Monthly State Let Construction Report For Waco District As Of Nov 10, 2024 Page 4 Of 4
Last Update: Sunday, November 10, 2024
 |
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HILL |
Highway | FM 2959 |
From | SH 81 |
To | US 77 |
CSJ | 3030-01-010 |
Proj ID | C 3030-1-10 |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 6.932 | 12787365.87 | | 6376254.46 | 49.8 |
Work Order | 02-02-24 |
Work Began | 04-01-24 |
Work Completed | |
Time Computed | 03-03-24 |
Contract Working Days | 202 |
Addl Days Granted | 0 |
Working Days Charged | 125 |
Percent Time Used | 61 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3030-01-010 BEAR CREEK CONSTRUCTION, LLC (20.69) D. I. J. CONSTRUCTION, INC. (0.79) COLD CREEK CONSTRUCTION, LTD (1.02) FORTSON CONTRACTING, INC. (0.67) KING GEORGE TRAFFIC SOLUTIONS LLC (0.16) PROFESSIONAL TRAFFIC CONTROL LLC (0.10) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.55) DALLAS LITE AND BARRICADE, INC. (0.01) HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.09)
|
Contract # | 01243008 |
| Totals | 12787365.87 | 1468699.70 | 6376254.46 | 49.8 |
|
County | MCLENNAN |
Highway | FM 3268 |
From | FM 185 |
To | FM 3047 |
CSJ | 3448-02-007 |
Proj ID | F 2B23(075) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.305 | 2735685.61 | | 2941348.01 | 99.9 |
Work Order | 09-08-23 |
Work Began | 10-19-23 |
Work Completed | |
Time Computed | 10-08-23 |
Contract Working Days | 105 |
Addl Days Granted | 0 |
Working Days Charged | 87 |
Percent Time Used | 82 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 3448-02-007 HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.81) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.58) J. H. ODEN CONTRACTING COMPANY (2.44) MURRAY CONSTRUCTION (0.72) WEST TEXAS ROCK RESOURCES, LLC (0.25) BEAR CREEK CONSTRUCTION, LLC (13.95) D. I. J. CONSTRUCTION, INC. (1.01)
|
Contract # | 08233036 |
| Totals | 2735685.61 | 0.00 | 2941348.01 | 99.9 |
|
County | CORYELL |
Highway | SH 9 |
From | SH 9 |
To | BU 190 |
CSJ | 3623-01-008 |
Proj ID | F 2024(911) |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| | 1170676.75 | | 598151.94 | 51.0 |
Work Order | 05-28-24 |
Work Began | 07-03-24 |
Work Completed | |
Time Computed | 06-27-24 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 32 |
Percent Time Used | 53 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 3623-01-008 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (15.29) D. I. J. CONSTRUCTION, INC. (7.21) HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.05) MARCOMS CONSTRUCTION LLC (6.54) PROFESSIONAL TRAFFIC CONTROL LLC (0.54) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.09) TEXAS MATERIALS GROUP, INC. (14.31) WILKO INDUSTRIAL, L.L.C. (8.14)
|
Contract # | 04243220 |
| Totals | 1170676.75 | 9411.00 | 598151.94 | 51.0 |
|