINO CONSTRUCTION, LLC (0.11)
W.O.E. CONSTRUCTION, INC. (0.00)
BRENDA PRICE TRUCKING (0.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24)
ANTIGO CONSTRUCTION, INC. (0.16)
PRIMATE CONSTRUCTION, LP (0.00)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
EVANS AND SONS PORTABLE ROCK CRUSHING, LLC (0.45)
Contract #05193001
Totals117517085.982650418.4359649877.6950.7

CountyMCLENNAN ETC
HighwaySH 6
FromSL 340
ToFALLS COUNTY LINE
CSJ0049-01-099
Proj IDSTP 2B20(186)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
36.3266830728.001236452.8818.1
Work Order09-18-20
Work Began05-10-21
Work Completed
Time Computed10-19-20
Contract Working Days240
Addl Days Granted0
Working Days Charged90
Percent Time Used37
Contractor(s)
MASSANA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-01-099
AREA WIDE PROTECTIVE, INC. (0.31)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (11.43)
Contract #08203062
Totals6830728.00922987.811236452.8818.1

CountyMCLENNAN
HighwayUS 84
FromSH 317
ToOAK CREEK DRIVE
CSJ0055-07-062
Proj IDF 2021(407)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.5781857024.50215433.5011.6
Work Order04-16-21
Work Began06-02-21
Work Completed
Time Computed05-17-21
Contract Working Days105
Addl Days Granted0
Working Days Charged16
Percent Time Used15
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0055-07-062
COMEN ENTERPRISE LLC (6.00)
Contract #03213017
Totals1857024.50215433.50215433.5011.6

CountyMCLENNAN
HighwayUS 84
FromHARRIS CREEK RD
ToSOUTH BOSQUE RIVER
CSJ0055-08-099
Proj IDNH 2018(346)
Work TypeGR, STRS & SURF
 
1.91320587594.9622851030.2799.9
Work Order03-12-18
Work Began04-16-18
Work Completed
Time Computed04-11-18
Contract Working Days595
Addl Days Granted19
Working Days Charged601
Percent Time Used97
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-099
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.04)
BOWMAN ENGINEERING & CONSULTING, INC (0.53)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SAN-ANN-CO., INC. (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.70)
PRIMATE CONSTRUCTION, INC. (0.09)
ROADWAY SPECIALTIES, INC. (1.18)
S & S BRIDGE PAINTING, INC. (0.03)
STRIPING TECHNOLOGY, L.P. (0.79)
WOLFE CONSTRUCTION GROUP, INC. (0.18)
PIPE WHOLESALERS OF TEXAS, INC. (7.06)
BOWMAN ENGINEERING & CONSULTING, INC. (0.04)
KRL CONSTRUCTION INC. (0.03)
Contract #02183005
Totals20587594.960.0022851030.2799.9

CountyMCLENNAN
HighwayUS 84
From0.15 MI W OF LAKE AIR DRIVE
ToFM 933
CSJ0055-15-072
Proj IDF 2021(567)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.4829930693.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-21
Work Began00-00-00
Work Completed
Time Computed09-15-21
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0055-15-072
DALLAS LITE AND BARRICADE, INC. (0.68)
BARRON ENVIRONMENTAL, L.P. (0.11)
STRIPING TECHNOLOGY, L.P. (2.14)
RADKE CONSTRUCTION SERVICES (RCS) LLC (2.55)
Contract #05213205
Totals9930693.780.000.000.0

CountyHAMILTON
HighwayFM 218
FromSH 36
ToFM 2486
CSJ0120-05-026
Proj IDSTP 2020(564)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.6075387759.044837024.8589.7
Work Order04-14-20
Work Began05-18-20
Work Completed
Time Computed05-14-20
Contract Working Days240
Addl Days Granted10
Working Days Charged244
Percent Time Used97
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0120-05-026
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.11)
D. I. J. CONSTRUCTION, INC. (1.29)
R K STEPHENS CONSTRUCTION, LLC (2.00)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.61)
ROADWAY SPECIALTIES, INC. (2.93)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.42)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
ACME BARRICADES, LLC (0.35)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #02203207
Totals5387759.04621144.014837024.8589.7

CountyHILL
HighwaySH 22
From1.23 MI W OF IH 35
To0.44 MI E OF IH 35
CSJ0121-03-063
Proj IDNH 2021(080)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.6841051927.65875711.2783.2
Work Order12-15-20
Work Began05-21-21
Work Completed
Time Computed01-14-21
Contract Working Days45
Addl Days Granted0
Working Days Charged33
Percent Time Used73
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0121-03-063
ROADWAY SPECIALTIES, INC. (2.83)
STRIPING TECHNOLOGY, L.P. (4.26)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.36)
TOTAL HIGHWAY MAINTENANCE, LLC (0.43)
Contract #11203225
Totals1051927.65760188.27875711.2783.2

CountyMCLENNAN
HighwaySH 31
FromUS 84
ToHILL COUNTY LINE
CSJ0162-01-098
Proj IDSTP 2B20(188)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.8481652981.551454272.5587.9
CountyHILL
HighwaySH 31
FromHILL COUNTY LINE
ToSOUTH BS31 IN MT CALM
CSJ0162-02-043
Proj IDSTP 2B20(188)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001729682.24605959.5783.0
CountyHILL
HighwaySH 31
FromNORTH BS 31 IN MT CALM
ToCR 3344
CSJ0162-02-044
Proj IDSTP 2B20(188)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.383473867.10388496.3481.9
CountyHILL
HighwaySH 31
FromSOUTH BS31 IN MT CALM
ToNORTH BS31 IN MT CALM
CSJ0162-12-002
Proj IDSTP 2B20(188)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.731187709.11149180.9079.4
Work Order09-18-20
Work Began01-14-21
Work Completed
Time Computed10-18-20
Contract Working Days120
Addl Days Granted0
Working Days Charged88
Percent Time Used73
Contractor(s)
MASSANA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-01-098
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (11.42)
AREA WIDE PROTECTIVE, INC. (0.27)
DUSTIN ALLEN, INC. (6.57)
Contract #08203064
Totals3044240.00557320.892597909.3685.3

CountyHAMILTON
HighwaySH 36
FromUS 281
ToCORYELL CO LINE
CSJ0183-03-050
Proj IDSTP 2019(839)
Work TypeREHABILITATION OF EXISTING ROAD
 
15.81312587706.0912956618.8999.9
Work Order06-20-19
Work Began08-05-19
Work Completed
Time Computed07-20-19
Contract Working Days330
Addl Days Granted5
Working Days Charged331
Percent Time Used98
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0183-03-050
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.64)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.30)
ROADWAY SPECIALTIES, INC. (3.70)
D. I. J. CONSTRUCTION, INC. (2.30)
SAN-ANN-CO., INC. (1.07)
SCR CIVIL CONSTRUCTION, LLC (2.21)
S & S BRIDGE PAINTING, INC. (2.16)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
J & M CONTRACTING, COMPANY (2.41)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.30)
AREA WIDE PROTECTIVE, INC. (1.52)
Contract #05193209
Totals12587706.0910663.0012956618.8999.9

CountyBELL
HighwayUS 190
From2.0 MI S OF FM 436 IN HEIDENHEIMER
ToMILAM C/L
CSJ0185-01-030
Proj IDNH 2019(599)
Work TypeWIDEN NON-FREEWAY
 
9.47077807569.0419249494.7924.7
Work Order04-21-20
Work Began06-01-20
Work Completed
Time Computed05-21-20
Contract Working Days904
Addl Days Granted0
Working Days Charged259
Percent Time Used28
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0185-01-030
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.73)
D. I. J. CONSTRUCTION, INC. (0.40)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03)
SCOTT DERR PAINTING CO, LLC (0.01)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
ROADWAY SPECIALTIES, INC. (1.00)
A BROTHERS MILLING, LLC (0.81)
GK CONSTRUCTION, LLC (0.32)
LONNIE LISCHKA COMPANY, INC. (0.00)
LONE STAR PAVING COMPANY (25.08)
TEXAS ALTERNATIVE GRASSER INCORPORATED (1.41)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.93)
WYLIE DRILLING & DRAINAGE, INC. (1.37)
PIONEER UTILITIES, INC. (1.84)
JL3 CONSTRUCTION SERVICES LLC (1.16)
GRINDER SWITCH TRUCKING, LLC (0.19)
LONNIE LISCHKA COMPANY, L.P. (8.70)
PANTHER CREEK TRANSPORTATION, INC. (0.75)
POTTER TRUCKING (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #11193201
Totals77807569.04851522.2319249494.7924.7

CountyMCLENNAN
HighwaySL 2
FromUS 84 (WACO DRIVE)
ToIH 35
CSJ0209-01-068
Proj IDC 209-1-68
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.8071886100.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0209-01-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213020
Totals1886100.890.000.000.0

CountyHILL
HighwayFM 933
From0.2 MI N OF FM 1304
To0.2 MI S OF FM 1304
CSJ0209-06-040
Proj IDF 2021(549)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.410114358.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-21
Work Began00-00-00
Work Completed
Time Computed07-22-21
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0209-06-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213035
Totals114358.600.000.000.0

CountyCORYELL
HighwayBU 190E
FromFM 1113 (AVENUE D)
ToCONSTITUTION DR.
CSJ0231-02-062
Proj IDNH 2020(690)
Work TypeTRANSPORTATION NON-ROADWAY
 
1.2184762516.85966996.1820.3
Work Order10-21-20
Work Began12-08-20
Work Completed
Time Computed11-20-20
Contract Working Days300
Addl Days Granted0
Working Days Charged107
Percent Time Used35
Contractor(s)
TTG UTILITIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0231-02-062
ENVIRONMENTAL SAFETY SERVICES, INC. (0.69)
A BROTHERS MILLING, LLC (1.52)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.42)
TIGHT LINE CONSTRUCTION, LLC (3.49)
D. I. J. CONSTRUCTION, INC. (1.50)
TEXAS MATERIALS GROUP, INC. (17.71)
Contract #09203206
Totals4762516.85114719.01966996.1820.3

CountyCORYELL
HighwayBU 190E
FromFM 116
ToROBERT GRIFFIN III BLVD
CSJ0231-02-064
Proj IDSTP 2B20(063)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.772905128.20500104.0055.2
Work Order08-14-20
Work Began04-20-21
Work Completed
Time Computed09-14-20
Contract Working Days105
Addl Days Granted0
Working Days Charged41
Percent Time Used39
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0231-02-064
D. I. J. CONSTRUCTION, INC. (1.19)
KRL CONSTRUCTION INC. (10.69)
Contract #07203227
Totals905128.2067240.00500104.0055.2

CountyBELL
HighwayUS 190
FromFM 3423 (INDIAN TRAIL)
To0.25 MI W OF PADDY HAMILTON
CSJ0231-03-145
Proj IDNH 2019(651)
Work TypeWF
 
7.17444733665.5926516619.5359.2
Work Order07-17-19
Work Began09-17-19
Work Completed
Time Computed08-16-19
Contract Working Days375
Addl Days Granted1
Working Days Charged331
Percent Time Used88
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-145
PIONEER UTILITIES, INC. (1.76)
GK CONSTRUCTION, LLC (0.42)
A BROTHERS MILLING, LLC (0.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
MICA CORPORATION (8.93)
PRIMATE CONSTRUCTION, LP (0.70)
ROADWAY SPECIALTIES, INC. (1.17)
D&S TEXAS ICON CONSTRUCTION (0.76)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.34)
BEAIRD DRILLING (1.46)
LONE STAR PAVING COMPANY (34.77)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.26)
S&S BRIDGE PAINTING (0.87)
LONE STAR GRADING & MATERIALS, LTD. (0.13)
MCL CONTRACTING, LLC (0.06)
HOUSTON SAWING & DRILLING (0.02)
Contract #06193004
Totals44733665.59802148.9926516619.5359.2

CountyBELL
HighwayIH 14
FromE CENTRAL TEXAS EXPY W
ToE CENTRAL TEXAS EXPY E
CSJ0231-03-147
Proj IDSTP 2020(941)MM
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
3098000.00747046.9524.1
Work Order08-18-20
Work Began10-05-20
Work Completed
Time Computed09-17-20
Contract Working Days240
Addl Days Granted0
Working Days Charged101
Percent Time Used42
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-147
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.76)
BEAIRD DRILLING (2.96)
BREDA COMPANY, INC. (0.61)
FORTSON CONTRACTING, INC. (0.90)
GRINDER SWITCH TRUCKING, LLC (0.77)
LONE STAR PAVING COMPANY (14.48)
PENHALL COMPANY (0.15)
PIONEER UTILITIES, INC. (11.10)
ROADWAY SPECIALTIES, INC. (0.40)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.00)
TRP CONSTRUCTION GROUP, LLC (0.75)
GK CONSTRUCTION, LLC (0.00)
Contract #07203213
Totals3098000.0079730.00747046.9524.1

CountyBELL
HighwayIH 14
FromCORYELL COUNTY LINE
To0.5 MI WEST OF FM 3423
CSJ0231-03-152
Proj IDNH 2021(228)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4573812.501384924.7430.2
Work Order03-05-21
Work Began04-26-21
Work Completed
Time Computed04-05-21
Contract Working Days210
Addl Days Granted0
Working Days Charged28
Percent Time Used13
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-152
BREDA COMPANY, INC. (0.10)
FC TRAFFIC CONTROL, INC. (0.71)
Contract #01213006
Totals4573812.50767882.921384924.7430.2