Monthly Local Let Maintenance Report For Yoakum District As Of Nov 10, 2024 Page 4 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJACKSON
HighwayUS0059
FromJACKSON, ETC.
To.
CSJ6467-58-001
Proj IDRMC - 646758001
Work TypeRAISED PAVEMENT MARKERS
 
0.010200809.50227468.4099.9
Work Order00-00-00
Work Began10-07-24
Work Completed
Time Computed10-14-24
Contract Working Days45
Addl Days Granted0
Working Days Charged3
Percent Time Used6
Contractor(s)
TRP INFRASTRUCTURE SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6467-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241330
Totals200809.50227468.40227468.4099.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND DEWITT COUNTIES
To.
CSJ6467-66-001
Proj IDSUP - 646766001
Work TypeSTATE USE CONTRACT
 
0.01069248.747875.2411.3
Work Order00-00-00
Work Began07-27-24
Work Completed
Time Computed07-27-24
Contract Working Days730
Addl Days Granted0
Working Days Charged91
Percent Time Used12
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6467-66-001
RUCON, INC. (0.00)
Contract #07241301
Totals69248.742645.017875.2411.3

CountyJACKSON
HighwayUS0059
FromCALHOUN, COLORADO, FAYETTE, GONZALES,
ToJACKSON, LAVACA, AND MATAGORDA
CSJ6468-56-001
Proj IDRMC - 646856001
Work TypeDEBRIS REMOVAL
 
0.010234300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-24
Work Completed
Time Computed11-11-24
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6468-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241307
Totals234300.000.000.000.0

CountyFAYETTE
HighwayIH0010
FromFAYETTE, GONZALES, COLORADO, AND
ToAUSTIN COUNTIES
CSJ6468-74-001
Proj IDSUP - 646874001
Work TypeSTATE USE CONTRACT
 
0.010752122.00206037.7827.3
Work Order00-00-00
Work Began07-20-24
Work Completed
Time Computed07-20-24
Contract Working Days180
Addl Days Granted185
Working Days Charged98
Percent Time Used26
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6468-74-001
RUCON, INC. (0.00)
Contract #07241302
Totals752122.0076531.16206037.7827.3

CountyDEWITT
HighwayUS0183
FromDEWITT COUNTY
To.
CSJ6470-57-001
Proj IDMMC - 647057001
Work TypeHOT-MIX COLD-LAID
 
0.010272155.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-30-24
Work Completed
Time Computed11-01-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241301
Totals272155.000.000.000.0

CountyCOLORADO
HighwayIH0010
FromDISTRICTWIDE WITH EXCEPTION OF CALHOUN
ToAND MATAGORDA.
CSJ6471-98-001
Proj IDMMC - 647198001
Work TypeSNOW AND ICE CONTROL
 
0.010106400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-31-24
Work Completed
Time Computed11-01-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6471-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241302
Totals106400.000.000.000.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND WHARTON COUNTIES
To.
CSJ6473-67-001
Proj IDSUP - 647367001
Work TypeSTATE USE CONTRACT
 
0.010613279.440.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-67-001
RUCON, INC. (0.00)
Contract #10241301
Totals613279.440.000.000.0

page 1 | page 2 | page 3 | page 4