Monthly State Let Construction Report For Amarillo District As Of Sep 10, 2024 Page 2 Of 4

Last Update: Tuesday, September 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDEAF SMITH
HighwayUS 60
FromEAST OF HEREFORD
ToRANDALL COUNTY LINE
CSJ0168-07-050
Proj IDC 168-7-50
Work TypeREHABILITATION OF EXISTING ROAD
 
26.39023784485.6013966928.6058.7
Work Order02-16-23
Work Began04-10-23
Work Completed
Time Computed03-18-23
Contract Working Days194
Addl Days Granted0
Working Days Charged187
Percent Time Used96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-050
FC TRAFFIC CONTROL, INC. (0.16)
INDUSTRIAL FABRICS, INC. (4.52)
PROFESSIONAL TRAFFIC CONTROL LLC (0.18)
TEX OP CONSTRUCTION, LP (1.14)
TRP CONSTRUCTION GROUP, LLC (1.66)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.34)
W. S. CONSTRUCTION COMPANY (0.58)
Contract #01233202
Totals23784485.602869458.0013966928.6058.7

CountyRANDALL
HighwayUS 60
FromDEAF SMITH CO LINE
ToUS 87 IN CANYON
CSJ0168-08-075
Proj IDF 2024(033)
Work TypeREHABILITATION OF EXISTING ROAD
 
15.07734924133.6116544614.5547.3
Work Order12-06-23
Work Began04-16-24
Work Completed
Time Computed03-04-24
Contract Working Days290
Addl Days Granted0
Working Days Charged92
Percent Time Used31
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-08-075
ALAMO BROTHERS CONCRETE INC (0.90)
FC TRAFFIC CONTROL, INC. (0.19)
H & F TRUCKING (0.02)
HJC FARMS, INC. (0.24)
MOBILE ENTERPRISES, INC. (0.20)
PERFORMANCE EQUIPMENT SERVICE (1.76)
SAENZ TRANSPORT, LLC (0.14)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.06)
TEX OP CONSTRUCTION, LP (1.13)
TRP CONSTRUCTION GROUP, LLC (1.99)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
W. S. CONSTRUCTION COMPANY (1.07)
TEXAS ROAD RECYCLERS, L.L.C. (0.53)
Contract #09233203
Totals34924133.615381828.2816544614.5547.3

CountyRANDALL
HighwayIH 27
FromSL 335
ToNORTH OF US 60/US 87 INTERCHANGE
CSJ0168-09-083
Proj IDF 2024(864)
Work TypeWIDEN FREEWAY
 
0.794312507980.8647026231.5415.0
Work Order04-25-24
Work Began07-15-24
Work Completed
Time Computed07-23-24
Contract Working Days1,155
Addl Days Granted0
Working Days Charged35
Percent Time Used3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-083
A BROTHERS MILLING, LLC (0.29)
ANTIGO CONSTRUCTION, INC. (0.04)
DK CONTRACTING, LLC (0.14)
FC TRAFFIC CONTROL, INC. (0.07)
GIBSON & ASSOCIATES, INC. (0.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.50)
PRIMATE CONSTRUCTION, LP (0.14)
TURKEY CREEK HDD, LLC (1.84)
2H, LLC (0.47)
TEX OP CONSTRUCTION, LP (0.01)
H & F TRUCKING (1.76)
TORO BRAVO CONSTRUCTION, LLC (0.33)
TRUMBLE CRANE & RIGGING (0.09)
ALAMO BROTHERS CONCRETE INC (1.67)
APOLLO CONSTRUCTORS, INC. (5.04)
SCOTT DERR PAINTING CO, LLC (0.13)
J. LEE MILLIGAN, INC. (27.19)
J. H. ODEN CONTRACTING COMPANY (0.69)
Contract #02243044
Totals312507980.8618205713.2447026231.5415.0

CountyRANDALL
HighwayIH 27
From0.058 MILES SOUTH OF 45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-180
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.5215291174.655275788.9499.7
CountyRANDALL
HighwayIH 27
From45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-181
Proj IDF 2021(518)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
3.15625024977.7618333500.7073.2
CountyPOTTER
HighwayIH 27
FromRANDALL COUNTY LINE
To0.2 MILES SOUTH OF IH 40
CSJ0168-10-077
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.499682460.65960743.5999.9
Work Order06-22-21
Work Began09-07-21
Work Completed
Time Computed07-22-21
Contract Working Days847
Addl Days Granted34
Working Days Charged745
Percent Time Used84
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-180
BARRICADES UNLIMITED (1.18)
SLATON BROTHERS, INC. (2.58)
H & F TRUCKING (2.17)
J. H. ODEN CONTRACTING COMPANY (0.18)
WILLIAMS DITCHING, LLC (1.21)
HJC FARMS, INC. (1.70)
GHC TRANSPORT, L.L.C. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.45)
PRIMATE CONSTRUCTION, LP (0.31)
JB PINNACLE GROUP, LLC (11.06)
ARTEX ELECTRIC, INC. (2.19)
OSCAR ORDUNO, INC. (5.42)
DUSTROL, INC. (0.44)
URBAN INFRACONSTRUCTION LLC (0.20)
IBCTX, LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.17)
ALAMO BROTHERS CONCRETE INC (4.11)
LMSE TRUCKING, LLC (0.00)
APOLLO CONSTRUCTORS, INC. (0.06)
Contract #05213202
Totals30998613.063235935.0024570033.2379.2

CountyGRAY
HighwayUS 60
FromFM 282
ToSH 70
CSJ0169-06-042
Proj IDF 2B24(156)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4.2145798331.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days278
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-06-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243058
Totals5798331.060.000.000.0

CountyGRAY
HighwayUS 60
FromLP 171 IN PAMPA
ToROBERTS COUNTY LINE
CSJ0169-07-053
Proj IDC 169-7-53
Work TypeSUPER-2 HIGHWAY
 
12.90014712201.1617879021.5499.9
CountyGRAY
HighwayUS 60
FromTIGNOR ST
ToCOUNTY ROAD 10
CSJ0169-07-054
Proj IDC 169-7-54
Work TypeREHABILITATION OF EXISTING ROAD
 
1.4271824177.811908191.2699.9
Work Order09-16-21
Work Began03-01-22
Work Completed
Time Computed10-18-21
Contract Working Days351
Addl Days Granted0
Working Days Charged333
Percent Time Used94
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-07-053
BARRICADES UNLIMITED (1.40)
DUSTIN ALLEN, INC. (1.58)
MARCOM"S MOWING SERVICE, LLC (0.66)
PINNACLE GRINDING AND GROOVING LLC (0.10)
TEX OP CONSTRUCTION, LP (0.74)
WITHERS CONSTRUCTION, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18)
W. S. CONSTRUCTION COMPANY (2.52)
TRP CONSTRUCTION GROUP, LLC (1.11)
SCR CIVIL CONSTRUCTION, LLC (0.12)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
Contract #08213006
Totals16536378.970.0019787212.8099.9

CountyLIPSCOMB
HighwayUS 60
FromHEMPHILL CO LINE
ToOKLAHOMA STATE LINE
CSJ0170-02-023
Proj IDC 170-2-23
Work TypeOVERLAY
 
11.26811577190.700.000.0
CountyROBERTS
HighwaySH 70
FromOCHILTREE CO LINE
ToCANADIAN RIVER
CSJ0490-04-051
Proj IDC 490-4-51
Work TypeOVERLAY
 
5.7935486431.490.000.0
CountyLIPSCOMB
HighwaySH 23
From11 MI NORTH OF US 83
ToUS 83
CSJ1337-02-014
Proj IDC 1337-2-14
Work TypeOVERLAY
 
11.1022411978.490.000.0
Work Order05-22-24
Work Began00-00-00
Work Completed
Time Computed04-15-25
Contract Working Days114
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0170-02-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243004
Totals19475600.680.000.000.0

CountyDEAF SMITH
HighwayUS 385
From16TH STREET
ToSOUTH OF US 60
CSJ0226-05-072
Proj IDF 2B24(155)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2.7215281885.170.000.0
Work Order07-17-24
Work Began00-00-00
Work Completed
Time Computed08-16-24
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-05-072
PENHALL COMPANY (5.43)
PBJ CONSTRUCTION (4.71)
GP7 CONSTRUCTION INC. (3.16)
Contract #06243226
Totals5281885.170.000.000.0

CountyPOTTER
HighwayIH 40
FromBI 40-D
ToFM 2590 (SONCY ROAD)
CSJ0275-01-199
Proj IDNH 2020(549)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.86325360575.7727444119.5599.9
CountyPOTTER
HighwaySL 335
FromFM 2590 NORTH
ToSW 9TH
CSJ2635-04-037
Proj IDNH 2020(550)
Work TypeNEW LOCATION NON-FREEWAY
 
2.33324672131.9725286498.1199.9
Work Order03-12-20
Work Began05-04-20
Work Completed
Time Computed06-10-20
Contract Working Days575
Addl Days Granted168
Working Days Charged974
Percent Time Used131
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-199
AARON CONCRETE CONTRACTORS, L.P. (1.01)
ACT SAW CUTTING & REMOVAL (0.11)
BARRICADES UNLIMITED (0.58)
CHEROKEE SERVICES (0.09)
SCOTT DERR PAINTING CO, LLC (0.07)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
TEXOP CONSTRUCTION (0.51)
TORO BRAVO CONSTRUCTION, LLC (0.20)
WILLIAMS DITCHING, LLC (4.71)
FC TRAFFIC CONTROL, INC. (0.32)
HJC FARMS, INC. (1.69)
H & F TRUCKING (4.90)
ARTEX ELECTRIC, INC. (2.34)
FARR FOUNDATION, INC. (0.77)
ALAMO BROTHERS CONCRETE INC (3.05)
DK CONTRACTING, LLC (0.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.02)
DIIBS SPECIALISTS, LLC (0.02)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
G & L REBAR (0.00)
URBAN INFRACONSTRUCTION LLC (0.20)
G & L REBAR (0.07)
ROYAL REBAR (0.02)
WEBBER BARRIER SERVICES, LLC. (0.03)
GHC TRANSPORT, L.L.C. (0.00)
PEREZ REBAR CONSTRUCTION (0.01)
DRILL PIER CONSTRUCTION, LLC (0.01)
MASSANA CONSTRUCTION INC. (0.18)
ARANDA TRANSPORT LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.22)
APOLLO CONSTRUCTORS, INC. (1.42)
Contract #02203001
Totals50032707.74295640.6552730617.6699.9

CountyPOTTER
HighwayIH 40 ETC
FromAT IH 27
To.
CSJ0275-01-229
Proj IDBR 2023(596)
Work TypeBRIDGE MAINTENANCE
 
0.1558159181.057742398.4894.8
Work Order06-14-23
Work Began10-09-23
Work Completed
Time Computed07-14-23
Contract Working Days175
Addl Days Granted54
Working Days Charged151
Percent Time Used65
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-229
FC TRAFFIC CONTROL, INC. (0.64)
TRP CONSTRUCTION GROUP, LLC (3.50)
J.H. PAINTING COMPANY (0.69)
SOUTHEAST GRINDING AND GROOVING LLC (0.52)
A-CORE CONCRETE CUTTING, INC. (2.67)
MACIAS SPECIALTY CONTRACTING LLC (6.08)
Contract #04233007
Totals8159181.052175479.157742398.4894.8

CountyPOTTER
HighwayIH 40
FromEAST OF HOPE ROAD
ToUS 287 INTERCHANGE
CSJ0275-01-244
Proj IDF 2B24(154)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
11497986.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed09-30-24
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-244
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243211
Totals11497986.780.000.000.0

CountyCARSON ETC
HighwayIH 40 ETC
FromAT BI 40 F
To.
CSJ0275-04-061
Proj IDBR 2024(461)
Work TypeBRIDGE MAINTENANCE
 
13665830.901962271.2014.3
Work Order01-04-24
Work Began05-08-24
Work Completed
Time Computed02-03-24
Contract Working Days468
Addl Days Granted0
Working Days Charged79
Percent Time Used16
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-04-061
2H, LLC (0.00)
AARON CONCRETE CONTRACTORS, LLC (10.09)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.38)
BARRICADES UNLIMITED (0.51)
CRANE SERVICES, INC. (0.09)
DIIBS SPECIALISTS, LLC (2.41)
L A FULLER & SONS CONSTRUCTION, LTD. (5.93)
HYDRO TECHNOLOGIES, INC. (3.89)
MOBILE ENTERPRISES, INC. (11.18)
TRP CONSTRUCTION GROUP, LLC (0.00)
TEXAS CUTTING & CORING GP, INC. (1.65)
Contract #12233007
Totals13665830.90243813.001962271.2014.3

CountyCARSON
HighwayIH 40
FromWB MM 107
ToWB MM 107.6
CSJ0275-04-069
Proj IDSTP 2B23(012)TAPS
Work TypeRESTORATION
 
0.6006318689.753999963.1464.2
Work Order09-06-23
Work Began01-29-24
Work Completed
Time Computed12-03-23
Contract Working Days96
Addl Days Granted0
Working Days Charged141
Percent Time Used146
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-04-069
APOLLO CONSTRUCTORS, INC. (7.29)
BARRICADES UNLIMITED (0.09)
GREEN PLAINS DESIGN (3.10)
HJC FARMS, INC. (1.55)
PRIMATE CONSTRUCTION, LP (1.05)
TRP CONSTRUCTION GROUP, LLC (1.19)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.11)
Contract #08233226
Totals6318689.75252444.463999963.1464.2

CountyGRAY
HighwayIH 40
FromW BI 40 H IN MCLEAN
ToSH 273
CSJ0275-11-090
Proj IDBR 2024(136)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
12919745.103330149.2025.7
Work Order11-16-23
Work Began04-13-24
Work Completed
Time Computed12-16-23
Contract Working Days247
Addl Days Granted0
Working Days Charged92
Percent Time Used37
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-090
ANTIGO CONSTRUCTION, INC. (0.36)
APOLLO CONSTRUCTORS, INC. (1.38)
BARRICADES UNLIMITED (0.30)
HJC FARMS, INC. (4.22)
PRIMATE CONSTRUCTION, LP (0.68)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
TRP CONSTRUCTION GROUP, LLC (2.80)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18)
Contract #10233010
Totals12919745.10138351.203330149.2025.7

CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE CO LINE
To0.6 MI EAST OF SH 23
CSJ0355-02-036
Proj IDC 355-2-36
Work TypeRESTORATION
 
3775022.480.000.0
CountyOCHILTREE
HighwaySH 15
FromUS 83
ToEAST LP 143
CSJ0355-03-033
Proj IDC 355-3-33
Work TypeRESTORATION
 
2247708.970.000.0
CountyOCHILTREE
HighwaySH 15
FromEAST LP 143
ToLIPSCOMB CO LINE
CSJ0355-03-034
Proj IDC 355-3-34
Work TypeRESTORATION
 
18025862.720.000.0
CountyOCHILTREE
HighwaySH 15
FromWEST LP 143
ToUS 83
CSJ0355-04-043
Proj IDC 355-4-43
Work TypeRESTORATION
 
4794516.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days166
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0355-02-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243006
Totals28843111.110.000.000.0

CountyHUTCHINSON
HighwaySH 136
From0.1 MILES SOUTH OF SH 152
ToNORTH BORGER TRAFFIC CIRCLE
CSJ0356-01-107
Proj IDF 2023(456)
Work TypeOVERLAY
 
9.5369658644.0510410274.7499.9
Work Order03-13-23
Work Began03-04-24
Work Completed
Time Computed04-12-23
Contract Working Days100
Addl Days Granted0
Working Days Charged102
Percent Time Used102
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-107
BARRICADES UNLIMITED (0.19)
DK CONTRACTING, LLC (0.44)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
DUSTIN ALLEN, INC. (6.18)
TEXOP CONSTRUCTION (0.68)
TRP CONSTRUCTION GROUP, LLC (1.48)
WITHERS CONSTRUCTION, LLC (0.93)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.36)
W. S. CONSTRUCTION COMPANY (6.56)
Contract #02233208
Totals9658644.05663867.0410410274.7499.9

CountyHUTCHINSON
HighwaySH 136
FromNORTH OF BORGER TRAFFIC CIRCLE
To240' NORTH OF JEFFERSON ST
CSJ0356-01-108
Proj IDF 2024(462)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2.7664885721.304638478.4394.9
Work Order02-02-24
Work Began03-18-24
Work Completed
Time Computed03-04-24
Contract Working Days263
Addl Days Granted0
Working Days Charged118
Percent Time Used44
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-108
APOLLO CONSTRUCTORS, INC. (3.30)
BARRICADES UNLIMITED (0.57)
ONE WAY CONCRETE CONSTRUCTION, LLC (31.75)
TRP CONSTRUCTION GROUP, LLC (1.71)
Contract #12233207
Totals4885721.30372684.504638478.4394.9

CountyHUTCHINSON ETC
HighwaySH 136 ETC
FromCANADIAN RIVER
To.
CSJ0356-01-112
Proj IDBR 2B24(553)
Work TypeBRIDGE MAINTENANCE
 
1.31814937903.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days293
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243028
Totals14937903.080.000.000.0

CountyGRAY
HighwaySH 152
FromUS 60
ToWHEELER CO LINE
CSJ0397-01-045
Proj IDSTP 2021(130)
Work TypeSUPER-2 HIGHWAY
 
17.99015464360.4117542315.3999.9
Work Order12-11-20
Work Began02-15-21
Work Completed
Time Computed01-11-21
Contract Working Days266
Addl Days Granted31
Working Days Charged271
Percent Time Used91
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-045
BARRICADES UNLIMITED (1.50)
BIG CREEK SAND & GRAVEL, INC. (11.85)
DUSTIN ALLEN, INC. (4.69)
MARCOM"S MOWING SERVICE, LLC (0.70)
TEX OP CONSTRUCTION, LP (2.06)
W. S. CONSTRUCTION COMPANY (9.72)
WEST TEXAS ROCK RESOURCES, LLC (0.37)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
TRP CONSTRUCTION GROUP, LLC (1.80)
Contract #11203004
Totals15464360.410.0017542315.3999.9

CountyHUTCHINSON
HighwaySH 152
FromSS 246
ToCARSON CO LINE
CSJ0455-01-048
Proj IDF 2023(821)
Work TypeOVERLAY
 
6.7957851871.786648643.7984.6
Work Order07-12-23
Work Began03-04-24
Work Completed
Time Computed08-11-23
Contract Working Days114
Addl Days Granted0
Working Days Charged95
Percent Time Used83
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0455-01-048
BAHENA CONSTRUCTION CO.,INC. (8.36)
BARRICADES UNLIMITED (0.28)
DK CONTRACTING, LLC (1.11)
DUSTIN ALLEN, INC. (5.22)
DUSTROL, INC. (0.57)
GIBSON & ASSOCIATES, INC. (3.59)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.26)
TRP CONSTRUCTION GROUP, LLC (1.64)
WITHERS CONSTRUCTION, LLC (0.52)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.86)
NELSON INDUSTRIAL SERVICES, INC. (0.08)
Contract #06233210
Totals7851871.782958986.446648643.7984.6

page 1 | page 2 | page 3 | page 4