Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | MORRIS ETC |
Highway | US 67 ETC |
From | 0.5 MI E OF US 259 |
To | 0.5 MI W OF US 259 |
CSJ | 0010-08-060 |
Proj ID | STP 2024(632)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 9.000 | 948821.60 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 150 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
VACA UNDERGROUND UTILITIES INC |
SUBCONTRACTOR(S) FOR CCSJ: 0010-08-060 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243036 |
| Totals | 948821.60 | 0.00 | 0.00 | 0.0 |
|
County | BOWIE ETC |
Highway | US 67 ETC |
From | 0.5 MI E OF SH 8 |
To | 0.5 MI W OF SH 8 |
CSJ | 0010-12-075 |
Proj ID | STP 2023(375)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 11.000 | 1397827.97 | | 1374139.64 | 99.1 |
Work Order | 03-23-23 |
Work Began | 12-04-23 |
Work Completed | |
Time Computed | 07-20-23 |
Contract Working Days | 172 |
Addl Days Granted | 0 |
Working Days Charged | 186 |
Percent Time Used | 108 |
Contractor(s) |
WG ENGINEERING & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-075 GOMEZ PROPERTY SOLUTIONS LLC (3.54) RANSOM DRILLING SERVICES, LLC (2.87) MEDELLIN HDD LLC (7.50) LINEAR TRAFFIC MARKINGS LLC (1.59)
|
Contract # | 01233222 |
| Totals | 1397827.97 | 104470.30 | 1374139.64 | 99.1 |
|
County | BOWIE ETC |
Highway | FM 991 ETC |
From | US 67 W |
To | US 67 E |
CSJ | 0010-19-014 |
Proj ID | F 2024(073) |
Work Type | SEAL COAT |
|
| 201.632 | 11823241.45 | | 10386352.34 | 87.8 |
Work Order | 01-11-24 |
Work Began | 05-01-24 |
Work Completed | |
Time Computed | 05-01-24 |
Contract Working Days | 88 |
Addl Days Granted | 18 |
Working Days Charged | 106 |
Percent Time Used | 100 |
Contractor(s) |
CDM HOLDINGS |
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-014 FC TRAFFIC CONTROL, INC. (1.75) INNOVATIVE ROADWAY SOLUTIONS, LLC (3.45) STRIPE-A-ZONE, LLC (7.21)
|
Contract # | 10233008 |
| Totals | 11823241.45 | 38188.58 | 10386352.34 | 87.8 |
|
County | BOWIE |
Highway | US 82 ETC |
From | 0.1 MI W OF US 259 |
To | FM 992 |
CSJ | 0046-03-038 |
Proj ID | F 2025(050) |
Work Type | WIDEN NON-FREEWAY |
|
| 26.384 | 114513431.82 | | 870000.00 | 0.7 |
Work Order | 09-18-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-18-24 |
Contract Working Days | 1,024 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DRAKE COMPANIES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0046-03-038 FLEX SUPPLY, LLC (0.28) J. H. ODEN CONTRACTING COMPANY (1.35) MAY CONSTRUCTION, LLC (1.80) EAST TEXAS BRIDGE, INC. (32.09) J 2 CONSTRUCTION SERVICES, LLC (0.67) MORRIS COUNTY CONTRACTORS, L.L.C. (0.32) SCOTT DERR PAINTING CO, LLC (0.01) SKC EARTHWORKS LIMITED LIABILITY COMPANY (4.27) SNOWHILL CONTRACTING LLC (1.66) STRIPING TECHNOLOGY, L.P. (1.80) SURFACE PREPARATION TECHNOLOGIES, LLC (0.13) TEX OP CONSTRUCTION, LP (0.49) TRUE ROADS, LLC (8.37) TORO BRAVO CONSTRUCTION, LLC (0.00)
|
Contract # | 08243052 |
| Totals | 114513431.82 | 870000.00 | 870000.00 | 0.7 |
|
County | BOWIE ETC |
Highway | SL 14 ETC |
From | ARKANSAS S/L |
To | US 82 |
CSJ | 0046-08-017 |
Proj ID | C 46-8-17 |
Work Type | SEAL COAT |
|
| 167.041 | 10662923.20 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 103 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MISSOURI PETROLEUM PRODUCTS COMPANY LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0046-08-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10243013 |
| Totals | 10662923.20 | 0.00 | 0.00 | 0.0 |
|
County | BOWIE ETC |
Highway | SH 8 ETC |
From | AT FM 1840 |
To | . |
CSJ | 0061-02-033 |
Proj ID | STP 2B24(043)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 10.500 | 1359816.40 | | 201600.00 | 14.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 210 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
VACA UNDERGROUND UTILITIES INC |
SUBCONTRACTOR(S) FOR CCSJ: 0061-02-033 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06243045 |
| Totals | 1359816.40 | 201600.00 | 201600.00 | 14.8 |
|
County | BOWIE |
Highway | SH 8 |
From | AT SULPHUR RIVER & SULPHUR RIV REL |
To | . |
CSJ | 0062-01-035 |
Proj ID | BR 2019(689) |
Work Type | BRIDGE REPLACEMENT |
|
| 1.551 | 35121366.72 | | 34116566.52 | 97.1 |
County | CASS |
Highway | SH 8 |
From | AT SULPHUR RIVER & SULPHUR RIV REL |
To | . |
CSJ | 0062-02-024 |
Proj ID | BR 2019(690) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.360 | 2612244.52 | | 2164472.82 | 82.8 |
Work Order | 05-02-19 |
Work Began | 05-13-19 |
Work Completed | |
Time Computed | 05-13-19 |
Contract Working Days | 1,215 |
Addl Days Granted | 11 |
Working Days Charged | 958 |
Percent Time Used | 78 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0062-01-035 BOWMAN ENGINEERING & CONSULTING, INC. (4.17) ISAACS CONSTRUCTION SERVICES LLC (0.09) JB PINNACLE GROUP, LLC (2.55) MORRIS COUNTY CONTRACTORS, L.L.C. (0.60) PANOLA SIGN & BARRICADE, INC. (0.16) STRIPING TECHNOLOGY, L.P. (0.73) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30) MASSEY CONTRACTORS, LLC (0.13) FARR FOUNDATION, INC. (1.00) CAP RIVER LLC (0.36) HERMANOS STEEL, LLC (0.03) SOUTHEAST GRINDING AND GROOVING LLC (0.01)
|
Contract # | 04193002 |
| Totals | 37733611.24 | 302977.58 | 36281039.34 | 96.1 |
|
County | HARRISON ETC |
Highway | US 59 ETC |
From | AT FM 1997 |
To | . |
CSJ | 0062-07-103 |
Proj ID | STP 2B24(045)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 9.000 | 1254209.20 | | 299103.99 | 23.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-02-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 170 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
VACA UNDERGROUND UTILITIES INC |
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-103 SAFETEX,INC. (3.68)
|
Contract # | 04243040 |
| Totals | 1254209.20 | 299103.99 | 299103.99 | 23.8 |
|
County | PANOLA |
Highway | US 59 |
From | US 79 N |
To | US 59 S |
CSJ | 0063-04-068 |
Proj ID | STP 2024(670)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.073 | 393564.14 | | 473691.12 | 99.9 |
County | PANOLA |
Highway | US 79 |
From | US 59 N |
To | US 79 S |
CSJ | 0063-11-061 |
Proj ID | STP 2024(670)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.602 | 437563.87 | | 243023.85 | 55.5 |
County | PANOLA |
Highway | SH 149 |
From | US 79 S |
To | 0.8 MI S OF SH 315 |
CSJ | 0063-11-062 |
Proj ID | STP 2024(670)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 1.836 | 274431.40 | | 250768.10 | 91.3 |
Work Order | 06-19-24 |
Work Began | 07-29-24 |
Work Completed | |
Time Computed | 07-19-24 |
Contract Working Days | 71 |
Addl Days Granted | 0 |
Working Days Charged | 59 |
Percent Time Used | 83 |
Contractor(s) |
H. V. CAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-04-068 DIAMOND ELITE BARRICADES, LLC (0.56) FLORES CONCRETE (19.27) SOUTHWEST ENVIRONMENT SERVICES LLC (3.23)
|
Contract # | 02243029 |
| Totals | 1105559.41 | 276819.92 | 967483.07 | 87.5 |
|
County | PANOLA |
Highway | US 59 |
From | AT INTERSECTION OF FM 1794 |
To | . |
CSJ | 0063-10-015 |
Proj ID | C 63-10-15 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.458 | 36905848.45 | | 22945086.30 | 62.1 |
Work Order | 07-13-23 |
Work Began | 08-08-23 |
Work Completed | |
Time Computed | 08-08-23 |
Contract Working Days | 504 |
Addl Days Granted | 0 |
Working Days Charged | 261 |
Percent Time Used | 51 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-10-015 HODGES AND SON CONSTRUCTION COMPANY, INC. (0.46) MORRIS COUNTY CONTRACTORS, L.L.C. (0.39) PANOLA SIGN & BARRICADE, INC. (0.15) SOUTHWEST ENVIRONMENT SERVICES LLC (0.34) STRIPING TECHNOLOGY, L.P. (1.58) TORO BRAVO CONSTRUCTION, LLC (0.33) ISAACS CONSTRUCTION SERVICES LLC (0.59) WEST TEXAS ROCK RESOURCES, LLC (0.01) A&A TREE SERVICES (0.00) HIGHWAY 1 LLC (0.39) STRAIGHT LINE SAWING & SEALING, INC. (0.07) TORO BRAVO CONSTRUCTION, LLC (0.03) KITECO PROPERTY SOLUTIONS INC. (0.10)
|
Contract # | 06233003 |
| Totals | 36905848.45 | 1317853.43 | 22945086.30 | 62.1 |
|
County | PANOLA |
Highway | SH 149 |
From | 0.8 MI S OF SH 315 |
To | US 59 |
CSJ | 0063-11-054 |
Proj ID | F 2023(026) |
Work Type | WIDEN NON-FREEWAY |
|
| 1.623 | 29546263.07 | | 21932664.89 | 74.2 |
Work Order | 10-19-22 |
Work Began | 11-03-22 |
Work Completed | |
Time Computed | 11-03-22 |
Contract Working Days | 205 |
Addl Days Granted | 208 |
Working Days Charged | 392 |
Percent Time Used | 94 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-054 CAP RIVER LLC (0.68) FARR FOUNDATION, INC. (2.38) ISAACS CONSTRUCTION SERVICES LLC (0.61) MORRIS COUNTY CONTRACTORS, L.L.C. (0.98) PANOLA SIGN & BARRICADE, INC. (0.12) SCOTT DERR PAINTING CO, LLC (0.03) STRIPING TECHNOLOGY, L.P. (2.28) INTERSTATE BARRICADES & MARKINGS, INC. (0.28) A&A TREE SERVICES (0.00) CARTHAGE DRILLING, INC. (0.03) SOUTHEAST GRINDING AND GROOVING LLC (0.01) STRAIGHT LINE SAWING & SEALING, INC. (0.05) KITECO PROPERTY SOLUTIONS INC. (0.17)
|
Contract # | 09223001 |
| Totals | 29546263.07 | 2331878.57 | 21932664.89 | 74.2 |
|
County | BOWIE |
Highway | US 259 |
From | 2.3 MI S OF FM 561 |
To | FM 561 |
CSJ | 0085-02-054 |
Proj ID | C 85-2-54 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.375 | 6010666.29 | | 3799727.78 | 63.2 |
County | BOWIE |
Highway | US 259 |
From | FM 561 |
To | 0.03 MI S OF CR 4243 |
CSJ | 0085-02-055 |
Proj ID | C 85-2-55 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.434 | 5477266.91 | | 3771607.73 | 68.8 |
County | BOWIE |
Highway | US 259 |
From | WARD CREEK |
To | 0.1 MI S OF CR 4243 |
CSJ | 0085-02-056 |
Proj ID | C 85-2-56 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 3.421 | 9488012.37 | | 7286969.68 | 76.8 |
Work Order | 03-06-24 |
Work Began | 04-15-24 |
Work Completed | |
Time Computed | 03-25-24 |
Contract Working Days | 276 |
Addl Days Granted | 32 |
Working Days Charged | 145 |
Percent Time Used | 47 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0085-02-054 MORRIS COUNTY CONTRACTORS, L.L.C. (1.43) PANOLA SIGN & BARRICADE, INC. (0.24) PROFESSIONAL TRAFFIC CONTROL LLC (0.02) STRIPING TECHNOLOGY, L.P. (1.12) SOUTHWEST ENVIRONMENT SERVICES LLC (0.39) WITHERS CONSTRUCTION, LLC (2.98) KITECO PROPERTY SOLUTIONS INC. (0.71)
|
Contract # | 02243005 |
| Totals | 20975945.57 | 2717039.49 | 14858305.19 | 70.8 |
|
County | BOWIE ETC |
Highway | FM 2735 ETC |
From | 8.3 MI. N. OF US 82 |
To | US 82 |
CSJ | 0085-03-017 |
Proj ID | STP 2021(299)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 58.345 | 1493307.90 | | 1490619.73 | 99.8 |
Work Order | 07-28-21 |
Work Began | 11-16-21 |
Work Completed | |
Time Computed | 08-30-21 |
Contract Working Days | 285 |
Addl Days Granted | 68 |
Working Days Charged | 348 |
Percent Time Used | 98 |
Contractor(s) |
HX FARMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0085-03-017 FLEX SUPPLY, LLC (1.67) H. V. CAVER, INC. (1.33) CLEANVAC ENVIRONMENTAL LLC (2.00)
|
Contract # | 06213026 |
| Totals | 1493307.90 | 36462.00 | 1490619.73 | 99.8 |
|
County | UPSHUR |
Highway | US 80 |
From | WOOD C/L |
To | 0.3 MI E OF SH 155N |
CSJ | 0096-03-075 |
Proj ID | F 2023(088) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.926 | 6277174.34 | | 6809445.57 | 99.9 |
Work Order | 10-11-22 |
Work Began | 03-23-23 |
Work Completed | |
Time Computed | 03-10-23 |
Contract Working Days | 162 |
Addl Days Granted | 4 |
Working Days Charged | 213 |
Percent Time Used | 128 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0096-03-075 COLD CREEK CONSTRUCTION, LTD (4.29) ISAACS CONSTRUCTION SERVICES LLC (2.06) MORRIS COUNTY CONTRACTORS, L.L.C. (1.66) SOUTHWEST ENVIRONMENT SERVICES LLC (0.88) PANOLA SIGN & BARRICADE, INC. (1.28) R & G CONSTRUCTION, LLC (17.73) REYNOLDS & KAY, LTD. (1.77) STRIPING TECHNOLOGY, L.P. (2.59) WEST TEXAS ROCK RESOURCES, LLC (0.31)
|
Contract # | 09223025 |
| Totals | 6277174.34 | 434.00 | 6809445.57 | 99.9 |
|
County | HARRISON |
Highway | US 80 |
From | GREGG C/L |
To | 0.1 MI. W. OF TOM BROWN PARKWAY |
CSJ | 0096-07-054 |
Proj ID | F 2B23(018) |
Work Type | OVERLAY |
|
| 6.742 | 6333886.66 | | 6005660.73 | 95.3 |
Work Order | 12-05-23 |
Work Began | 12-07-23 |
Work Completed | |
Time Computed | 12-07-23 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 155 |
Percent Time Used | 121 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0096-07-054 CAP RIVER LLC (1.82) DREWERY CONSTRUCTION COMPANY, INCORPORATED (4.61) ISAACS CONSTRUCTION SERVICES LLC (0.11) KENT TREE SERVICE LLC (4.19) MORRIS COUNTY CONTRACTORS, L.L.C. (0.21) PANOLA SIGN & BARRICADE, INC. (0.30) R & G CONSTRUCTION, LLC (4.03) SOUTHWEST ENVIRONMENT SERVICES LLC (1.47) STRIPING TECHNOLOGY, L.P. (5.33) REYNOLDS & KAY, LTD. (4.83) HIGHWAY 1 LLC (0.16)
|
Contract # | 08233011 |
| Totals | 6333886.66 | 110063.70 | 6005660.73 | 95.3 |
|
County | HARRISON |
Highway | US 80 |
From | 0.3 MI. E. OF FM 134 |
To | LOUISIANA S/L |
CSJ | 0096-10-028 |
Proj ID | F 2B24(109) |
Work Type | OVERLAY |
|
| 2.397 | 3801385.64 | | 3550329.91 | 93.3 |
Work Order | 08-01-24 |
Work Began | 09-18-24 |
Work Completed | |
Time Computed | 09-02-24 |
Contract Working Days | 47 |
Addl Days Granted | 0 |
Working Days Charged | 38 |
Percent Time Used | 80 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0096-10-028 PANOLA SIGN & BARRICADE, INC. (0.24) R & G CONSTRUCTION, LLC (1.38) SOUTHWEST ENVIRONMENT SERVICES LLC (1.36) STRIPING TECHNOLOGY, L.P. (2.29) WITHERS CONSTRUCTION, LLC (3.46) J. H. ODEN CONTRACTING COMPANY (0.26)
|
Contract # | 06243229 |
| Totals | 3801385.64 | 3259679.91 | 3550329.91 | 93.3 |
|
County | CASS ETC |
Highway | FM 248 ETC |
From | SH 43 |
To | MARION C/L |
CSJ | 0138-10-029 |
Proj ID | STP 2021(287)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 98.460 | 2714170.79 | | 3583252.07 | 99.9 |
Work Order | 05-20-21 |
Work Began | 07-06-21 |
Work Completed | |
Time Computed | 06-21-21 |
Contract Working Days | 304 |
Addl Days Granted | 145 |
Working Days Charged | 488 |
Percent Time Used | 108 |
Contractor(s) |
H. V. CAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0138-10-029 PANOLA SIGN & BARRICADE, INC. (1.19) SOUTHWEST ENVIRONMENT SERVICES LLC (1.90) JM YANEZ CONSTRUCTION, INC. (14.01) ISAACS CONSTRUCTION SERVICES LLC (1.21) CLEANVAC ENVIRONMENTAL LLC (0.73)
|
Contract # | 04213005 |
| Totals | 2714170.79 | 7921.25 | 3583252.07 | 99.9 |
|
County | BOWIE |
Highway | IH 369 |
From | IH 30 |
To | US 59 |
CSJ | 0218-02-055 |
Proj ID | F 2024(669) |
Work Type | OVERLAY |
|
| 3.523 | 10246641.10 | | 8968782.65 | 87.5 |
Work Order | 03-14-24 |
Work Began | 07-14-24 |
Work Completed | |
Time Computed | 04-15-24 |
Contract Working Days | 98 |
Addl Days Granted | 0 |
Working Days Charged | 63 |
Percent Time Used | 64 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0218-02-055 CHEROKEE SERVICES (1.42) KITECO PROPERTY SOLUTIONS INC. (1.42) MORRIS COUNTY CONTRACTORS, L.L.C. (0.43) PANOLA SIGN & BARRICADE, INC. (0.18) PROFESSIONAL TRAFFIC CONTROL LLC (0.07) STRIPING TECHNOLOGY, L.P. (1.08) TEXOP CONSTRUCTION (2.38) TIME STRIPING, INC. (0.06)
|
Contract # | 02243215 |
| Totals | 10246641.10 | 314380.80 | 8968782.65 | 87.5 |
|
County | CASS |
Highway | US 59 |
From | 0.1 MI S OF FM 2791 |
To | 0.1 MI S OF LOUISE STREET |
CSJ | 0218-03-086 |
Proj ID | C 218-3-86 |
Work Type | OVERLAY |
|
| 0.580 | 1923482.60 | | 795263.28 | 41.4 |
County | CASS |
Highway | US 59 |
From | 0.1 MI S OF LOUISE STREET |
To | 0.1 MI N OF FM 249 |
CSJ | 0218-04-117 |
Proj ID | C 218-4-117 |
Work Type | OVERLAY |
|
| 2.103 | 7650358.23 | | 2910618.48 | 38.0 |
Work Order | 03-07-24 |
Work Began | 08-08-24 |
Work Completed | |
Time Computed | 04-08-24 |
Contract Working Days | 93 |
Addl Days Granted | 0 |
Working Days Charged | 94 |
Percent Time Used | 101 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0218-03-086 BAHENA CONSTRUCTION CO.,INC. (1.43) DUSTIN ALLEN, INC. (0.41) PANOLA SIGN & BARRICADE, INC. (0.41) PROFESSIONAL TRAFFIC CONTROL LLC (0.08) SOUTHWEST ENVIRONMENT SERVICES LLC (2.12) TEXOP CONSTRUCTION (7.58) TRAFFIC HIGHWAY MAINTENANCE, LLC (1.93) WITHERS CONSTRUCTION, LLC (0.75)
|
Contract # | 02243210 |
| Totals | 9573840.83 | 1923604.32 | 3705881.76 | 38.7 |
|
County | CASS |
Highway | US 59 |
From | 0.2 MI N OF SL 236 (SOUTHBOUND ONLY) |
To | 0.5 MI S OF FM 3129 |
CSJ | 0218-03-094 |
Proj ID | C 218-3-94 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 6.400 | 7806580.01 | | 8870145.10 | 99.9 |
Work Order | 02-02-24 |
Work Began | 03-26-24 |
Work Completed | |
Time Computed | 03-04-24 |
Contract Working Days | 74 |
Addl Days Granted | 0 |
Working Days Charged | 68 |
Percent Time Used | 91 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0218-03-094 BAHENA CONSTRUCTION CO.,INC. (0.29) DUSTIN ALLEN, INC. (0.35) INDUSTRIAL FABRICS, INC. (0.21) O. TREVINO CONSTRUCTION, LLC (2.38) PANOLA SIGN & BARRICADE, INC. (0.38) STRIPING TECHNOLOGY, L.P. (3.47) SURFACE PREPARATION TECHNOLOGIES, LLC (0.13) SOUTHWEST ENVIRONMENT SERVICES LLC (1.30) TEXOP CONSTRUCTION (6.32) WITHERS CONSTRUCTION, LLC (2.53) ACT SAW CUTTING & REMOVAL (0.25) BRENDA PRICE TRUCKING, INC. (0.04) H. V. CAVER, INC. (0.04)
|
Contract # | 01243210 |
| Totals | 7806580.01 | 1052.48 | 8870145.10 | 99.9 |
|