Monthly State Let Construction Report For Amarillo District As Of Nov 10, 2024 Page 1 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.701693926.6778.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began09-29-20
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged111
Percent Time Used60
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
CONCRETE CONNECTION (5.15)
FC TRAFFIC CONTROL, INC. (1.57)
LINEAR TRAFFIC MARKINGS LLC (1.67)
CONCRETE CONNECTION, LLC (5.15)
CIRCLE FOUR ENTERPRISES, LLC (1.15)
MEDELLIN HDD LLC (0.86)
BARRICADES UNLIMITED (1.80)
TURKEY CREEK HDD, LLC (0.83)
Contract #03193227
Totals2152762.70634718.011693926.6778.6

CountyHEMPHILL
HighwayUS 60
FromBIRCH STREET IN CANADIAN
ToFM 2388
CSJ0030-06-060
Proj IDF 2023(455)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.85013300304.6610804412.5781.2
CountyHEMPHILL
HighwayUS 60
FromFM 2388
ToC&G N OF CANADIAN
CSJ0030-06-067
Proj IDC 30-6-67
Work TypeSAFETY IMPROVEMENT PROJECTS
 
105295.750.000.0
Work Order04-04-23
Work Began05-11-23
Work Completed
Time Computed05-04-23
Contract Working Days305
Addl Days Granted0
Working Days Charged201
Percent Time Used65
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-060
DK CONTRACTING, LLC (0.37)
HJC FARMS, INC. (0.47)
PBJ CONSTRUCTION (1.66)
APOLLO CONSTRUCTORS, INC. (6.98)
FC TRAFFIC CONTROL, INC. (0.36)
L A FULLER & SONS CONSTRUCTION, LTD. (28.16)
TRP CONSTRUCTION GROUP, LLC (2.48)
TORO BRAVO CONSTRUCTION, LLC (0.68)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
Contract #02233209
Totals13405600.412496971.7110804412.5780.5

CountyHEMPHILL
HighwayUS 83
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-022
Proj IDF 2023(180)
Work TypeOVERLAY
 
6.9285382629.985629128.7599.9
Work Order12-05-22
Work Began07-17-23
Work Completed
Time Computed01-04-23
Contract Working Days71
Addl Days Granted0
Working Days Charged62
Percent Time Used87
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-022
BARRICADES UNLIMITED (1.65)
DIIBS SPECIALISTS, LLC (6.57)
DK CONTRACTING, LLC (0.91)
DUSTROL, INC. (0.68)
H & F TRUCKING (0.18)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.34)
TRP CONSTRUCTION GROUP, LLC (1.28)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.17)
W. S. CONSTRUCTION COMPANY (3.05)
MOBILE ENTERPRISES, INC. (0.26)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.08)
Contract #11223025
Totals5382629.980.005629128.7599.9

CountyDALLAM
HighwayUS 87
FromAT BU 87-B (7TH STREET)
To.
CSJ0040-03-068
Proj IDF 2021(646)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.222354993.20391544.1999.9
CountyHARTLEY
HighwayUS 87
FromAT 16TH STREET
To.
CSJ0041-01-048
Proj IDSTP 2021(647)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200248962.61269415.3399.9
Work Order02-03-23
Work Began04-24-23
Work Completed
Time Computed06-05-23
Contract Working Days88
Addl Days Granted0
Working Days Charged161
Percent Time Used182
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-068
TURKEY CREEK HDD, LLC (2.40)
CONCRETE CONNECTION, LLC (23.69)
FC TRAFFIC CONTROL, INC. (0.33)
LINEAR TRAFFIC MARKINGS LLC (6.16)
Contract #06213032
Totals603955.810.00660959.5299.9

CountyHARTLEY ETC
HighwayUS 87 ETC
FromDALHART CURB AND GUTTER
ToUS 87/385 SPLIT
CSJ0041-01-050
Proj IDF 2B23(294)
Work TypeSEAL COAT
 
107.39319650397.7019940061.7699.9
Work Order01-11-24
Work Began05-17-24
Work Completed
Time Computed07-22-24
Contract Working Days101
Addl Days Granted0
Working Days Charged89
Percent Time Used88
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-050
CENTERLINE TECHNOLOGIES, LLC (10.60)
COX PAVING COMPANY OF TEXAS, INC. (20.36)
FC TRAFFIC CONTROL, INC. (0.73)
INNOVATIVE ROADWAY SOLUTIONS, LLC (10.33)
RED SIXTEEN CONSTRUCTION, INC (0.32)
Contract #11233003
Totals19650397.701292864.5719940061.7699.9

CountyPOTTER
HighwayUS 87
From1.75 MI NORTH OF CANADIAN RIVER
To5.0 MI NORTH OF FM 1719
CSJ0041-05-055
Proj IDSTP 2024(780)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.3271814586.801258187.3569.3
CountyPOTTER
HighwayUS 87
From5.0 MI NORTH OF FM 1719
ToFM 1719
CSJ0041-07-122
Proj IDSTP 2024(780)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0041080198.50798692.1573.9
Work Order04-11-24
Work Began09-17-24
Work Completed
Time Computed05-10-24
Contract Working Days163
Addl Days Granted0
Working Days Charged48
Percent Time Used29
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-055
BARRICADES UNLIMITED (0.56)
FOX CONTRACTING KY, INC. (24.45)
MARCOMS CONSTRUCTION LLC (1.72)
Contract #03243025
Totals2894785.301395109.502056879.5071.0

CountyPOTTER
HighwayUS 87
FromCENTRAL AVE. NB BRIDGE
To.
CSJ0041-07-113
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.0723086684.052141136.6670.4
CountyPOTTER
HighwayUS 87
FromCENTRAL AVE. SB BRIDGE
To.
CSJ0041-07-114
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.0722901074.20665289.9322.9
CountyPOTTER
HighwayUS 87
FromHASTINGS AVE. NB BRIDGE
To.
CSJ0041-07-115
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.1252834563.951702454.8660.0
CountyPOTTER
HighwayUS 87
FromHASTINGS AVE. SB BRIDGE
To.
CSJ0041-07-116
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.1252843410.15513904.4818.0
Work Order05-17-23
Work Began12-01-23
Work Completed
Time Computed06-15-23
Contract Working Days302
Addl Days Granted0
Working Days Charged185
Percent Time Used61
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-113
ALAMO BROTHERS CONCRETE INC (20.46)
APOLLO CONSTRUCTORS, INC. (2.38)
BARRICADES UNLIMITED (0.44)
HARDY HOLE DRILLING (3.70)
HJC FARMS, INC. (3.07)
PRIMATE CONSTRUCTION, LP (0.67)
TRP CONSTRUCTION GROUP, LLC (0.62)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
Contract #04233208
Totals11665732.35215311.455022785.9343.3

CountyPOTTER
HighwayUS 87
FromUS 87 AT S 15TH AVE BRIDGE
To.
CSJ0041-07-117
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0371343373.751501843.1799.9
CountyPOTTER
HighwayUS 87
FromUS 87 AT 15TH AVE NB BRIDGE
To.
CSJ0041-07-118
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0371346900.501323386.0398.2
CountyPOTTER
HighwayIH 40
FromIH 40 AT CROCKETT ST EB BRIDGE
To.
CSJ0275-01-232
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.1042160190.35828511.1038.3
CountyPOTTER
HighwayIH 40
FromIH 40 AT CROCKETT ST WB BRIDGE
To.
CSJ0275-01-233
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.1042117950.05793574.7537.4
Work Order04-25-23
Work Began08-29-23
Work Completed
Time Computed05-25-23
Contract Working Days240
Addl Days Granted0
Working Days Charged198
Percent Time Used82
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-117
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (1.43)
BARRICADES UNLIMITED (0.68)
DUKE ELECTRIC CO., INC. (0.92)
DUSTIN ALLEN, INC. (0.86)
DUSTROL, INC. (0.83)
H & F TRUCKING (0.10)
TORO BRAVO CONSTRUCTION, LLC (2.03)
ALAMO BROTHERS CONCRETE INC (4.98)
TRP CONSTRUCTION GROUP, LLC (1.69)
PENHALL COMPANY (0.36)
Contract #03233043
Totals6968414.65560077.664447315.0565.4

CountyARMSTRONG
HighwayUS 287
FromCARSON CO LINE
To8.6 MILES EAST
CSJ0042-03-047
Proj IDF 2025(201)
Work TypeOVERLAY
 
8.16818049267.750.000.0
CountyARMSTRONG
HighwayUS 287
FromCARSON CO LINE
ToCR 4
CSJ0042-03-048
Proj IDSTP 2025(200)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.1141842206.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243009
Totals19891474.250.000.000.0

CountyPOTTER
HighwaySL 395
FromGARFIELD ST
ToROSS ST
CSJ0042-11-006
Proj IDSTP 2023(467)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.6075976375.1592057.311.5
Work Order09-06-24
Work Began10-28-24
Work Completed
Time Computed10-06-24
Contract Working Days152
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-11-006
APOLLO CONSTRUCTORS, INC. (18.41)
BARRICADES UNLIMITED (0.48)
C & C ENVIRONMENTAL SERVICES (0.21)
GREEN PLAINS DESIGN (5.83)
KING GEORGE TRAFFIC SOLUTIONS LLC (2.41)
Contract #06243014
Totals5976375.1538038.0192057.311.5

CountyMOORE
HighwayUS 287
FromSOUTH OF FM 281
ToDUMAS
CSJ0066-04-079
Proj IDF 2021(699)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.9064229617.382379321.9359.1
Work Order08-25-21
Work Began03-30-22
Work Completed
Time Computed09-24-21
Contract Working Days137
Addl Days Granted0
Working Days Charged265
Percent Time Used193
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-079
MARCOM"S MOWING SERVICE, LLC (3.01)
DUSTROL, INC. (0.25)
TOTAL HIGHWAY MAINTENANCE, LLC (8.57)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.48)
LYNCO CONSTRUCTION (5.06)
LONE STAR EROSION CONTROL (2.34)
TEXAS GUARDRAIL CONTRACTORS LLC (9.90)
Contract #07213217
Totals4229617.38124924.322379321.9359.1

CountyMOORE
HighwayUS 287
FromFM 281
ToSHERMAN COUNTY LINE
CSJ0066-04-083
Proj IDF 2B24(080)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.3012231728.041329881.7559.5
Work Order06-06-24
Work Began09-09-24
Work Completed
Time Computed09-09-24
Contract Working Days51
Addl Days Granted0
Working Days Charged29
Percent Time Used56
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-083
VACA UNDERGROUND UTILITIES INC (16.58)
C & C ENVIRONMENTAL SERVICES (0.45)
TRP CONSTRUCTION GROUP, LLC (1.95)
BARRICADES UNLIMITED (0.53)
Contract #05243225
Totals2231728.041080563.401329881.7559.5

CountyMOORE
HighwayUS 87
FromSOUTH CITY LIMITS OF DUMAS
ToSH 152
CSJ0066-05-065
Proj IDNH 2013(606)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.56336473058.2838104425.3399.9
CountyMOORE
HighwayUS 87
FromAT SH 152
To.
CSJ0066-05-070
Proj IDSTP 2021(393)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.100327315.70739720.9599.9
Work Order05-20-21
Work Began07-06-21
Work Completed
Time Computed06-21-21
Contract Working Days838
Addl Days Granted0
Working Days Charged703
Percent Time Used83
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-065
BARRICADES UNLIMITED (1.97)
JR WEST TEXAS CONCRETE LLC (8.60)
L&H ELECTRICAL, LLC (2.71)
DUSTROL, INC. (0.89)
L A FULLER & SONS CONSTRUCTION, LTD. (15.00)
PRIMATE CONSTRUCTION, LP (0.51)
RK HALL, LLC (15.08)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.10)
DK CONTRACTING, LLC (0.29)
REINHOLD ELECTRIC, INC (2.69)
TRP CONSTRUCTION GROUP, LLC (0.77)
Contract #04213202
Totals36800373.9822500.0038844146.2899.9

CountyMOORE ETC
HighwayUS 87 ETC
FromSOUTH DUMAS CITY LIMITS
ToPOTTER COUNTY LINE
CSJ0066-05-081
Proj IDC 66-5-81
Work TypeSEAL COAT
 
41.94618664181.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243207
Totals18664181.220.000.000.0

CountyRANDALL
HighwayUS 87
FromRUSSELL LONG BLVD
To4 LANE DIVIDED
CSJ0067-01-087
Proj IDF 2024(460)
Work TypeOVERLAY
 
3.8359542615.343756006.3239.3
Work Order02-21-24
Work Began07-25-24
Work Completed
Time Computed08-23-24
Contract Working Days167
Addl Days Granted0
Working Days Charged71
Percent Time Used42
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0067-01-087
LINEAR TRAFFIC MARKINGS LLC (1.52)
APOLLO CONSTRUCTORS, INC. (4.25)
BARRICADES UNLIMITED (0.33)
DUININCK, INC. (58.55)
INDUSTRIAL FABRICS, INC. (8.29)
DUSTROL, INC. (0.67)
H & F TRUCKING (0.47)
Contract #12233012
Totals9542615.341498697.773756006.3239.3

CountyOLDHAM
HighwayIH 40
From6.2 MI E OF NEW MEXICO (MM 6)
To11.2 MI E OF NEW MEXICO (MM 12)
CSJ0090-02-055
Proj IDF 2B24(295)
Work TypeOVERLAY
 
9.75115078257.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-24-24
Work Began00-00-00
Work Completed
Time Computed04-15-25
Contract Working Days116
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0090-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243012
Totals15078257.780.000.000.0

CountyPOTTER
HighwayIH 40
FromIH 40/HOPE RD BRIDGE
To.
CSJ0090-05-107
Proj IDBR 2024(779)
Work TypeBRIDGE REPLACEMENT
 
10246889.624819095.7047.0
Work Order04-25-24
Work Began08-05-24
Work Completed
Time Computed05-25-24
Contract Working Days182
Addl Days Granted0
Working Days Charged59
Percent Time Used32
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-107
LINDAMOOD, INC. (1.65)
DK CONTRACTING, LLC (0.26)
TORO BRAVO CONSTRUCTION, LLC (0.75)
L A FULLER & SONS CONSTRUCTION, LTD. (10.69)
TRP CONSTRUCTION GROUP, LLC (0.31)
SQUARE CONTRACTING INC (8.64)
CROSSBAR LOGISTICS LLC (0.34)
MARRS ELECTRIC LLC (0.17)
Contract #03243010
Totals10246889.621432553.894819095.7047.0

CountyPOTTER
HighwayIH 40
FromIH 40/ADKISSON RD BRIDGE
To.
CSJ0090-05-108
Proj IDBR 2024(730)
Work TypeBRIDGE REPLACEMENT
 
9782900.982741259.3928.0
Work Order03-21-24
Work Began08-07-24
Work Completed
Time Computed04-21-24
Contract Working Days200
Addl Days Granted0
Working Days Charged43
Percent Time Used21
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-108
ALAMO BROTHERS CONCRETE INC (7.36)
BARRICADES UNLIMITED (0.32)
DUSTROL, INC. (0.89)
HJC FARMS, INC. (0.63)
LMSE TRUCKING, LLC (0.77)
PENHALL COMPANY (0.11)
SCOTT DERR PAINTING CO, LLC (0.28)
TRP CONSTRUCTION GROUP, LLC (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.64)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.90)
TORO BRAVO CONSTRUCTION, LLC (0.26)
TORO BRAVO CONSTRUCTION, LLC (0.62)
Contract #02243011
Totals9782900.98510467.002741259.3928.0

CountyPOTTER
HighwayBI 40-D
FromIH 40
ToSL 279
CSJ0090-05-109
Proj IDSTP 2025(139)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.3978119862.000.000.0
CountyPOTTER
HighwayBI 40-D
FromIH 40
ToSL 279
CSJ0090-05-110
Proj IDSTP 2025(139)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.3972201889.250.000.0
CountyPOTTER
HighwayBI 40-D
FromIH 40 WEST
ToSL 279
CSJ0090-05-112
Proj IDF 2025(140)
Work TypeOVERLAY
 
9198576.440.000.0
CountyPOTTER
HighwayBI 40-D
FromWEST SL 335
ToSL 279 (SW 9TH AVE)
CSJ0090-05-113
Proj IDSTP 2B24(107)TP
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
11461726.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days322
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243203
Totals30982053.940.000.000.0

CountyPOTTER
HighwayBI 40-D
FromON BI 40-D EB
ToAT BNSF RR
CSJ0090-06-044
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482915940.532045438.4175.7
CountyPOTTER
HighwayBI 40-D
FromON BI 40-D WB
ToAT BNSF RR
CSJ0090-06-045
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482291335.601937980.5584.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began05-03-21
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted13
Working Days Charged522
Percent Time Used138
Contractor(s)
UNITED FIRE & CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-044
PINNACLE GRINDING AND GROOVING LLC (0.20)
HUNTER DEMOLITION & WRECKING CORPORATION (3.49)
BARRICADES UNLIMITED (1.90)
FC TRAFFIC CONTROL, INC. (0.47)
L&H ELECTRICAL, LLC (1.54)
RK HALL, LLC (6.23)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.41)
HJC FARMS, INC. (1.85)
A BROTHERS MILLING, LLC (0.35)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.36)
TORO BRAVO CONSTRUCTION, LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.91)
AARON CONCRETE CONTRACTORS, L.P. (3.17)
PENHALL COMPANY (0.16)
TRP CONSTRUCTION GROUP, LLC (0.87)
Contract #01213007
Totals5207276.1359878.303983418.9679.6

page 1 | page 2 | page 3 | page 4