Monthly Local Let Maintenance Report For Yoakum District As Of Jan 10, 2023 Page 1 Of 5

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWHARTON
HighwayUS0059
FromWHARTON, MATAGORDA,
ToAUSTIN & COLORADO COUNTIES
CSJ6245-16-001
Proj IDRMC - 624516001
Work TypeCRACK SEAL
 
0.001156979.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NA-TEX
SUBCONTRACTOR(S) FOR CCSJ: 6245-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09121302
Totals156979.900.000.000.0

CountyDEWITT
HighwayUS0183
FromDEWITT, LAVACA
ToAND GONZALES COUNTIES
CSJ6249-91-001
Proj IDRMC - 624991001
Work TypePAVEMENT MARKINGS ON-CALL
 
0.001147738.7557269.5938.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-18-13
Work Began01-23-13
Work Completed
Time Computed01-23-13
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10121302
Totals147738.750.0057269.5938.7

CountyVICTORIA
HighwayUS0059
FromVICTORIA, CALHOUN
ToAND JACKSON
CSJ6249-95-001
Proj IDRMC - 624995001
Work TypePAVEMENT MARKINGS ON-CALL
 
0.001176320.00111833.2163.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-13
Work Began02-01-13
Work Completed
Time Computed02-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10121303
Totals176320.000.00111833.2163.4

CountyFAYETTE
HighwaySH0071
FromFAYETTE AND
ToCOLORADO COUNTIES
CSJ6249-96-001
Proj IDRMC - 624996001
Work TypePAVEMENT MARKING ON-CALL
 
0.001175270.0074213.3242.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-16-13
Work Began01-23-13
Work Completed
Time Computed01-23-13
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10121304
Totals175270.000.0074213.3242.3

CountyAUSTIN
HighwayFM1458
FromAT SAN FELIPE DE AUSTIN HISTORICAL SITE
ToIN AUSTIN COUNTY
CSJ6335-09-001
Proj IDRMC - 633509001
Work TypeCONSTRUCTION OF SIDEWALKS/PARKING LOT
 
0.001246913.00236279.1595.6
Work Order00-00-00
Work Began11-04-19
Work Completed
Time Computed11-11-19
Contract Working Days30
Addl Days Granted5
Working Days Charged35
Percent Time Used100
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6335-09-001
LONE STAR PAVING COMPANY (15.13)
CEN TEX HYDROSEED, INC. (2.51)
Contract #07191302
Totals246913.000.00236279.1595.6

CountyJACKSON
HighwayFM3131
FromJACKSON COUNTY
To.
CSJ6344-00-001
Proj IDRMC - 634400001
Work TypeSMALL / LARGE ROADSIDE SIGN ASSEMBLIES
 
0.00159845.00287527.5199.9
Work Order00-00-00
Work Began11-13-19
Work Completed
Time Computed11-20-19
Contract Working Days30
Addl Days Granted0
Working Days Charged9
Percent Time Used30
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6344-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05191303
Totals59845.000.00287527.5199.9

CountyDEWITT
HighwayUS0183
FromDEWITT COUNTY
To.
CSJ6347-81-001
Proj IDSUP - 634781001
Work TypePICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.00127040.008320.00100.0
Work Order00-00-00
Work Began09-01-19
Work Completed05-14-20
Time Computed09-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged238
Percent Time Used32
Contractor(s)
WORKQUEST
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6347-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08191302
Totals27040.001184.008320.00100.0

CountyAUSTIN
HighwayFM0109
FromAUSTIN, COLORADO, JACKSON, AND
ToWHARTON COUNTIES
CSJ6350-33-001
Proj IDRMC - 635033001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
0.010241971.55700426.8699.9
Work Order00-00-00
Work Began05-24-21
Work Completed
Time Computed05-31-21
Contract Working Days30
Addl Days Granted28
Working Days Charged57
Percent Time Used98
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6350-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211313
Totals241971.550.00700426.8699.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA COUNTY
To.
CSJ6350-35-001
Proj IDRMC - 635035001
Work TypeON CALL SWEEPING
 
0.00152060.613985.917.6
Work Order00-00-00
Work Began03-08-21
Work Completed
Time Computed03-15-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
SWEEPING CORPORATION OF AMERICA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6350-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12201309
Totals52060.610.003985.917.6

CountyFAYETTE
HighwayIH0010
FromFAYETTE, ETC.
To.
CSJ6356-24-001
Proj IDMMC - 635624001
Work TypeHYDRAULIC CEMENT
 
0.010328000.006125.001.8
Work Order00-00-00
Work Began11-01-22
Work Completed
Time Computed11-01-22
Contract Working Days120
Addl Days Granted0
Working Days Charged61
Percent Time Used50
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6356-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09221305
Totals328000.000.006125.001.8

CountyGONZALES
HighwayIH0010
FromGONZALES COUNTY
To.
CSJ6356-33-001
Proj IDMMC - 635633001
Work TypeFLEXIBLE BASE (MATERIAL ONLY)
 
0.00120680.0020574.53100.0
Work Order00-00-00
Work Began06-24-20
Work Completed07-28-21
Time Computed06-24-20
Contract Working Days120
Addl Days Granted0
Working Days Charged92
Percent Time Used76
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6356-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03201307
Totals20680.000.0020574.53100.0

CountyCOLORADO
HighwayIH0010
FromDISTRICT WIDE
To.
CSJ6358-83-001
Proj IDRMC - 635883001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010337822.20339195.0099.9
Work Order00-00-00
Work Began01-18-22
Work Completed
Time Computed01-25-22
Contract Working Days60
Addl Days Granted0
Working Days Charged77
Percent Time Used128
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6358-83-001
BEAVER BOYS SERVICES LLC (90.00)
Contract #10211310
Totals337822.200.00339195.0099.9

CountyGONZALES
HighwayIH0010
FromGONZALES, FAYETTE, AND COLORADO
ToCOUNTIES
CSJ6368-67-001
Proj IDRMC - 636867001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010324377.28310053.3495.5
Work Order00-00-00
Work Began07-06-21
Work Completed
Time Computed07-13-21
Contract Working Days730
Addl Days Granted0
Working Days Charged531
Percent Time Used72
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6368-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211314
Totals324377.2874744.94310053.3495.5

CountyCALHOUN
HighwaySH0035
FromCALHOUN COUNTY
To.
CSJ6368-70-001
Proj IDRMC - 636870001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
204508.00132610.0064.8
Work Order00-00-00
Work Began07-01-21
Work Completed
Time Computed07-08-21
Contract Working Days730
Addl Days Granted0
Working Days Charged536
Percent Time Used73
Contractor(s)
CLASSIC IRRIGATION & LANDSCAPE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6368-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211315
Totals204508.000.00132610.0064.8

CountyCOLORADO
HighwaySH0071
FromCOLORADO COUNTY
To.
CSJ6368-71-001
Proj IDRMC - 636871001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
245398.32257483.7899.9
Work Order00-00-00
Work Began06-28-21
Work Completed
Time Computed07-06-21
Contract Working Days730
Addl Days Granted0
Working Days Charged538
Percent Time Used73
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6368-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211316
Totals245398.3234190.46257483.7899.9

CountyAUSTIN
HighwaySH0036
FromAUSTIN COUNTY
To.
CSJ6368-75-001
Proj IDRMC - 636875001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
208179.20307801.2799.9
Work Order00-00-00
Work Began07-31-21
Work Completed
Time Computed08-07-21
Contract Working Days730
Addl Days Granted0
Working Days Charged506
Percent Time Used69
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6368-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211317
Totals208179.207668.03307801.2799.9

CountyWHARTON
HighwayUS0059
FromWHARTON, ETC.
To.
CSJ6374-51-001
Proj IDMMC - 637451001
Work TypeROCK/RIPRAP
 
0.010120000.0062089.82100.0
Work Order00-00-00
Work Began08-05-21
Work Completed08-01-22
Time Computed08-09-21
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211340
Totals120000.0020971.3162089.82100.0

CountyJACKSON
HighwaySH0111
FromJACKSON COUNTY
To.
CSJ6377-67-001
Proj IDRMC - 637767001
Work TypeJANITORIAL MAINTENANCE
 
0.01010186.0013035.0099.9
Work Order00-00-00
Work Began05-27-21
Work Completed
Time Computed05-27-21
Contract Working Days365
Addl Days Granted365
Working Days Charged578
Percent Time Used79
Contractor(s)
ALPHA AND OMEGA CLEANING SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04211301
Totals10186.00720.0013035.0099.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA COUNTY
To.
CSJ6377-90-001
Proj IDRMC - 637790001
Work TypeJANITORIAL MAINTENANCE
 
0.01019336.0034020.0099.9
Work Order00-00-00
Work Began05-25-21
Work Completed
Time Computed05-26-21
Contract Working Days365
Addl Days Granted365
Working Days Charged579
Percent Time Used79
Contractor(s)
ALPHA AND OMEGA CLEANING SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04211302
Totals19336.001920.0034020.0099.9

CountyGONZALES
HighwayUS0090
FromGONZALES COUNTY, ETC.
To.
CSJ6378-41-001
Proj IDRMC - 637841001
Work TypeMILLING
 
0.010205848.46218479.1499.9
Work Order00-00-00
Work Began08-10-21
Work Completed
Time Computed08-17-21
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6378-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211341
Totals205848.460.00218479.1499.9

page 1 | page 2 | page 3 | page 4 | page 5